Meta Pixel
CNR: --
DISPOSED

MANISHA PRATAP SINGH vs ADVANCE INDIA PROJECTS LIMITED

Case NumberRERA-GRG-708-2022
Date of Filing--
Case TypeRERA-GRG
Last Hearing19 Oct 2023
StateHaryana
CityGurgaon
Year of Filing2022

Party Details

Petitioner
  • MANISHA PRATAP SINGH
Respondent
  • ADVANCE INDIA PROJECTS LIMITED

Case Summary

MANISHA PRATAP SINGH filed Case No. RERA-GRG-708-2022 in the Haryana Real Estate Regulatory Authority (RERA) against ADVANCE INDIA PROJECTS LIMITED. The case has undergone 10 hearings over 1 year and 6 months. The case was disposed of on 19 Oct 2023. 10 orders have been issued in this matter.

Hearing History (10)

  • 19OCT 2023
    Hearing

    Judge: VIJAY KUMAR GOYAL

    Order pronounced. Both the counsels of the parties confirmed that offer of possession was made on 22.2.2022 and assured return have been paid till 24th December2021. The counsel for the respondent states that since occupation certificate has been obtained in 24.12.2021 and hence no assured return thereafter has been paid to the complainant-allottee. The respondent is required to make payment of arrears of assured return @ Rs.211435- per month till offer of possession as per agreement which has not been paid by the respondent to the complainant. Arguments heard. In view of the above assured return till offer of possession is allowed. Matter stands disposed off. Detailed order will follow. File be consigned to the registry.

    Stage: DISPOSED

  • 21SEP 2023
    Hearing

    Judge: VIJAY KUMAR GOYAL

    The present complaint has been received on 22.02.2022 and the reply on behalf of respondent was received on 15.07.2022. The complainant also filed application for appointment of LC and the said issue was deliberated upon vide proceedings dated 16.11.2022. Succinct facts of the case as per complaint and reply are as under: S. N. Particulars Details 1.       Name of the project “AIPL Joy Central” 2.       Project location Sector 65, Gurugram 3.       Allotment letter 05.04.2017 [As per page no. 47 of complaint] 4.       Unit No. 96, Ground floor [As per page no.  60 of complaint] 5.       Unit Area 1386 sq. ft. (super area) [As per page no. 60 of complaint] Revised area – 1385.91 sq. ft. [As per page 65 of reply] 6.       Date of agreement for sale 15.11.2017 [As per page no. 55 of complaint] 7.       Possession clause 44. The company endeavours to hand over the possession of the unit to the allottee within a period of 54 months with a further grace period of 6 months, from 1 September 2017 (Emphasis supplied) 8.       Due date of possession 01.09.2022 Grace period of 6 months are allowed 9.       Total sale consideration Rs.3,85,78,190/- [As per statement of accounts dated 22.02.2022 on page 80 of the reply] 10.              Amount paid by the complainant Rs. 4,14,98,214/- [As per statement of accounts dated 22.02.2022 on page 80 of the reply] 11.              Assured return clause 32. Where the allottee has opted for payment plan as per annexure A attached herewith and accordingly, the company has agreed to pay Rs.2,11,435/- per month by way of assured return to the allottee from 06.05.2017 till the date of issue of notice of possession of the unit. 12.              Amount paid to the complainant by way of assured return Rs.67,33,231/- As per calculation sheet annexed at page no 79 of the reply The complainant has admitted in his complaint that the respondent had stopped paying assured returns to the complainant from 24.12.2021 on page 5 of the complaint 13.              Occupation certificate 24.12.2021 [As per page 62 of reply] 14.              Offer of possession 22.02.2022 [As per page 65 of reply] The complainant has already submitted the written submissions on 23.8.2023 and the counsel for the respondent requests for its submission within one week after supplying a copy the complainant. The complainant present in person states that at the time of booking of the unit, there were different payment plans and the complainant has chosen the construction link payment plan in respect of office unit which is at page 47 of the complaint which clearly provided that 20.50 percent amount shall be demanded on completion of super structure- office block. While the payment has been demanded on 4th February,2022 but  as per LC report , the super structure in respect of office block was not completed and already is part of their admission dated 16 .11.2022.  However, the counsel for the respondent clarifies that application form at page 30 of the reply at page 51 under clause 44, it has been clarified that the company shall be carrying out extensive development and construction activities in future in the entire area out side the project and the application agreed to not raise any objection for the same.  Further stated that  since the unit is in  retail block  and hence condition of completion of super structure of office block in the agreement was also only inadvertently.  Counsel for the respondent shall file written submissions within a week with an advance copy to the counsel for the complainant. Order reserved. Matter to come up on 19.10.2023 for pronouncement of orders.

    Stage: RESERVED

  • 7SEP 2023
    Hearing

    Judge: VIJAY KUMAR GOYAL

    In view of Govt. Notification No.28/67/2008-1HR-1 dated 05.09.2023 declaring 07.9.2023 as Gazetted holiday on account of Janmashtami the case is adjourned.   The next date of hearing is fixed for 21.9.2023 for the purpose already fixed.

