Durga Processors Pvt. Limited vs GETCO & Ors.
Party Details
- Durga Processors Pvt. Limited
- GETCO & Ors.
Case Summary
Durga Processors Pvt. Limited filed Case No. 2438/2025 in the Gujarat Electricity Regulatory Commission against GETCO & Ors.. The case has undergone 5 hearings over 9 months. The case is currently pending. 5 orders have been issued in this matter.
Hearing History (5)
- 26FEB 2026Hearing
Judge: N/A
Petition under Section 86 of EA, 2003 read with Regulations 80 & 82 of GERC (Conduct of Business) Regulations, 2004 read with Gujarat Renewable Energy Policy, 2023 and Amendments thereof and Tariff Order dated 31.08.2024 praying to exercise its powers under Section 86 of the Electricity Act, 2003 and direct the Respondent GETCO to grant extension of time for commissioning of the Evacuation Line along with bays and metering system of 4.15 MW Solar–Wind Hybrid Project.
- 19AUG 2025Hearing
Judge: N/A
Petition under Section 86 of the Electricity Act, 2003 read with Regulations 80 and 82 of GERC (Conduct of Business) Regulations, 2004 read with Gujarat Renewable Energy Policy, 2023 and Amendments thereof and Tariff Order dated 31.08.2024 praying to exercise its powers under Section 86 of the Electricity Act, 2003 and direct the Respondent GETCO to grant extension of time for commissioning of the Evacuation Line along with bays and metering system of the 4.15 MW Solar – Wind Hybrid Project.
- 17JUL 2025Hearing
Judge: N/A
Petition under Section 86 of the Electricity Act, 2003 read with Regulations 80 and 82 of GERC (Conduct of Business) Regulations, 2004 read with Gujarat Renewable Energy Policy, 2023 and Amendments thereof and Tariff Order dated 31.08.2024 praying to exercise its powers under Section 86 of the Electricity Act, 2003 and direct the Respondent GETCO to grant extension of time
Orders (5)
- 5MAR 2026orderView Order ↗
Order No: 1
- 4SEP 2025orderView Order ↗
Order No: 1
- 2AUG 2025orderView Order ↗
Order No: 2