BANDIRAVI VARMA vs The State of Andhra Pradesh,

Case NumberWP 19603/2023
Date of Filing1 Aug 2023
Case TypeWP
Last Hearing--
State--
City--
Year of Filing2023

Party Details

Petitioner
  • BANDIRAVI VARMA
Respondent
  • The State of Andhra Pradesh
  • State of Andhra Pradesh
  • The Chief Engineer
  • The Superintending Engineer
  • The Executive Engineer
  • The Pay and Accounts Officer

Case Summary

BANDIRAVI VARMA filed Case No. WP 19603/2023 in the High Court Of Andhra Pradesh on 1 Aug 2023 against The State of Andhra Pradesh and State of Andhra Pradesh. The case is currently pending. 2 orders have been issued in this matter.

Orders (2)

Judgement DetailsView full order PDF ↗

THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION No.19603 of 2023 ORDER: 1.

The petitioner had been awarded the contract of various works under subject scheme in Srikakulam District.

After execution of the said contract, a final bill was prepared for a sum of Rs.4,85,546/- as per the sanctioned orders.

As the payment of the said amount has not been made by the respondents, the petitioner has approached this Court by way of this writ petition.

2.

It is the contention of the petitioner that even though the respondents admitted that the petitioner is entitled for payment of the aforesaid sum of money, no payment is being made.

The petitioner contends that such non-payment of money is clearly arbitrary and high- handed requiring the interference of this Court.

3.

This Court, in various orders, including the judgment of a learned Single Judge of this Court dated 05.10.2021 in W.P.No.10038 of 2021 and batch had taken the view that such non-payment of dues is arbitrary and that such dues need to be cleared by the respondents at the earliest.

4.

On the other hand, learned Government Pleader for Irrigation while admitting about the claim of the petitioner placed on record 2 instructions received from the Executive Engineer, Srikakulam, dated 20.11.2023.

He would submit that based on the outcome of the V&E enquiry and soon after receipt of the Budget release order from the Government, the payment will be arranged.

5.

In view of the aforesaid directions of this Court in various cases and after hearing the submissions of learned counsel for the petitioner, learned Government Pleader for Irrigation this Writ Petition is disposed of with a direction to the respondents to release the amount of Rs.4,85,546/- to the petitioner, along with the interest @ 6% per annum, in view of the judgment of the Hon’ble Division Bench of this Court in Writ Appeal No.724 of 2021 and batch dated 12.10. ted 12.10.2023, within a period of six (06) weeks from the date of receipt of a copy of this order.

It would also be open to the petitioner to agitate his claim for higher rate of interest, if any payable by the respondents, in an appropriate forum.

There shall be no order as to costs.

Consequently, Miscellaneous Petitions, if any, pending in this Writ Petition shall stand closed. _____________________________________ VENKATESWARLU NIMMAGADDA, J 20.11.2023 LSP 3 193 THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION No.19603 of 2023 20.11.2023 LSP