    Stage: PENDING

  • 20JUL 2023
    Hearing

    Judge: VIJAY KUMAR GOYAL

    The complainant has sought assured return as per clause 32 of BBA at a monthly return of Rs.2,11,425/- with effect from 25.02.2017 till the date of notice of possession. The respondent has not complied with the terms and conditions of the agreement. Though for some time the amount of assured returns was paid but later on, the respondent refused to pay the same by taking a plea of the Banning of Unregulated Deposit Schemes Act, 2019. The respondent has offered the possession of the unit on 22.02.2022 after receiving the occupation certificate dated 24.12.2021 from the competent authority.  Arguments heard. Both the parties are directed to submit written submissions within 15 days with an advance copy to each other. Matter to come up  on 07.09.2023 for further proceedings and orders.

    Stage: PENDING

  • 17FEB 2023
    Hearing

    Judge: VIJAY KUMAR GOYAL

    Due to paucity of time, matter could not be heard. Adjourned to 20.07.2023 for further proceedings.

    Stage: PENDING

  • 16NOV 2022
    Hearing

    Judge: VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA

    The present complaint has been received on 22.02.2022 and the reply on behalf of respondent was received on 15.07.2022. The complainant filed an application dated 04.08.2022 requesting for appointment of LC. The counsel for the complainant states that appointment of LC is necessary to prove the contention that the complete super structure of the office block is yet not complete and as a consequence  the offer of possession  is pre-mature  as per the milestone  mentioned in the BBA.  On the other hand,  the counsel for the respondent states that there is no necessity to appoint LC in the matter  since it is an admitted fact that the complete super-structure of the office block is not yet complete.   However,   he states that the offer of possession is valid since the unit has been allotted in the ground floor of the retail block for which OC has been duly issued dated 24.12.2021 which categorically mentions "retail plus multiplex from ground floor,  I- 4  floor”.  This is the contention made in the reply  to the application  at page 51.  The counsel  for the complainant states that there is no separate “retail block”  in the project.  In fact,  there are only retail units which are situated in the office block. Arguments heard. In view of the submissions made, t here is no requirement for appointment of LC. Matter to come up for final arguments on 17.02.2023 the date already fixed in this case.

    Stage: PENDING

  • 9NOV 2022
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA

    File taken up today as 9.11.2022 was declared as public holiday by the Haryana Govt. vide notification No.28012006-1HRI dated 3rd November2022 in all offices of the Haryana Govt. in the jurisdiction of the areas namely Ambala Charkhi Dadri Gurugram Karnal KurukshetraRewariRohtakSirsa and Sonepat in connection with poll for Members of Zila Prishads and Panchayat Samities. In view of above facts the matter is adjourned to 16.11.2022 for the purpose already fixed.

    Stage: PENDING

  • 26OCT 2022
    Hearing

    Judge: VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA

    Vide resolution No. 643 dated 21.10.2022, the District Bar Association has informed that the District Courts are not working on 26.10.2022 on the occasion of Bhai Dooj and has requested the Authority to also adjourn the matters.  Matter to come up on 17.02.2023  for  the purpose as already fixed.

    Stage: PENDING

  • 22JUL 2022
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL

    The District Bar Association Gurugram vide resolution No.448 dated 22.07.2022 has requested for suspension of work in District Courts Gurugram today i.e. 22.07.2022 due to untimely and sad demise of Shri Rajesh Khatri Advocate son of Shri Hazari Lal Advocate. In view of the above, the hearings are  adjourned.                   Matter to come up on 26.10.2022 for further proceedings.

    Stage: PENDING

  • 13APR 2022
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL

    Vide resolution No. 252 dated 11.04.2022, it was informed by the District Bar Association Gurugram that the District Courts are not working on 13.04.2022 and 15.04.2022 on the occasion of Vaisakhi and Good Friday respectively and requested to this Hon’ble Authority to adjourn the matters listed today i.e. 13.04.2022.   Reply has not filed till date. The respondent is directed to file the same within 15 days with an advance copy to the complainant. Accordingly, the matter is adjourned to 22.07.2022 for the purpose as already fixed.

    Stage: FIRST HEARING

Orders (10)

Judgement DetailsView full order PDF ↗

HARERA GURUGRAI\,,] Complaint Nos. and 707 of 2022 & 7OA ot 2022 BEFORE THE HARYANA REAL ESTATE REGULATORY AUTHORITY, GURUGRAM Order reserved oni 21.09.2023 Order pronounced on: t9.to.zo23 CORAM: Shri Viiay Kumar Goyal Memher ORDER 1.

This order shall dispose ofboth the complaints titled as above filed before the authority under section 31 of the Real Estate (Regulation and Development) Act,20L6 (hereinafter referred as "the Act") read with rule 28 of the Haryana Real Estate (Regulation and Developmentl Rules, 2017 (hereinafter referred as "the rules") for violation of section 11(41(al of the Act wherein it is inter alia prescribed that the promoter shall be responsible for all its obligations, resp onsib ilitie s and functions to the allottee as per the agreement for sale executed inter se between parties.

