Case Summary

GUVNL filed Case No. 2434/2024 in the Gujarat Electricity Regulatory Commission against GSECL. The case has undergone 4 hearings over 7 months. The case is currently pending. 3 orders have been issued in this matter.

Hearing History (4)

  • 20JAN 2026
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (b) read with Section 62 of the Electricity Act, 2003 for approval of the Supplemental PPA dated 13.11.2024 for extension of PPA dated 22.01.1997 for 210 MW Unit 7 Wanakbori Thermal Power Station for further period up to 01.04.2030 or the actual useful life of the plant whichever is earlier.

  • 6OCT 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (b) read with Section 62 of the Electricity Act, 2003 for approval of the Supplemental PPA dated 13.11.2024 for extension of PPA dated 22.01.1997 for 210 MW Unit 7 Wanakbori Thermal Power Station for further period up to 01.04.2030 or the actual useful life of the plant whichever is earlier.

  • 19AUG 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (b) read with Section 62 of the Electricity Act, 2003 for approval of the Supplemental PPA dated 13.11.2024 for extension of PPA dated 22.01.1997 for 210 MW Unit 7 Wanakbori Thermal Power Station for further period up to 01.04.2030 or the actual useful life of the plant whichever is earlier.

  • 12JUN 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (b) read with Section 62 of the Electricity Act, 2003 for approval of the Supplemental PPA dated 13.11.2024 for extension of PPA dated 22.01.1997 for 210 MW Unit 7 Wanakbori Thermal Power Station for further period up to 01.04.2030 or the actual useful life of the plant whichever is earlier.

Orders (3)