Enerpare Solar Power 9 Pvt. Limited vs GETCO
Case Number2570/2025
Date of Filing--
Case Type--
Last Hearing26 Feb 2026
StateGujarat
CityGandhinagar
Year of Filing2025
Party Details
Petitioner
- Enerpare Solar Power 9 Pvt. Limited
Respondent
- GETCO
Case Summary
Enerpare Solar Power 9 Pvt. Limited filed Case No. 2570/2025 in the Gujarat Electricity Regulatory Commission against GETCO. The case has had one hearing so far. The case is currently pending. 1 order has been issued in this matter.
Hearing History (1)
- 26FEB 2026Hearing
Judge: N/A
Petition under Section 86 (1) (c) (e) & (f) & and other applicable provisions of the Electricity Act, 2003 read with read with Clause 3.9 of the GERC Order No. 06 of 2024 dated 31.08.2024 seeking extension of time period of 120 days for the commissioning of 25 MW Solar Power Plant and evacuation infrastructure due to occurrence of unforeseen events.
Orders (1)
- 6MAR 2026orderView Order ↗
Order No: 1