2.

The core issues emanating from them are similar in nature and the complainant(s) in the above referred matters are allottees of the project, namely,"AIPLIOY CENTML" (commercial colonyl being developed by the ;, NAME OF THE BUILDER M/S ADVANCE INDIA PROIECTS LIMITED PROIECT NAME "AIPL IOY CENTRAL" S.

No.

Case No.

Case title APPEAMNCE 1. cR/707 /2022 Manisha Pratap Singh v/s M/s Advance India Projects Limited Ms.

Dagger Malhotra Advocate and Shri Harshit Batra Advocate 2. cR/70812022 Ms, Dagger Malhotra Advocate and Shri Harshit Batra Advocate Page 1of30 v/s M/s Advance India Projects Limited b,- IIA|?IRA P".GURUGRAI/ 3. occuDation Certificatet - 24.1 2,2 021 Possession Clause: - 44.

Force Maieure Subject to the aforesqid and Subject to the Allottee not being in default under ony port ofthis Agreement including but not limited to the timely payment of the Totol Price cind glso subject to the Allottee hoving complied with all formalities or doiimentations os Qresaribed by the compony, the company endeavours to hand over the possession of the Unit to the Allottee within q period of 54 months with a funher grace pertod of 6 months, Jrom 1 September 2 0 77.,,....... .,,............." Assured Return Clause: - 32, Where the Allottee has opted for Poyment Plon as per qnnexure A ottoched herewith and accordingly, the Company has agreed to poy Rs.64,891/- per month by way ofossured return to the Allottee fron 25.02.2017 till the dqte of issue of notice ofpossession of the unit.

The return sholl be inclusive of oll toxes whotsoever pqyable or due on the return.

Complaint Nos. and 707 of2.022 & 70A of 2022 same respondent/promoter i.e., M/s Advance India Projects Limited.

The terms and conditions of the booking application form, agreement to sell and allotment letter against the allotment of units in the upcoming project of the respondent/builder and fulcrum of the issues involved in both the cases pertains to failure on the part of the promoter to deliver timely possession of the units in question, seeking award of assured return till valid offer of possession, to complete the super structure of office block and compensation.

The details of the complaints, reply to status, unit no., date of agreement, possession clause, due date of possession, total salc consideration, total paid amount, and relief sought are given in the table below; Project Name and Location Advance India Proiects Limited at "AlPL JOY CENTRAL", Sectors 65.

Gurueram.

Page 2 of30 v HARERA GURUGRA[/ Complaint Nos. and 707 of 2022 &7OA of 2022 Sr.

No Complaint No., Case Title, and Date of Iiling of complaint Reply status Unit No.

Date of execution of agreemellt to sell Due date of possession Total Consideration /Total Amount paid by the complainants in Rs. t. cR /707 / 2022 Manisha Pratap Singh v/s India Projects Limited.

Dateof filingof complaint 22.02.2022 Reply received on 15.07.2022 I I# 05, Cround floot admeasuring Revised area- 445.11sq. ft.

IPage no. page 66 ofthe replyl 15.11_2017 lAs per page no.23 of complaintl n 07.09.2022 [Grace period ol6 mon$s are allowed) (Note: calculated 01. ulated 01.09-2017 + 6 months grace period mention in the buyer's agreemen0 TSC: ' 1,16,O5,79A/. r,24,50,662 / - ( As per accounts dated 22.02.2022 ot page 82 of the replyl cR/708/ 2022 Manisha Pratap Singh v/s M/s lndia Projects Limited.

Date of Filing of complaint 22.02.2022 Reply 1s.o7.2022 96, Ground floor admeasuring 1386 sq. ft Isuperarea) Revised area 1385.91 sq. fL [As per page 65 ofreplyl 15.71.2017 lAs per pagc no.55 ol complarnll I 01.09.2022 (craceperiod o[6 months areallowed) INoter- calculated from the 01.09.2017 + 6 montis grace period mention in the buyer's agreement) TSC: - 3,85,74,190 / - 4,14,9A,214 / - ( As per statement of accounts dated 2Z-O2-2o22 oi page 80 of the reply) The complainant inthe above complaints have sought the following reliefs: 1.

Direct the respondent to pay assured return to the complainant from 25.12.2021, till date ofvalid offer of possession as Rs.10,51,813.62 /- per month.

Direct the respondent to not illegally offer of possession without completion of construction ofthe super structure ofoffice block as otherwise the same would be contrary to the terms aSreed in the unit buyer's aqreement. h, Page 3 of30 5.

Complaint Nos. and 707 of2022 & 708 of 2022 elaborated as follows: Abbreviation Full form TSC Total Sale consideration 4.

AP Amount Daid by the allottee The aforesaid complaints were filed against the promoter on account of violation of the booking application form, agreemcnt to sell and allotment Ietter against the allotment of units in the upcoming project of the respondent/builder and for not handing over the possession by the due date, seeking award of assured return till valid offer of possesslon, to complete the super structure of office block and compensation.

