Meta Pixel
CNR: --
SINE DIE

HARERA vs ANSAL PROPERTIES AND INFRASTRUCTURE LTD

Case NumberRERA-GRG-5859-2019
Date of Filing--
Case TypeRERA-GRG
Last Hearing9 Nov 2023
StateHaryana
CityGurgaon
Year of Filing2019

Party Details

Petitioner
  • HARERA
Respondent
  • ANSAL PROPERTIES AND INFRASTRUCTURE LTD

Case Summary

HARERA filed Case No. RERA-GRG-5859-2019 in the Haryana Real Estate Regulatory Authority (RERA) against ANSAL PROPERTIES AND INFRASTRUCTURE LTD. The case has undergone 11 hearings over 3 years and 9 months. The case is currently pending. 5 orders have been issued in this matter.

Hearing History (11)

  • 9NOV 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    It has come to the notice of the authority that the company is in the NCLT. Therefore, matter is sine die.

    Stage: SINE DIE

  • 18OCT 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    Matter adjourned for 09-11-2023 at 10:00 A.M.

    Stage: PENDING

  • 28SEP 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    None is appeared on behalf of the respondent. The promoter is directed to submit the detailed reply and submit the compliance report of proceeding dated 28-06-2023. The company is under NCLT, therefore, the IRP is directed to submit the updated status of NCLT and appear before the authority for hearing on 18-10-2023 at 11:00 A.M.

    Stage: PENDING

  • 7SEP 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    Due to public holiday, matter  is adjourned to 28-09-2023 at 11:00 A.M.

    Stage: PENDING

  • 9AUG 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    None is appeared on behalf of the respondent. It has been noticed that there was no authorized person of the company to appear before the authority for personal hearing. Therefore, one final opportunity of hearing is given to submit the detailed reply and submit the compliance report of proceeding dated 28-06-2023 and appear before the authority for hearing on 07-09-2023 at 11:00 A.M. otherwise authority shall be bound to proceed Ex-parte.

    Stage: PENDING

  • 2AUG 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    Matter adjourned for 09-08-2023 at 11:00 A.M.

    Stage: PENDING

  • 28JUN 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    Sh. Tushar Bahmani (Advocate) is appeared on behalf of the respondent. The counsel of the respondent submits that the company is in the NCLT vide order dated 16-11-2022 and further stated that order of NCLT has been challenged by various allottees in NCLAT regarding appointment of IRP and clarification with regard to IBC proceedings about the company as a whole or some particular project, appeal is fixed up for 24-07-2023. Copy of the order of NCLAT is submitted in the authority. Further, the counsel seeks an adjournment of one month to clarify the position and submits the detailed reply as to which licenses are covered in the part completion received by the promoter. Also, the promoter will clarify regarding phasing if any of the project approved by the DTCP Haryana. IRP is also directed to appear on next date of hearing to clarify the position of the project. Matter to come up on 02-08-2023 at 11:00 A.M.

    Stage: PENDING

  • 27APR 2020
    Hearing

    Judge: SANJEEV KUMAR ARORA

    Matter adjourned for 28-06-2023 at 11.00 A.M

    Stage: PENDING

  • 16MAR 2020
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR SUBHASH CHANDER KUSH

    With reference to show cause notice No. RERA-GRG-5859-2019 dated 12.12.2019, Mr. R.A. Gupta, Mr. Siddharth Yadav and Mr. Sanjay Kumar on behalf of company appeared before the authority for personal hearing. The matter be examined as to whether the facts submitted by the promoter are correct and the project qualifies for exemption of the objection. The case file be put up before the authority. The case is adjourned to 27.04.2020 at 11:00 AM.

    Stage: PENDING

  • 10FEB 2020
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR SUBHASH CHANDER KUSH

    With reference to show cause notice No. RERA-GRG-5859-2019 dated 12.12.2019, Mr. R.A. Gupta, Mr. Siddharth Yadav and Mr. Sanjay Kumar on behalf of company appeared before the authority for personal hearing. The reply submitted by the respondent is under scrutiny.             The matter is adjourned for hearing on 16.03.2020 at 11:00 AM

    Stage: PENDING

  • 20JAN 2020
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR SUBHASH CHANDER KUSH

    WITH REFERENCE TO SHOW CAUSE NOTICE NO. RERA-GRG-5859-2019 DATED 12.12.2019 MR. R.A. GUPTA MR. SIDDHARTH YADAV AND MR. SANJAY KUMAR ON BEHALF OF COMPANY APPEARED BEFORE THE AUTHORITY FOR PERSONAL HEARING. THE PROMOTER IS DIRECTED TO PROVIDE COPY OF OCCUPATION CERTIFICATE ALREADY OBTAINED AND PART COMPLETION CERTIFICATE AND ALSO DIRECTED TO PROVIDE ALL INFORMATION WITH REGARD TO TOTAL AREA FOR WHICH SANCTION PLAN HAS BEEN GOT APPROVED. FURTHER PROMOTER IS DIRECTED TO SUBMIT LAYOUT PLAN AND EXPLAIN EACH DETAIL RELATED TO THE PROJECT WITHIN 10 DAYS. THE MATTER IS FIXED FOR HEARING ON 10.02.2020 AT 1100 AM

    Stage: FIRST HEARING

Orders (5)