Meta Pixel
CNR: --
PENDING

GUVNL vs

Case Number1906/2020
Date of Filing--
Case Type--
Last Hearing23 Apr 2026
StateGujarat
CityGandhinagar
Year of Filing2020

Party Details

Petitioner
  • Gujarat Urja Vikas Nigam Limited

Case Summary

Gujarat Urja Vikas Nigam Limited filed Case No. 1906/2020 in the Gujarat Electricity Regulatory Commission. The case has undergone 11 hearings over 5 years and 3 months. The case is currently pending. 11 orders have been issued in this matter.

Hearing History (11)

  • 23APR 2026
    Hearing

    Judge: N/A

    Petition under Section 63 read with Section 86 (1) (b) of the Electricity Act, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

  • 13OCT 2025
    Hearing

    Judge: N/A

    Petition under Section 63 read with Section 86 (1) (b) of the Electricity Act, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

  • 17APR 2025
    Hearing

    Judge: N/A

    Petition under Section 63 read with Section 86 (1) (b) of the Electricity Act, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

  • 15OCT 2024
    Hearing

    Judge: N/A

    Petition under Section 63 read with Section 86 (1) (b) of the Electricity Act, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

  • 26SEP 2024
    Hearing

    Judge: N/A

    Petition under Section 63 read with Section 86 (1) (b) of the Electricity Act, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

  • 2MAR 2024
    Hearing

    Judge: N/A

    In the matter of Petition under Section 63 read with Section 86 (1) (b) of the EA, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

  • 28FEB 2024
    Hearing

    Judge: N/A

    In the matter of Petition under Section 63 read with Section 86 (1) (b) of the EA, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

  • 23JAN 2024
    Hearing

    Judge: N/A

    In the matter of Petition under Section 63 read with Section 86 (1) (b) of the EA, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

  • 28DEC 2023
    Hearing

    Judge: N/A

    In the matter of Petition under Section 63 read with Section 86 (1) (b) of the EA, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

  • 28JAN 2021
    Hearing

    Judge: N/A

    In the matter of Petition under Section 63 read with Section 86 (1) (b) of the EA, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

  • 29DEC 2020
    Hearing

    Judge: N/A

    In the matter of Petition under Section 63 read with Section 86 (1) (b) of the EA, 2003 seeking adoption of tariff discovered under Competitive Bidding process for procurement of power from 700 MW Solar PV Projects to be set up in 1000 MW Dholera Solar Park in Gujarat through RFS dated 18.03.2020 (Phase IX).

Orders (11)