It has been decided to treat the said complaints as an application for non- compliance of statutory obligations on the part of the promoter/ respondent in terms of section 34[fl of the Act which mandates the authority to ensure compliance ofthe obligati e obligations cast upon the promoters, the allottee(s) and the real estate agents under the Act, the rules and the regulations made thereunder.

The facts ofboth the complaints filed by the complainant(sl/allottee(s.) are also similar.

Out of the above-mentioned case, the particulars of lead case CR/707/2022 titled qs Manisha Pratap Singh V/S M/s Advonce Indio Projects Limited are being taken into consideration for determining the rights of the allottee(s) qua assured return till valid offer of possession, to complete the super structure of office block and compensation.

Proiect and unit related details 6.

A.

HARERA GURUGRAIU 3, Direct the respondent to odhere to the terms mentioned in the unit's buyer's agreement along with the onnexure A of the agreement and to make offer of possession in compliance of the said terms.

4.

Award the litigation cost to the tune of Rs.50,000/- in the fqvour ofthe comploinant.

Note: In the table referred above, certain abbreviations have been used, They are V Page 4 of 30 HARERA P*GURUGRAM 7.

Complaint Nos. and 707 of 2022 & 70A of 2022 The particulars ofthe project, the details ofsale consideration, the amount paid by the complainant(s), date ofproposed handing over the possession, delay period, ifany, have been detailed in the following tabular form: cR/707/2022 titled as Manisha Pratap singh v/s M/s Advance India Proiects Limited, s.

N.

Particulars Details 1.

Name ofthe project "AIPL Joy Central" 2.

Project location ;ector 65, Gurugram 3. !

Allotment letter 70.o4.2077 [As per page no.

15 of complaint] 4.

Unit No.

05, Ground lloor [As per page no.

28 ofcomplaint] 5.

Unit Area lt ({/ 455 sq. ft. (super areal [As per page no.

2B of complaint] Revised area- 445.11 sq. ft. lPage no. page 66 of the reply] 6.

Date ofagreement for sale 75.1,1,.2077 [As per page no.

23 of complaint] 7.

Possession clause it t tl 44. ,,,,... ... ,,,... ...The contpany endeavours to hand over the possession of Lhe unit to the allotteewithin a period of 54 months with o further grace period oi6 months, from 1 September 2017 (Emphasis supplied) B.

Due date ofpossession oL.o9.2022 (Grace period of6 months are allowed) 9.

Total sale consideration Rs.1,16,05,798/- [As per statement of accounts dated 22.02.2022 on page 82 of the replyl 10.

Amount paid by the complainant Rs.7,24,50,662 /- [As per statement of accounts dated 22.02.2022 on page 82 of the replyl Page 5 of30 w HARERA P- GURUGRAM Complaint Nos. and 707 of 2022 &708 of 2022 B. s Facts ofthe complaint * 0005 on the ground floor, having super iarea of 455 sq. ft. in the respondent's project namely, "AIPL Joy Central," The respondent issued an allotment letter dated 10.04.201,7, allotted the above- mentioned unit in favour of the complainant and confirmed the payment plan opted by the complainant which stated that the offer of possession shall be made only after completion of the superstructure 11.

Assured return clause Where the allottee hos opted for payment plan as per annexure A attached herewith and accordingly, the company has agreed to pay Rs.64,891/- per month by way ol assured return to the allottee from 25,02.2077 till the date of issue of notice ol possession of the unit 12.

Amount paid to the complainant by way of assured return ffi R9.ZO,16,B7 3 / - 4s,per calculation sheet annexed at page no 81 ofthe reply The complainant has admitted in his complaint that the respondent had 13.

Occupation certificate 24.72.2027 [Page 63 ofthe reply] 74.

I I 22.02.2022 [Page 66 ofthe reply] II : following submissions in the complaint: - lied for allotment of a retail unit bearing no.

Ilowing su!missions in the complaint: - Page 6 of 30 v ffiHARERA #GuRUGRAM ofthe office block The respondent also confirmed the assured returns plan opted by the complainant. b.

That on 15.11. on 15.11.2017, the respondent entered BBA with the complainant reiterating the afore-mentioned terms and conditions and payment plan so opted under the allotment letter and assured returns.

The total sale consideration of the said unit was Rs.1,18,63,670/- and the complainant has till date paid a total of Rs.L,24,50,662/- to the respondent. c.

The assured return amount was mutually agreed to be 110lo annually (subject to TDS) on all the advance payments (excluding GST amountJ d. made by the complainant to the respondent.

The respondent has stopped paying assured return amount Rs.1,0 5,813.62 /- per month to the complainant after 24.12,2021.

That the complainant has been constantly enquiring from the respondent regarding the non-payment of assured returns from the month of 25.72.202I onwards but all in vain.

The respondent has stated that it will pay assured returns till date of receipt of occupation certificate and not beyond that, which is absolutely in contravention of the buyer's agreement, which provides that the respondent is obligated to pay till offer of possession.

