Suzlon Energy Ltd. vs GETCO

Case Number2518/2025
Date of Filing--
Case Type--
Last Hearing26 Sept 2025
State--
City--
Year of Filing2025

Party Details

Petitioner
  • Suzlon Energy Limited
Respondent
  • GETCO

Case Summary

Suzlon Energy Limited filed Case No. 2518/2025 in the Gujarat Electricity Regulatory Commission against GETCO. The case has undergone 5 hearings over 1 month. The case is currently pending. 5 orders have been issued in this matter.

Hearing History (5)

  • 26SEP 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (f) of the Electricity Act, 2003 seeking quashing/setting aside the email dated 14.02.2025 and the letter dated 01.03.2025 issued by GETCO thereby illegally rejecting Stage – II connectivity application of the Petitioner qua the infrastructure being developed by it for evacuation of power from its 35 MW Wind Power Project to GETCO’s 66 KV Nadadhri Sub-station for extraneous reasons untenable in the eyes of law.

  • 22SEP 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (f) of the Electricity Act, 2003 seeking quashing/setting aside the email dated 14.02.2025 and the letter dated 01.03.2025 issued by GETCO thereby illegally rejecting Stage – II connectivity application of the Petitioner qua the infrastructure being developed by it for evacuation of power from its 35 MW Wind Power Project to GETCO’s 66 KV Nadadhri Sub-station for extraneous reasons untenable in the eyes of law.

  • 19SEP 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (f) of the Electricity Act, 2003 seeking quashing/setting aside the email dated 14.02.2025 and the letter dated 01.03.2025 issued by GETCO thereby illegally rejecting Stage – II connectivity application of the Petitioner qua the infrastructure being developed by it for evacuation of power from its 35 MW Wind Power Project to GETCO’s 66 KV Nadadhri Sub-station for extraneous reasons untenable in the eyes of law.

  • 31JUL 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (f) of the Electricity Act, 2003 seeking quashing/setting aside the email dated 14.02.2025 and the letter dated 01.03.2025 issued by GETCO thereby illegally rejecting Stage – II connectivity application of the Petitioner qua the infrastructure being developed by it for evacuation of power from its 35 MW Wind Power Project to GETCO’s 66 KV Nadadhri Sub-station for extraneous reasons untenable in the eyes of law.

  • 29JUL 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (f) of the Electricity Act, 2003 seeking quashing/setting aside the email dated 14.02.2025 and the letter dated 01.03.2025 issued by GETCO thereby illegally rejecting Stage – II connectivity application of the Petitioner qua the infrastructure being developed by it for evacuation of power from its 35 MW Wind Power Project to GETCO’s 66 KV Nadadhri Sub-station for extraneous reasons untenable in the eyes of law.

Orders (5)