NA MESCOM vs Beta Wind Farm Private Limited

Case NumberRP/8/2024
Date of Filing6 Nov 2024
Case TypeReview Petition
Last Hearing22 Apr 2025
StateKarnataka
CityBengaluru
Year of Filing2024

Party Details

Petitioner
  • MESCOM v. M/s. Beta Wind Farm Pvt. Ltd.
Respondent
  • BETA WIND FARM PRIVATE LIMITED NOT APPLICABLE NAPNOT APPLICABLENOT APPLICABLEBASCON FUTURA SV 4TH FLOOR NO10 1 VENKATANARAYANA ROAD TNAGAR CHENNAI TAMIL NADU INDIA

Case Summary

MESCOM v. M/s. Beta Wind Farm Pvt. Ltd. filed Case No. RP/8/2024 in the Karnataka Electricity Regulatory Commision on 6 Nov 2024 against BETA WIND FARM PRIVATE LIMITED NOT APPLICABLE NAPNOT APPLICABLENOT APPLICABLEBASCON FUTURA SV 4TH FLOOR NO10 1 VENKATANARAYANA ROAD TNAGAR CHENNAI TAMIL NADU INDIA. The case has undergone 6 hearings over 4 months. The case is currently pending.

Hearing History (6)

  • 22APR 2025
    Order is pronounced on 22.04.2025. Parties be intimated. Registry is directed to upload the copy of this order on website of KERC.

    Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)

    Stage: FOR PRONOUNCEMENT OF ORDERS

  • 8APR 2025
    Case called for hearing on 08.04.2025. Counsel for petitioner Sri. Shahbaaz Husain for Precinct Legal present. Counsel for Respondent Ms. Janani Shankar for MSA Partners present. Both counsels made their respective arguments on the merits of the case and concluded. Commission heard both the counsels and reserved the case for orders.

    Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)

    Stage: FOR HEARING

  • 11MAR 2025
    Case called for hearing on 11.03.2025. Counsel for petitioner Sri. K. Sumanth Gowda for Precinct Legal present and prays to hear the matter before the full Bench. Counsel Ms. Aishwarya Subramani for MSA Partners appeared for Respondent, filed xerox copies of vakalath along with reply with a copy to petitioner. Further undertakes to file original reply & vakalath within three days’ time. Commission heard both the counsels. Granted time for Respondent to file original reply and vakalath in the registry. Call on 08.04.2025.

    Judge: Single Member Bench - HKJ(L)

    Stage: FOR APPEARANCE OF RESPONDENT(S)

  • 21JAN 2025
    Case called for hearing on admission on 21.01.2025. Counsel Ms. Stephania Pinto for Precinct Legal present, made submissions for review of Commission Order dated 13.08.2024 in OP No. 01/2024 for review of 75% of the generic tariff instead of 85% for the energy injected during non-existence of W&B Agreement by placing on record relevant W&BA Clauses to substantiate the claim and prays to admit the case. Commission heard the counsel, noted the submissions, perused the WBA agreements, admitted the petition and directed the registry to issue notice to the Respondent. Call on 11.03.2025.

    Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)

    Stage: FOR HEARING ON ADMISSION

  • 10DEC 2024
    Case called for hearing on admission on 10.12.2024. Counsel Ms. Devika Ganesh for Precinct Legal present, filed relevant Wheeling & Banking Agreements to substantiate the claim for Review of commission order dated 13.08.2024 in OP No. 01/2024 for granting 75% of the generic tariff instead of 85% for the energy injected during the non-subsistence of WBA and prays for to argue on admission. Commission heard the counsel, granted time. Call on 21.01.2025.

    Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)

    Stage: FOR HEARING ON ADMISSION

  • 3DEC 2024
    Case called for admission on 03.12.2024. Counsel for petitioner Ms. Stephania Pinto for Precinct Legal present, made submissions for review of the order dated 13.08.2024 in OP No. 01/2024 in view of inadvertent error in the said order in granting 85% of the generic tariff instead of 75% during the subsistence of WBA as per norms and prays to admit the review petition. Commission heard the counsel, noted that since the review petition is to be heard by full bench, the case is adjourned for hearing on admission by full bench on 10.12.2024.

    Judge: Single Member Bench - JA(M)