As per the clause 44 of the buyer's agreement, the respondent was to offer possession to the complainant within 54 months from 01.09.2077 plus 6 months grace period, therefore the due date of possession behg01.09,2022 That, in the said project there were to be constructed a total 23 floors (being ground floor plus 22 floorsl out of which ground floor plus 4 Complaint Nos. and 707 ot 2022 &7OA of 2022 Page 7 of 30 N HARERA GURUGRAM floors are retail units and 5tt floor till 22nd floor are office units.

The entire tower in entirety was the office block.

Therefore, completion of construction of the superstructure of the said office block is a pre- requisite to making offer of possession.

That the respondent on the other hand, informed the complainant that the respondent is in the process of offer possession of the unit to the complainant without completion of the construction of the superstructure o tructure ofthe "offlde Sock" to avoid its liability to pay assured returns under clause 32 of the agreement and therefore the same is contradictory and in complete violation of the buyer's agreement.

As per buyer's agreement, an offer of possession can be made only after completion of construction of super structure of office block and not before that.

The same is necessary in practicality as well as retail unit cannot be operated ifthere is heavy structural construction going on in the Office Units above the retail units in the office block.

The respondent has received the occupation certificate of the retail units, but the office block itself is still under construction and it is not even possible to inspect the retail unit without wearing a helmet to enter the same due to heavy construction going on in the office units above the retail units in the office block.

Relief sought by the complainant: - The complainant has sought following relief(s) a.

Direct the respondent to pay assured return to the complainant from 25.72.2021 till date of valid offer of possession as Rs.10,51,81.3.62/- per month.

Complaint Nos. and 707 of 2022 & 7OA of 2022 c.

9.

Page 8 of30 N Complaint Nos. and 707 of 2022 &7OA of 2022 HARERA ffiGURUGRAI/ b.

C, d.

Direct the respondent to not illegally offer of possession without completion of construction of the super structure of office block as otherwise the same would be contrary to the terms agreed in the unit buyer's agreement.

Direct the respondent to adhere to the terms mentioned in the unit's buyer's agreement along with the annexure A of the agreement and to make offer of possession in compliance of the said terms.

Award the litigation cost to;he tune of Rs.50,000/- in the favour of the complainant. ilii{ D, Reply by the respondent 10.

The respondent contested the complaint on the following grounds: - 1. ll. complaint. complaint.

That filing of the present complaint seeking possession ol the unit in question cannot be entertained when the due date of delivery has not been attained yet.

That, the complainant has filed the present complainant before this authority which is not maintainable.

That the complainant is praying for the relief of "Assured Returns" which is beyond the jurisdiction that this authority.

That from the bare perusaL of the Act oF 2016, the said Act provides for three kinds of remedies in case of any dispute between a builder and buyer with respect to the development of the proiect as per the agreement, as provided under section 18 of the Act, 2016 for w Page 9 of 30 SHARERA S-,ounuennHr violation of any provision of the Act.

That the said remedies are of "Refund" in case, the allottee wants to withdraw from the project and the other being "interest for delay of every month" in case the allottee wants to continue in the project and the last one is for compensation for the loss occurred by the allottee. iii.

That nowhere in the said provision the authority has been dressed in jurisdiction to grant " Returns".

Therefore, the present complaint is filed with grave illegalities and Iack ofjurisdiction and the same is liable to be dismissed at the very outset and the complainant shall be directed to file pursue the complaint before the civil court for any dispute arises from the agreement in the form of investment agreement and lease agreement. iv.

That, moreover, the payment of assured returns has been banned as per the prevalent laws.

On 3L.07.201,9, The Banning of Unreguloted Deposits Schemes Act, 2019 ('the BUDS Act") was notified and came into force.

That under the said BUDS Act, all the unregulated deposit schemes such as Assured Returns have been banned and made punishable with strict penal provisions. rovisions.

That being a law-abiding company, by no stretch ofimagination, the Respondent can continue to make the payments of the Assured Returns in violation of the BUDS Act. v.

That at the very outset that the instant complaint is untenable both in facts and in law and is liable to be rejectc-d on this ground alone.

Complaint Nos. and 707 of 2022 &7OB of 2022 lA, Page 10 of30 I llARERA ffiGURUGRAM Moreover, the complaint is filed without any cause of action and hence is liable to be dismissed. lt is again submitted that the complaint is pre- mature in nature and the present preliminary submissions/objections may please be read along with the preliminary objections to the maintainability of the complaint.

That at the outset, it needs to be noted that the development of the project namely "AIPL loy. @fol" ,lor^t"d at Sector 65 Gurugram, Haryana has been done-Wn{iipit}e Licenses no.

249 of 2007 dated r rl That the complainant being interested in the real estate development project of the respondent applied for an allotment on a possession linked payment plan via application form dated 05.04.2017.

The application form was executed willingly and voluntarily between the parties.

The complainant understood all and every term and condition of the same and the subsequent buyer's agreement. 'Ihe complainant categorically noted that a copy of the agreement had been provided to her, hence, it was only after the having perused the same, the application form was executed by the complainant as a pre-requisite for execution ofthe agreement and for booking ofthe unit. viii.

That thereafter, a provisional retail shop unit bearing no.

05, having super area 455 sq. ft. located on ground floor was allotted vide an Complaint Nos. and 707 of 2022 &708 of 2022 vI.

