Panara Craft LLP vs DGVCL & Others

Case Number2488/2025
Date of Filing--
Case Type--
Last Hearing26 Feb 2026
State--
City--
Year of Filing2025

Party Details

Petitioner
  • Panara Craft LLP
Respondent
  • DGVCL & Others

Case Summary

Panara Craft LLP filed Case No. 2488/2025 in the Gujarat Electricity Regulatory Commission against DGVCL & Others. The case has undergone 5 hearings over 7 months. The case is currently pending. 6 orders have been issued in this matter.

Hearing History (5)

  • 26FEB 2026
    Hearing

    Judge: N/A

    Petition under Sections 86 (1) (c) (e) and (f) of EA, 2003 and as per Clause 3.9 of Order No. 06 of 2024 dated 31.08.2024 for extension of date of grid connectivity and commissioning in respect of 7.8 MW solar plant for captive use due to occurnance of uncontrollable events.

  • 4OCT 2025
    Hearing

    Judge: N/A

    Petition under Sections 86 (1) (c) (e) and (f) of Electricity Act, 2003 and as per Clause 3.9 of GERC Order No.06 of 2024 dated 31.08.2024 for extension of date of grid connectivity and commissioning in respect of 7.8 MW solar plant for captive use due to occurnance of uncontrollable events.

  • 24JUL 2025
    Hearing

    Judge: N/A

    In the matter of Petition under Sections 86 (1) (c) (e) and (f) of Electricity Act, 2003 and as per Clause 3.9 of GERC Order No. 06 of 2024 dated 31.08.2024 for extension of date of grid connectivity and commissioning in respect of 7.8 MW solar plant for captive use due to occurnance of uncontrollable events.

  • 10JUL 2025
    Hearing

    Judge: N/A

    In the matter of Petition under Sections 86 (1) (c) (e) and (f) of Electricity Act, 2003 and as per Clause 3.9 of GERC Order No. 06 of 2024 dated 31.08.2024 for extension of date of grid connectivity and commissioning in respect of 7.8 MW solar plant for captive use due to occurnance of uncontrollable events.

  • 1JUL 2025
    Hearing

    Judge: N/A

    In the matter of Petition under Sections 86 (1) (c) (e) and (f) of Electricity Act, 2003 and as per Clause 3.9 of GERC Order No. 06 of 2024 dated 31.08.2024 for extension of date of grid connectivity and commissioning in respect of 7.8 MW solar plant for captive use due to occurnance of uncontrollable events.