GUVNL & Ors vs

Case NumberOrder No. 05/2024
Date of Filing--
Case Type--
Last Hearing19 Sept 2025
State--
City--
Year of Filing2024

Party Details

Petitioner
  • Suzlon Global Services Limited
Respondent
  • SLDC

Case Summary

Suzlon Global Services Limited filed Case No. Order No. 05/2024 in the Gujarat Electricity Regulatory Commission against SLDC. The case has undergone 10 hearings over 9 months. The case is currently pending. 10 orders have been issued in this matter.

Hearing History (10)

  • 19SEP 2025
    Hearing

    Judge: N/A

    Review Petition under Regulation 72 (1) of GERC (Conduct of Business) Regulations, 2004 notified vide Notification No. 02/2004 against the Wind Tariff Order No. 05/2024 of the Commission regarding “Tariff Framework for Procurement of Power by Distribution Licensees and others from Wind Power Projects for State of Gujarat, and clarification regarding control period effective date.

  • 19SEP 2025
    Hearing

    Judge: N/A

    As per the Hon’ble APTEL’s Judgement dated 03.07.2025 in (i) Appeal No. 06 of 2025 & IA No. 1887 of 2024, (ii) Appeal No. 07 of 2025 & IA No. 1876 of 2024, (iii) Appeal No. 38 of 2025 & IAs No. 1903 of 2024 & 547 of 2025, (iv) Appeal No. 79 of 2025 & IA No. 2001 of 2024 and (v) Appeal No. 164 of 2025 & IA No. 08 of 2025, schedule the hearing in Order No. 05 of 2024 - in the matter of Tariff Framework for Procurement of Power by Distribution licensees and Others from Wind Power Projects for State of Gujarat.

  • 19AUG 2025
    Hearing

    Judge: N/A

    As per the Hon’ble APTEL’s Judgement dated 03.07.2025 in (i) Appeal No. 06 of 2025 & IA No. 1887 of 2024, (ii) Appeal No. 07 of 2025 & IA No. 1876 of 2024, (iii) Appeal No. 38 of 2025 & IAs No. 1903 of 2024 & 547 of 2025 and (iv) Appeal No. 79 of 2025 & IA No. 2001 of 2024, schedule the hearing in Order No. 05 of 2024 - in the matter of Tariff Framework for Procurement of Power by Distribution licensees and Others from Wind Power Projects for State of Gujarat.

  • 17JUL 2025
    Hearing

    Judge: N/A

    Petition under Section 86 of EA, 2003 read with Order No. 05/2024 dated 31.08.2024 “Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind Power Projects for the State of Gujarat” passed by the Commission seeking extension of Scheduled Date of Commissioning (SCOD) of infrastructure being developed by the Petitioner for evacuation of power form its 200 MW wind farm located at Jamjodhpur to 220 kV Kalawad sub-station of Respondent/ GETCO, on account of occurrence of Force Majeure events.

  • 10JUL 2025
    Hearing

    Judge: N/A

    Petition under Section 86 of EA, 2003 read with Order No. 05/2024 dated 31.08.2024 “Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind Power Projects for the State of Gujarat” passed by the Commission seeking extension of Scheduled Date of Commissioning (SCOD) of infrastructure being developed by the Petitioner for evacuation of power form its 200 MW wind farm.

  • 29MAY 2025
    Hearing

    Judge: N/A

    Petition under Section 86 of EA, 2003 read with Order No. 05/2024 dated 31.08.2024 “Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind Power Projects for the State of Gujarat” passed by the Commission seeking extension of Scheduled Date of Commissioning (SCOD) of infrastructure being developed by the Petitioner for evacuation of power form its 200 MW wind farm located at Jamjodhpur to 220 kV Kalawad sub-station of Respondent/ GETCO, on account of occurrence of Force Majeure events.

  • 28MAY 2025
    Hearing

    Judge: N/A

    Petition to devise a mechanism to implement the Commission’s Tariff Order No. 05 of 2024 dated 31.08.2024 by relaxing the requirement to install Remote Terminal Unit at each Wind Turbine Generator in the State of Gujarat.

  • 5FEB 2025
    Hearing

    Judge: N/A

    Petition under Section 86 of EA, 2003 read with Order No. 05/2024 dated 31.08.2024 “Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind Power Projects for the State of Gujarat” passed by the Commission seeking extension of Scheduled Date of Commissioning (SCOD) of infrastructure being developed by the Petitioner for evacuation of power form its 200 MW wind farm located at Jamjodhpur to 220 kV Kalawad sub-station of Respondent/ GETCO, on account of occurrence of Force Majeure events.

  • 18DEC 2024
    Hearing

    Judge: N/A

    Petition under Section 86 of EA, 2003 read with Order No. 05/2024 dated 31.08.2024 “Tariff Framework for Procurement of Power by l Distribution Licensees and Others from Wind Power Projects for the State of Gujarat” passed by the Commission seeking extension of Scheduled Date of Commissioning (SCOD) of infrastructure being developed by the Petitioner for evacuation of power form its 200 MW wind farm located at Jamjodhpur to 220 kV Kalawad sub-station of Respondent/GETCO, on account of occurrence of Force Majeure events

  • 4DEC 2024
    Hearing

    Judge: N/A

    In the matter of Petition to devise a mechanism to implement the Commission’s Tariff Order No. 05 of 2024 dated 31.08.2024 by relaxing the requirement to install Remote Terminal Unit at each Wind Turbine Generator in the State of Gujarat.