VlI.

Page 11 of 30 fb" ffiHARERA ffi GuRucRA[/ Complaint Nos. and 707 of 2022 &7OA of 2022 allotment letter dated 10.04.2017.

0.04.2017.

Accordingly, the buyer's agreement was delivered to be executed, to the complainant vide letter dated 26.06.2017.

That upon delay in execution of the agreement, the respondent also served the complainant with a reminder dated 78.08.20L7.

That it was thereafter that finally, the BBA was executed on 75.L7.2017 . lx.

That, the project underwr in the building plans, upon which, objections/suggestion for the approval of the building plan was rightly invited from the complainant vide letter dared 21.11.2019, however, none were submitted by the complainant.

Thereafter, the unit of the complainant was renumbered from 0005 to GF-05 and the supper area ofthe unit was reduced to 445.98 sq. ft. and the same was rightly communicated to the complainant on 20.05.2020, x.

That, as per clause 44 of the agreement, the due date of delivery of possession was subject to the force maieure conditions, timely payment by the allottee and obliging with the other terms and conditions of the agreement and the same was fixed to be 54 months with a further grace period of 6monthsfrom 0L.09.20L7, accordingly, the subjective due date of delivery of possession oI the unit comes out lo be O1.O9.2022.

That the present complaint is pre mature and not maintainable and hence cannot be continued and is entitled to be dismissed.

Accordingly, the contents of the preliminary objections to Page 12 of30 lv HARERA P*GURUORAI/ Complaint Nos. and 707 of 2022 & 7OB of 2022 xi. the maintainability ofthe complaint may please be read along with and are not repeated herein for the sake of brevity.

That even though the respondentwas deeply aggrieved with a number of unforeseeable circumstances causing hindrance in the continuous construction of the project, like the ban on construction activities, orders by the NGT and EPCA, demobilisation oflabour, the grave effect of the corona virus pandlrnig. etc. being circumstances beyond the control of the respondbnt'; and force maieure circumstances. umstances. lthe construction and rightfully applied for occupancy certificate for Retail + multiplex on 09.05.2021 xlI. and valid notice of offer of That as per clause 11 of the BBA, the complainant was obligated to take possession of the unit within 30 days from the date of notice of offer of possession which was to be made after the receipt of the occupancy certificate onU...Tt! the offalr of posseqsion was given as per the settled law according to which, possession can be delivered upon the receipt of occupancy certificate. xiii.

That, furthermore, it is a matter of fact that the parties agreed for the payment of assured returns as per clause 32 of the BBA.

However, the payment of such assured returns was not static and subject to force and rightfully obtained the same on 24.).2.2021.

Thereafter, the V Page 13 oF30 ffiHARERA # alnuennnr .

Complaint Nos. and 707 of 2022 &7OA of 2022 maieure conditions as per clause 44 of the buyer's agreement, as reiterated hereinabove, which categorically noted that upon force maieure circumstances, the assured returns shall not be paid by the company. xiv.

That, the authority does not have the jurisdiction to deal with cases pertaining to assured returns and the same lies beyond the purview of the Act and the payment ofas*lred returns has been banned under the BUDS Act.

That, without prejudice to the foregoing and the objections to the maintainability of the complaint and the non-existence of jurisdiction of this authoriry, it is submitted that the true and, bona fde intent and conduct of the respondent needs to be noted here, as is evident from the fact that the under the electronic clearance system pay out, the respondent has issued a letter dated 17.08.2018 for the pre-payment of assured return confirmation from 01.07.2018 and further from 06.07.201a till the date of notice of offer of possession.

The intent of the respondent has always been to fulfil its contractual obligations. xv. tions. xv.

That despite the same, the respondent maintained on its commitment of payment of assured return. l'hat on 0(t.07.2020, the payment of assured returns was divided in two parts of 50% each and the same were made payable in the following manner: Part IAR: Due evety month from the succeedinlJ date oJ lockdown perbd known as AR Restort date.

Page 14 of 30 ir ffi& HARERA GURUGRAI/ Part ll AR: Accruing from succeedlng date oflockdown period olong with interes@120k.

The above arrangement was duly informed to the complainant vide letter dated 06.07.2020.

That the respondent has rightly paid the assured return from time to time, as evident from the assured return sheet. xvi.

That the complainant stands in default of taking the offer of possessio n and making the due paynients.

The malafide conduct of the complainant is evident from the fact that the complainant has enjoyed the payments of assured returns and failed to comply with their obligations, That as on 22.02.2022, the complainant has to pay Rs.7,38,231/-.

That, apart from violating the obligations under the BBA, the complainant stands in violation ofsections 19(6J and 19( 11) and hence is liable to pay interest under Section 19(7J of the RERA Act, 20t6.

Complaint Nos. and 707 of 2022 &708 of 2022 on the can be written 11.

Copies of all the relevant documents have been filed and placed record.

Their authenticity is not in dispute.

Hence, the complaint decided on the basis of these undisputed documents and submissions made by the parties.

E.

Jurisdiction ofthe authority 12.

