N.R. Solar Park vs PGVCL
Party Details
- N.R. Solar Park
- PGVCL
Case Summary
N.R. Solar Park filed Case No. 2271/2023 in the Gujarat Electricity Regulatory Commission against PGVCL. The case has undergone 2 hearings over 1 year and 8 months. The case is currently pending. 1 order has been issued in this matter.
Hearing History (2)
- 26AUG 2025Hearing
Judge: N/A
Petition under Section 86 (1) (b) and (e) of the Electricity Act, 2003 for incorporating provision regarding “Change in Law” in the PPA to be executed by State DISCOMs with Project Developers under the Government of Gujarat’s “Policy for Development of Small Scale Distributed Solar Projects 2019” notified vide G.R. No. SLR/11/2019/51/B1 dated 06.03.2019 and approval of draft PPA”.
- 22DEC 2023Hearing
Judge: N/A
In the matter of Miscellaneous Petition under Section 86 (1) (b) and (e) of the Electricity Act, 2003 for incorporating provision regarding “Change in Law” in the PPA to be executed by State DISCOMs with Project Developers under the Government of Gujarat’s “Policy for Development of Small Scale Distributed Solar Projects 2019” notified vide G.R. No. SLR/11/2019/51/B1 dated 06.03.2019 and approval of draft PPA”.
Orders (1)
- 29DEC 2023orderView Order ↗
Order No: 1