V BASAVA SHANKARA RAO vs THE STATE OF ANDHRA PRADESH
Party Details
- V BASAVA SHANKARA RAO
- THE STATE OF ANDHRA PRADESH
- The Principle Secrtary
- The Engineer in Chief
- The District Collector
- The Superintendent Engineer
- The Executive Engineer
Case Summary
V BASAVA SHANKARA RAO filed Case No. WP 2874/2023 in the High Court Of Andhra Pradesh on 4 Feb 2023 against THE STATE OF ANDHRA PRADESH and The Principle Secrtary. The case has had one hearing so far. The case is currently pending. 1 order has been issued in this matter.
Hearing History (1)
- 15MAR 2023Next Hearing
Judge: N/A
Orders (1)
- 25APR 2023judgementView Order ↗
Order No: 1
Judgement DetailsView full order PDF ↗
HON’BLE SRI JUSTICE R.
RAGHUNANDAN RAO WRIT PETITION No.2874 of 2023 ORDER: The petitioner had been awarded various contracts for taking up “Neeru-Chettu” Programme for Improvements O&M Repairs to strengthening of banks to KSR Minor drain, removal of weed growth by spraying chemicals Kuchinapudi medium drain, Allaparru medium drain, removal of Nagaram south medium drain and Pillivaagu medium drain in Bapatla District, under various Agreements.
After execution of the said works, a final bill for Rs.10,98,287/- had been prepared and submitted to the concerned for payment.
As the payment of the said amount has not been made by the respondents, the petitioner had approached this Court, by way of this writ petition.
2.
It is the contention of the petitioner that even though the respondents admitted that the petitioner is entitled for payment of the aforesaid sums of money, no payment is being made.
The petitioner contends that such non-payment of money is clearly arbitrary and high-handed requiring the interference of this Court.
2 3.
This Court, in various orders, including the judgment of a learned Single Judge of this Court dated 05.10.2021 in W.P.No.10038 of 2021 and batch had taken the view that such non-payment of dues is arbitrary and that such dues need to be cleared by the respondents at the earliest.
4.
The learned Government Pleader submits that the respondent authorities are verifying the claims of the petitioner and would be in a position to make payment only after such verification is completed.
5.
In view of the aforesaid directions of this Court in various cases and after hearing the submissions of the learned counsel for the petitioner, learned Government Pleader for Irrigation, this writ petition is disposed of with a direction to the respondents to complete the verification process within a period of three weeks from the date of receipt of a copy of this order and thereafter to pay the amount due to the petitioner depending upon the outcome of the veri f the verification, within a period of six weeks.
It is clarified that in the event of the verification process not being 3 completed within the aforesaid period of three weeks, the respondents shall pay the amount due to the petitioner, without insisting upon any further time for verification.
It would also be open to the petitioner to agitate his/her/their claim for interest, if any payable by the respondents, in an appropriate forum.
There shall be no order as to costs.
As a sequel, pending miscellaneous petitions, if any, shall stand closed. ____________________________ R.