The authority has complete territorial and subject matter jurisdiction adjudicate the present complaint for the reasons given below.

Page 15 of 30 [L E.I Territorialiurisdiction 13.

As per notification no.7/92 /2017-1TCP dated 14.12.2017 issued by Town and Country Planning Department, Haryana the jurisdiction of Haryana Real Estate Regulatory Authority, Gurugram shall be entire Gurugram district for all purposes. purposes.

In the present case, the proiect in question is situated within the planning area_.of Gurugram district.

Therefore, this authority has complete territo;iai'jurisdiction to deal with the present ::': '. a : complaint. .

I tl HARERA ffiGURUGRAI/ E,ll Subiect-matterjurisdl Section 11[4)(aJ of the Act, responsible to the allottee as reproduced as hereunder: Complaint Nos, and 707 of 2022 &70a of 2022 des that the promoter shall be Section 11[4)(a] is 14. eement for sale.

Section 77 (4) The promoter shall- ns, responsibilities and functions the rules and regulotions made the agreement for sale, or to the associqtion of ollottees, as lhP case moy be, till the conveyonce ofoll Lhe opartments, plSts or buildiiis,d{the case moy be, to the ollouees, or the common qreai'bdldossoiittionbSa ottees or 6he competent authority, as the case mqy be; Sedion 34-Functions of the Authority: 34A of the Act provides to ensure complionce of the obligations cost upon the promoters, the ollottees qnd the reol estate ogents under this Act and the rules ond regulations mode thereunder.

15.

Hence, inviewofthe authoritative pronouncement ofthe Hon'ble Supreme Court in the case mentioned above, the authority has the iurisdiction to Page 16 oF 30 v F.

1-6. ffiHARERA H arRuGRA[I entertain a complaint seeking refund of the amount and interest on the refund amount.

Findings on the reliefsought by the complainant.

F.l Direct the respondent to pay assured return to the complainant from 25.72.2021 till date o f valid offer of possession as Rs.10,51,813,62 / - per month.

The complainant has sought assured return on monthly basis as per clause 32 of agreement to sell dated 15.7L2017, the companyhas agreed to pay an amount of Rs.2,L1,435 /- per month by way of assured return to the allottee from 06.05.2017 tilllhdd2tb ofissue ofnotice ofpossession ofthe unit. fthe unit.

The respondent has not complied with the terms and conditions of the agreement to sell, Though for some time, the amount of assured returns was paid but later o!1, tbe respondent refused to pay the same by - 1.. , I I taking a plea of the Banning of Unregulated Deposit Schemes Act, 2 019.

But that Act does not create. a.!ar for payment of assured returns even after coming into operation lnd the payments made in this regard are protected as per section 2(a)[iii) -of the above-mentioned Act.

However, the plea of respondent is otherwise and who took a stand that though it paid the amount of assured return upto the December 2021 but did not pay assured return amount after coming into force of the Act of 2019 as the same was declared illegal.

The Act of 2016 defines "agreement for sale" means an agreement entered into between the promoter and the allottee [Section 2(c)].

An agreement for sale is defined as an arrangement entered between the promoter and Complaint Nos. and 707 of 2022 &7OA of 2022 L7.

Page 17 of30 tu HARERA MGURUGRAI/ allottee with freewill and consent of both the parties.

An agreement defines the rights and liabilities of both the parties i.e., promoter and the allottee and marks the start ofnew contractual relationship between them.

This contractual relationship gives rise to future agreements and transactions between them.

The different kinds of payment plans were in vogue and legal within the meaning ofthe agreement for sale.

One ofthe integral part of this agreemenriis $,q transaction of assured return inter- se parties.

The "agreement for sale" after coming into force ofthis Act (i.e., Act of 2016) shall be in the prescribed form as per rules but this Act of 2016 does not rewrite the "agreement" entered between promoter and allottee prior to coming into force of the Act as held by the Hon'ble Bombay High Court in case Neelkamal Realtors Suburban Private Limited and Anr. v/s llnion of lndia & Ors., (Writ Petition No. tition No.

2737 of 2017) decided on 06.12,2017.

Since the agreement defines the buyer-promoter relationship therefore., it can.bq.said. that the agreement for assured . ? !r r returns between the ipromotiir and allottee arises out of the same relationship.

Therefolel-i! cq1!e said that the real estate regulatory authority has complete jurisdiction to deal with assured return cases as the contractual relationship arise out of agreement for sale only and between the same parties as per the provisions of section 11(4J (a) of the Act of 2016 which provides that the promoter would be responsible for all the obligations under the Act as per the agreement for sale till the Complaint Nos. and 707 of 2022 &7OB of 2022 Page 18 of30 (v Complaint Nos. and 707 of2022 & 7OA of 2022 & 18.

HARERA M GURUGRAM execution of conveyance deed of the unit in favour of the allottee.

Now, three issues arise for consideration as to: i.

Whether the authority is within its jurisdiction to vary its earlier stand regarding assured returns due to changed facts and circumstances. ii.

Whether the authority is competent to allow assured returns to the allottee in pre-RERA cases, after the Act of 2016 came into operation, iii.

