Onix-Two Enersol Private Limited vs GETCO
Party Details
- Onix-Two Enersol Private Limited
- GETCO
Case Summary
Onix-Two Enersol Private Limited filed Case No. 2481/2025 in the Gujarat Electricity Regulatory Commission against GETCO. The case has undergone 5 hearings over 10 months. The case is currently pending. 3 orders have been issued in this matter.
Hearing History (5)
- 7APR 2026Hearing
Judge: N/A
Petition under Section 86 of EA 2003 read with Order No. 01 of 2024 dated 22.02.2024 ‘Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind-Solar Hybrid Projects Including Storage, if any, and other Commercial issues for the State of Gujarat’ passed by the Commission, seeking extension of the Scheduled Date of Commissioning of infrastructure being developed by the Petitioner for evacuation of power from its 40 MW Hybrid Power Plant to GETCO’s 66 kV Sutrapada Sub-Station on account of occurrences and circumstances beyond the reasonable control of the Petitioner being Unforeseen events or reasons.
- 20AUG 2025Hearing
Judge: N/A
Petition under Section 86 of the Electricity Act, 2003 read with Order No. 01 of 2024 dated 22.02.2024 ‘Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind-Solar Hybrid Projects Including Storage, if any, and other Commercial issues for the State of Gujarat’ passed by this Commission, seeking extension of the Scheduled Date of Commissioning of infrastructure being developed by the Petitioner for evacuation of power from its 40 MW Hybrid Power Plant to the Respondent GETCO’s 66 kV Sutrapada Sub-Station on account of occurrences and circumstances beyond the reasonable control of the Petitioner being Unforeseen events or reasons.
- 17JUL 2025Hearing
Judge: N/A
Petition under Section 86 of the Electricity Act, 2003 read with Order No. 01 of 2024 dated 22.02.2024 ‘Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind-Solar Hybrid Projects Including Storage, if any, and other Commercial issues for the State of Gujarat’ passed by this Commission, seeking extension of the Scheduled Date of Commissioning of infrastructure being developed by the Petitioner for evacuation of power from its 40 MW Hybrid Power Plant to the Respondent GETCO’s 66 kV Sutrapada Sub-Station on account of occurrences and circumstances beyond the reasonable control of the Petitioner being Unforeseen events or reasons.
Orders (3)
- 16APR 2026orderView Order ↗
Order No: 1
- 23JUL 2025orderView Order ↗
Order No: 2
- 11JUN 2025orderView Order ↗
Order No: 3