Torrent Power Ltd. vs Adani Renewable Energy Eight Ltd. & Torrent Saurya Urja 2 Pvt. Ltd.
Party Details
- TPL
- Adani Renewable Energy Eight Limited & Others
Case Summary
TPL filed Case No. 2053/2022 in the Gujarat Electricity Regulatory Commission against Adani Renewable Energy Eight Limited & Others. The case has undergone 5 hearings over 2 years and 8 months. The case is currently pending. 4 orders have been issued in this matter.
Hearing History (5)
- 26AUG 2025Hearing
Judge: N/A
Petition under Section 86 (1) (b) of the Electricity Act, 2003 read with Article 9 of the Power Purchase Agreement dated 12.05.2021 executed between Torrent Power Limited (Distribution) and Adani Renewable Energy Eight Limited and Power Purchase Agreement dated 12.05.2021 executed between Torrent Power Limited (Distribution) and Torrent Saurya Urja 2 Pvt. Limited for adjustment in tariff under the claim of Change in Law.
- 11SEP 2024Hearing
Judge: N/A
Petition under Section 86 (1) (b) of the Electricity Act, 2003 read with Article 9 of the Power Purchase Agreement dated 12.05.2021 executed between Torrent Power Limited (Distribution) and Adani Renewable Energy Eight Limited and Power Purchase Agreement dated 12.05.2021 executed between Torrent Power Limited (Distribution) and Torrent Saurya Urja 2 Pvt. Limited for adjustment in tariff under the claim of Change in Law.
- 4OCT 2023Hearing
Judge: N/A
Petition under Section 86 (1) (b) of the Electricity Act, 2003 read with Article 9 of the Power Purchase Agreement dated 12.05.2021 executed between Torrent Power Limited (Distribution) and Adani Renewable Energy Eight Limited and Power Purchase Agreement dated 12.05.2021 executed between Torrent Power Limited (Distribution) and Torrent Saurya Urja 2 Pvt. Limited for adjustment in tariff under the claim of Change in Law.
Orders (4)
- 4SEP 2025orderView Order ↗
Order No: 1
- 17DEC 2024orderView Order ↗
Order No: 2
- 18OCT 2023orderView Order ↗
Order No: 3