SREEDJAR ENGINEERING WORKS vs THE STATE OF AP

Case NumberWP 10792/2023
Date of Filing12 Apr 2023
Case TypeWP
Last Hearing26 Jul 2023
State--
City--
Year of Filing2023

Party Details

Petitioner
  • SREEDJAR ENGINEERING WORKS
Respondent
  • THE STATE OF AP
  • The Commissioner
  • The Superintending Engineer Irrigation Circle
  • The Executive Engineer
  • The Principal Secretary

Case Summary

SREEDJAR ENGINEERING WORKS filed Case No. WP 10792/2023 in the High Court Of Andhra Pradesh on 12 Apr 2023 against THE STATE OF AP and The Commissioner. The case has had one hearing so far. The case is currently pending. 1 order has been issued in this matter.

Hearing History (1)

  • 26JUL 2023
    Next Hearing

    Judge: N/A

Orders (1)

Judgement DetailsView full order PDF ↗

THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION No.10792 of 2023 ORDER: 1.

The petitioner has been awarded the contract of work(s) under the subject scheme in Nellore District.

After execution of the said contract, a final bills were prepared for a sum of Rs.16,24,282/-, Rs.7,29,495/- and Rs.7,94,842/- respectively as per the sanctioned orders.

As the payment of the said amounts has not been made by the respondents, the petitioner has approached this Court by way of this writ petition.

2.

It is the contention of the petitioner that even though the respondents admitted that the petitioner is entitled for payment of the aforesaid sums of money, no payment is being made.

The petitioner contends that such non-payment of money is clearly arbitrary and high- handed requiring the interference of this Court.

3.

This Court, in various orders, including the judgment of a learned Single Judge of this Court dated 05.10.2021 in W.P.No.10038 of 2021 and batch had taken the view that such non-payment of dues is arbitrary and that such dues need to be cleared by the respondents at the earliest.

4.

On the other hand, learned Government Pleader for Irrigation while admitting about the claim of the petitioner placed on record the written instructions dated 08.12.2023 received from the Executive 2 Engineer, Nellore.

He would submit that LOC is not allotted to the above said works, after release of the LOC the above bills will be submitted to payment.

Soon after release of budget, the bill amount will be paid to the petitioner.

5.

In view of the aforesaid directions of this Court in various cases and after hearing the submissions of learned counsel for the petitioner, learned Government Pleader for Irrigation this Writ Petition is disposed of with a direction to the respondents to release the amount of Rs.16,24,282/-, Rs.7,29,495/- and Rs. /- and Rs.7,94,842/- respectively to the petitioner, along with the interest @ 6% per annum, in view of the judgment of the Hon’ble Division Bench of this Court in Writ Appeal No.724 of 2021 and batch dated 12.10.2023, within a period of six (06) weeks from the date of receipt of a copy of this order.

It would also be open to the petitioner to agitate his claim for higher rate of interest, if any payable by the respondents, in an appropriate forum.

There shall be no order as to costs.

Consequently, Miscellaneous Petitions, if any, pending in this Writ Petition shall stand closed. _______________________________ VENKATESWARLU NIMMAGADDA, J 11.12.2023 JLV 3 315 THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION No.10792 of 2023 11.12.2023 JLV