CNR: --
PENDING
NA RK Powergen Private Limited vs Bangalore Electricity Supply Company
Case NumberOP/1/2026
Date of Filing24 Dec 2025
Case TypeOriginal Petition
Last Hearing--
StateKarnataka
CityBengaluru
Year of Filing--
Party Details
Petitioner
- RK POWERGEN PRIVATE LIMITED NO 14
- DR GIRIAPPA ROAD
- T NAGARCHENNAI- 600 017
Respondent
- BANGALORE ELECTRICITY SUPPLY COMPANY CORPORATE OFFICE
- K.R CIRCLEBENGALURU- 560 001 560001
Case Summary
NA RK Powergen Private Limited vs Bangalore Electricity Supply Company (Case No. OP/1/2026) is listed in the Karnataka Electricity Regulatory Commision, filed on 24 Dec 2025. The case has undergone 4 hearings over 2 months. The case is currently pending.
Hearing History (4)
28APR 2026
Case called for hearing on 28.04.2026. Counsel for Petitioner Sri. Shridhar Prabhu for Navayana Law Offices present. Counsel for R-1 to R-3 Sri. Sumanth K. Gowda for Precinct Legal present and filed statement of objections with a copy to Petitioner. Both counsels addressed their respective arguments on merits of the case and concluded. Commission having heard the arguments of both counsels reserved the case for orders.
Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)
Stage: FOR STATEMENT OF OBJECTIONS
21APR 2026
Case called for hearing on 21.04.2026. Counsel for petitioner Sri. Shridhar Prabhu for Navayana Law Offices present. Counsel for R-1 to R-3 Ms. Stephania Pinto for Precinct Legal present, undertakes to file vakalath for R-1 & R-2 and prays for a weeks’ time to file statement of objections. Commission having heard the counsels, granted time for respondents to file statement of objections with a copy to petitioner. Call on 28.04.2026.
Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)
Stage: FOR APPEARANCE OF RESPONDENT(S) AND OBJECTIONS
17MAR 2026
Case called for hearing on 17.03.2026. Counsel for petitioner Ms. Aishwarya Chandran for Navanaya Law Officers present through video conferencing. Counsel Ms. Stepahia Pinto for Precinct Legal present, submits that vakalath for R-3 (KPTCL) is filed in the registry on 16.03.2026 and prays for time to file statement of objections. Further, undertook to file vakalth for R-1 & R-2 (BESCOM) after receiving instructions. Commission heard the counsel, granted time to file vakalth for R1 & R2 and statement of objections of R-3. Call on 21.04.2026.
Judge: Two Members Bench - HKJ(L)+JA(M)
Stage: FOR APPEARANCE OF RESPONDENT(S)
Similar Cases
⚖️⚖️⚖️⚖️⚖️
Mrs Mangalore Electricity Supply Company LtdMESCOM vs Nil
Mr MAHADEVA vs NIL
NA Gulbarga Electricity Supply Company Limited vs Karnataka Electricity Regulatory Commission Bengaluru
Mr CHAMUNDESHWARI ELECTRICITY SUPPLY CORPORATION LIMITED vs nil
Ms SOLITAIRE POWERTECH PRIVATE LIMITED vs KARNATAKA POWER TRANSMISSION CORPORATION LIMITED