GIPCL vs GUVNL

Case Number2003/2021
Date of Filing--
Case Type--
Last Hearing19 May 2026
State--
City--
Year of Filing2021

Party Details

Petitioner
  • Gujarat Industries Power Company Limited
Respondent
  • GUVNL

Case Summary

Gujarat Industries Power Company Limited filed Case No. 2003/2021 in the Gujarat Electricity Regulatory Commission against GUVNL. The case has undergone 6 hearings over 4 years and 2 months. The case is currently pending. 4 orders have been issued in this matter.

Hearing History (6)

  • 19MAY 2026
    Hearing

    Judge: N/A

    Petition under Section 86 of the Electricity Act, 2003 read with Article 9 of the Power Purchase Agreement dated 26.08.2019 executed between Gujarat Industries Power Company Limited and Gujarat Urja Vikas Nigam Limited seeking approval for compensation due to Change in Law Event being imposition of Safeguard Duty having its direct effect on the project cost.

  • 25AUG 2025
    Hearing

    Judge: N/A

    Petition under Section 86 of the Electricity Act, 2003 read with Article 9 of the Power Purchase Agreement dated 26.08.2019 executed between Gujarat Industries Power Company Limited and Gujarat Urja Vikas Nigam Limited seeking approval for compensation due to Change in Law Event being imposition of Safeguard Duty having its direct effect on the project cost.

  • 4JUL 2023
    Hearing

    Judge: N/A

    In the matter of Petition under Section 86 of the Electricity Act, 2003 read with Article 9 of the Power Purchase Agreement dated 26.08.2019 executed between Gujarat Industries Power Company Limited and Gujarat Urja Vikas Nigam Limited seeking approval for compensation due to Change in Law Event being imposition of Safeguard Duty having its direct effect on the project cost.

  • 31MAY 2023
    Hearing

    Judge: N/A

    In the matter of Petition under Section 86 of the Electricity Act, 2003 read with Article 9 of the Power Purchase Agreement dated 26.08.2019 executed between Gujarat Industries Power Company Limited and Gujarat Urja Vikas Nigam Limited seeking approval for compensation due to Change in Law Event being imposition of Safeguard Duty having its direct effect on the project cost.

  • 3NOV 2022
    Hearing

    Judge: N/A

    In the matter of Petition under Section 86 of the Electricity Act, 2003 read with Article 9 of the Power Purchase Agreement dated 26.08.2019 executed between Gujarat Industries Power Company Limited and Gujarat Urja Vikas Nigam Limited seeking approval for compensation due to Change in Law Event being imposition of Safeguard Duty having its direct effect on the project cost.

  • 8MAR 2022
    Hearing

    Judge: N/A

    In the matter of Petition under Section 86 of the Electricity Act, 2003 read with Article 9 of the Power Purchase Agreement dated 26.08.2019 executed between Gujarat Industries Power Company Limited and Gujarat Urja Vikas Nigam Limited seeking approval for compensation due to Change in Law Event being imposition of Safeguard Duty having its direct effect on the project cost.

Orders (4)