CNR: --
PENDING

Ms Wardha Solar Maharashtra Private Ltd vs Karnataka State Load Dispatch Centre

Case NumberOP/30/2024
Date of Filing26 Sept 2024
Case TypeOriginal Petition
Last Hearing21 Apr 2026
StateKarnataka
CityBengaluru
Year of Filing2024

Party Details

Petitioner
  • MS WARDHA SOLAR MAHARASHTRA PRIVATE LTDC/o AGM AGED ABOUT 43 YEARSNot ApplicableNOT APPLICABLEADANI CORPORATE HOUSE
  • NEAR VAISHNODEVI CIRCLE
  • SHANTIGRAM
  • KHODIYAR
  • AHMEDABAD- 382330
  • GUJARAT. 382330
Respondent
  • MS PARAMPUJYA SOLAR ENERGY PRIVATE LTDAGED ABOUT 43 YEARSNot ApplicableNOT APPLICABLEADANI CORPORATE HOUSE
  • NEAR VAISHNODEVI CIRCLE
  • SHANTIGRAM
  • KHODIYAR
  • AHMEDABAD- 382330
  • GUJARAT. 382330

Case Summary

MS WARDHA SOLAR MAHARASHTRA PRIVATE LTDC/o AGM AGED ABOUT 43 YEARSNot ApplicableNOT APPLICABLEADANI CORPORATE HOUSE and NEAR VAISHNODEVI CIRCLE filed Case No. OP/30/2024 in the Karnataka Electricity Regulatory Commision on 26 Sept 2024 against MS PARAMPUJYA SOLAR ENERGY PRIVATE LTDAGED ABOUT 43 YEARSNot ApplicableNOT APPLICABLEADANI CORPORATE HOUSE and NEAR VAISHNODEVI CIRCLE. The case has undergone 7 hearings over 1 year and 3 months. The case is currently pending.

Hearing History (7)

  • 21APR 2026
    Case called for hearing on 21.04.2026. Counsel for petitioner Ms. Sakshi Kapur for J. Sagar Associates present through video conferencing and submits that rejoinder is filed with a copy to respondents and ready to address arguments. Counsel for R-1 & R-4 Sri. Sumanth K. Gowda for Precinct Legal present and prays time to address arguments. Commission having noted the submissions of the counsels, for R-1 & R-4 granted time to address arguments. For arguments, call on 02.06.2026.

    Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)

    Stage: FOR REJOINDER

  • 24MAR 2026
    Case called for hearing on 24.03.2026. Counsel for petitioner Ms. Sakshi Kapoor for JSA Advocates present through video conferencing and prays two weeks’ time to file rejoinder. Counsel for R-1 & R-4 Ms. Stephania Pinto for Precinct Legal present and submits that statement of objections is filed in the registry on 10.03.2026. Commission having noted the submissions of the counsels, granted time to petitioner to file rejoinder. Call on 21.04.2026.

    Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)

    Stage: FOR APPEARANCE OF RESPONDENT(S) AND OBJECTIONS

  • 24FEB 2026
    Case called for hearing on 24.02.2026. Counsel for petitioner Ms. Sakshi Kapoor for JSA Advocates and Solicitors present through video conferencing. Counsel for R-1 & R-4 Sri. Sumanth K. Gowda for Precinct Legal present prays one weeks’ time for filing statement of objections. Petitioner counsel prays two weeks’ time to file rejoinder after receipt of objections. No representation for R-2 & R-5. Commission heard the counsels, noted the submissions and granted time for R-1 & R-4 to file objections on or before 03.03.2026 with a copy to petitioner for filing rejoinder within two weeks thereafter. Call on 24.03.2026.

    Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)

    Stage: FOR STATEMENT OF OBJECTIONS

  • 20JAN 2026
    Case called for hearing on 20.01.2026. Counsel Ms. Sakshi Kapoor for JSA Advocates & Solicitors appeared for petitioners through video conferencing, made submissions that the petitioners are seeking relief against respondents No. 1 & 2 for loss of generation. Further, submits that since the relief of must run status has been sought, MNRE is made as a formal party as per regulations. Counsel Ms. Stephania Pinto for Precinct Legal present for R-4 (KPTCL) and undertakes to seek instructions to file vakalth for R-1 (SLDC) and prays four weeks’ time to file statement of objections. Notice issued to R-2 (SECI) returned back as addressee left. Sri. Nadim Ahmed, General Manager, Grid India, SRLDC present for R-5. Petitioner counsel prays for time to file rejoinder after receipt of statement of objections. Commission heard the counsels, noted their submissions, directed the counsel for R-1 and R-4 to furnish the copy of Statement of objections on R-5 to file their response / reply. Granted time to R-1 and R-4 to file statement of objections with a copy to petitioner for filing rejoinder within a week thereafter. Call on 24.02.2026.

    Judge: Two Members Bench - PRK(C)+HKJ(L)

    Stage: FOR APPEARANCE OF RESPONDENT(S) AND OBJECTIONS

  • 16DEC 2025
    Case scheduled for hearing on 02.12.2025 is rescheduled and the same is called for hearing on 16.12.2025. Counsel for petitioner Ms. Saakshi Kapoor for JSA Advocates & Solicitors appeared through video conferencing. Counsel Sri. Sumanth K. Gowda for Precinct Legal present, submits that Vakalath is filed for R-4 (KPTCL), undertakes to seek instructions for filing vakalath for R-1 (SLDC). R-2, R-3 & R-5 not represented despite service of notice. Commission heard the counsels and sought clarification on the role of MNRE i.e., 3rd respondent and necessity of making them as a party to this petition since there is no allegations and relief being sought against MNRE. The petitioner advocate submits that since the relief sought is for Must Rum status of the plant, MNRE has been made as respondent and further undertook to verify the same and to take necessary steps on the requirement of MNRE as respondent. Heard, the Commission directed the registry to issue one more notice to R-2 & R-5 besides directing the R-1 & R4 to file statement of objections with a copy to petitioner. Call on 20.01.2026.

    Judge: Two Members Bench - HKJ(L)+JA(M)

    Stage: FOR APPEARANCE OF RESPONDENT(S)

  • 23SEP 2025
    Case called for hearing on admission on 23.09.2025. Counsel for petitioner Ms. Sakshi Kapoor for JSA Advocates & Solicitors along with Sri. Dipak Panchal, DGM, Ms. Wardha Solar Private Limited present. Counsel for petitioner submits that they have complied the directions of this Commission issued on 07.01.2025 and quantified the amount for generation loss, paid the court fee on the quantified amount and amended petition was filed in the registry in this regard and prays to admit the petition. Commission heard the petitioner counsel, perused the documents and admitted the petition and directed the registry to issue notice to the respondents. Call on 02.12.2025.

    Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)

    Stage: FOR HEARING ON ADMISSION

  • 7JAN 2025
    Case called for admission on 07.01.2025. Counsel Ms. Saakshi Kapur for petitioner and Party-in-person Sri. Deepak Panchal present, made submissions to enforce ‘must run’ status granted to the solar power projects, direct SLDC to stop issuing instructions to back down the solar power generated from the petitioners’ project, and to pay for loss of generation to the extent of Rs. 84.32 crores as per para 25 of the petition. Further submits that the present petition is being filed in the background of the orders of Hon’ble High Court of Karnataka dated 11.06.2024, Hon’ble APTEL Judgement dated 02.08.2021 read with POSOCO Report, Commission order dated 19.12.2023 in OP No. 20/2019 where the orders are supportive in favour of the petitioner and hence, prays to admit the petition subject to payment of court fee at a later date since the methodology for estimating the charges are yet to be approved the Commission. Commission heard the counsel and party-in-person, noted the submissions alongside with the orders cited above and expressed its view that since, no specific claim for quantification of loss of energy commensurate with exact compensation is forthcoming in the prayer, directed the petitioner to quantify the same along with payment of court fee as per KERC(fee) Regulations and to file amendment application to the effect. Commission also noted that no specific directions for curtailment from competent authority are available in the petition. Petitioner counsel prays 30 days’ time to comply. Time granted. Next date of hearing will be intimated after receipt of compliance.

    Judge: Full Bench - PRK(C)+HKJ(L)+JA(M)

    Stage: FOR ADMISSION