SURENDRA SINGH SHEKHAWAT vs STATE OF RAJASTHAN
Party Details
- SURENDRA SINGH SHEKHAWAT
- STATE OF RAJASTHAN
Case Summary
SURENDRA SINGH SHEKHAWAT filed Case No. Execution Application No. 9/2023 in the National Green Tribunal on 23 Sept 2023 against STATE OF RAJASTHAN. The case has undergone 12 hearings over 1 year and 10 months. The case is currently pending. 12 orders have been issued in this matter.
Hearing History (12)
- 10SEP 2025Hearing
Judge: Mr. Justice Sheo Kumar SinghMr. Sudhir Kumar Chaturvedi
- 27MAY 2025Hearing
Judge: Mr. Justice Sheo Kumar SinghMr. Sudhir Kumar Chaturvedi
- 20MAR 2025Hearing
Judge: Mr. Justice Sheo Kumar Singh Dr. Afroz Ahmad
Orders (12)
- 10NOV 2025judgementView Order ↗
Order No: 12
- 10SEP 2025orderView Order ↗
Order No: 11
- 27MAY 2025orderView Order ↗
Order No: 10
Judgement DetailsView full order PDF ↗
1 E.A.
No.09/2023(CZ) Surendra Singh Shekhawat Vs.
State of Rajasthan & Ors.
Item No.07 BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONE BENCH, BHOPAL (Through Video Conferencing) Execution Application No.09/2023(CZ) In Original Application No.63/2023(CZ) Surendra Singh Shekhawat Applicant(s) Vs.
Respondent(s) Date of Hearing: 10.11.2025 CORAM: HON’BLE MR.
JUSTICE SHEO KUMAR SINGH, JUDICIAL MEMBER HON'BLE MR.
SUDHIR KUMAR CHATURVEDI, EXPERT MEMBER For Applicant (s): None.
For Respondent(s) : Mr.
Rishabh Kumar, Adv. for State of Rajasthan (for Mr.
Shoeb Hasan Khan, Adv.) Mr.
Rajeev Acharya, Adv. for MoEF&CC (for Dr.
Sapna Aggarwal, Adv.) Mr.
Rohit Sharma, Adv. for R-3 Mr.
Yadvendra Yadav, Adv. for R-7 ORDER 1.
Learned counsel for the respondent - State PCB Mr.
Rohit Sharma has submitted that aggrieved by the order and Civil Appeal has been field before the Hon’ble Supreme Court of India as Civil Appeal No.7607/2023 and the Hon’ble Supreme Court vide order dated 16.05.2025 passed the order as follows :- “ORDER We have perused the affidavit filed on behalf of the We petitioner/State in compliance with the order dated 7th April, 2025 as well as the counter affidavit filed by the first respondent. have also perused the report of the CSRI-National Environmental Engineering Research Institute (NEERI).
As regards the proposal for creation of two wetlands, we direct the 2 E.A.
State to implement the project of creating two wetlands under the supervision of the NEERI in terms of the report submitted by the NEERI.
It is pointed out that the food court has been completely demolished.
As regards removal of seven wonders structures, we have already granted time till 17th September, 2025.
We direct the petitioner/State to file a further affidavit as regards the progress made in the work in relation to the two wetlands which are referred above by the end of July 2025.
July 2025.
List on 4th August, 2025.’’ 2.
Since the matter is pending before the Hon’ble Supreme Court thus, filing an application of execution is being premature.
The Execution Application stands disposed of and matter shall be taken up/decided/implemented in accordance with the order of the Hon’ble Supreme Court of India.
Applicant is at liberty to file afresh execution application after the order of the Hon’ble Supreme Court of India.
3.
The Execution Application No.
09/2023(CZ) stands disposed of accordingly.
Sheo Kumar Singh, JM Sudhir Kumar Chaturvedi, EM 10th November, 2025 EA No.09/2023(CZ) in OA No.63/2023(CZ) PN