Whether the Act of 2019 bars pa,,rnent of assured returns to the allottee :" in pre-REM cases, ',, ,1 Anr.

Vs, M/s Londmark 78), and Sh.

Bharam Singh & Anr.

Vs, Venetain LDF Projects LLP" (supra), it was held by the authority that it has no jurisdiction to deal with cases of assured returns.

Though in those cases, the issue ofassured returns was involved to be paid by the builder to an allottee but at that time, n€ither the full facts were brought before the authority nor it was argued on behalf of the allottees that on the basis of contractual obligations, the builder is obligated to pay that amount.

However, there is no bar to take a different view from the earlier one if new facts and law have been brought before an adjudicating authority or the court. the court.

There is a doctrine of "prospective overruling" and which provides that the law declared by the court applies to the cases arising in future only and its applicability to the cases which have attained finality is saved because the repeal would otherwise work hardship to those who had trusted to its existence.

A reference in this regard can be Page 19 of 30 |il, && HARERA GURUGRAM Complaint Nos. and 707 of 2022 &7OA ot 2022 made to the case of Sorwan Rumar & Anr vs.

Madan Lal Aggarwal Appeal (civil) 7058 oI 2003 decided on 06.02.2003 and wherein the hon'ble apex court observed as mentioned above.

So, now the plea raised with regard to maintainability ofthe complaint in the face ofearlier orders ofthe authority in not tenable.

The authority can take a different view from the earlier one on the basis of new facts and Iaw and the pronouncements made bythe apex court of thel;iu{!.is now well settled preposition of law that when payment of assured -tgb{ins i! part and parcel of builder buyer's agreement (maybe th.rere is a:rlause in that document or by way of addendum, memorandum ofunderstanding or terms and conditions ofthe not liable to pay the amount of assured return.

Moreover, an agreement for sale defines the builder-buyer I relationship.

So, it can be said that. the agreement for assured returns I . ':': -" between the promotel.and an allotee arises out of the same relationship trx and is marked by the original agreement for sale.

Therefore, it can be said that the authority has coJnpleteJuri,sdiction with respect to assured return cases as the contractual relationship arises out of the agreement for sale only and between the same contracting parties to agreement for sale.

In the case in hand, the issue ofassured returns is on the basis ofcontractual obligations arising between the parties.

Then in case of Pioneer Urban Land and Infrastructure Limited & Anr.

V/s Union of India & Ors. (Writ Page 20 of 30 M HARERA P*GURUGRAI/ Petition (Civil) No.

Civil) No.

43 o12019) decided on 09.08.2019, it was observed by the Hon'ble Apex Court of the land that "... allottees who had entered into "assured return/committed returns' agreements with these developers, whereby, upon payment of a substantial portion of the total sale consideration upfront at the time of execution of agreement, the developer undertook to pay a cer!3i-n amount to allottees on a monthly basis from the date of executiorg,of&greement till the date of handing over borrowing' which became clear from the developer's annual returns in which the amount raised was shown as "commitment charges" undcr the head "financial costs".

As a result, such allottees were held to be "financial creditors" within the meaning of section 5[7) of the Code" including its treatment in books of accounts of the promoter and for the purposes of income tax.

Then, in the latest pronouncement on this aspect in case Iaypee Kensington Boulevard Apartments Welfore Association and Ors.

Vs.

NBCC (lndid) Ltd. and Ors. (24.03.2021-SC): MANU/ SC/0206 /2027, lhe same view was followed as taken earlier in the case of Pioneer Urban Land Infrastructure Ld & Anr. with regard to the allottees of assured returns to be financial creditors within the meaning of section 5(7) of the Code.

Then after coming into force the Act of 2016 w.e.f 01.05.2017, the builder is obligated to register the project with the authoriry being an Complaint Nos. and 707 of 2022 &7OA of 2022 V Page 21of30 SHARERA #b- arnuelrnrtr Complaint Nos. and 707 ot 2022 &708 of 2022 ongoing project as per proviso to section 3 (1) of the Act of 2017 read with rule 2(o) of the Rules, 201"7.

The Act of 2016 has no provision for re- writing of contractual obligations between the parties as held by the Hon'ble Bombay High Court i.n case Neelkamal Realtors Suburban Private Limited and Anr.

V/s Union of India & Ors., (supra) as quoted earlier. d earlier.

So, the respondent/builder can't takc a plea that there was no contractual obligation to pay the amount ofassured returns to the allottee after the Act of 2016 came into force or that a new agreement is being executed with regard to that fact, When there is an obligation of the promoter against an allottee to pay the amount of assured returns, then he can't wriggle out from that situation by taking a plea ofthe enforcement of Act of 2076, BUDS Act 2019 or any other law.

19.

It is pleaded on behalf of respondent/builder that after the Banning of Unregulated Deposit Schemes Act of 2019 came into force, there is bar for payment of assured returns to an allottee.

But again, the plea taken in this regard is devoid of merit.

Section 2(4) ofthe above mentioned Act defines the word 'deposit' as an amount of money received by way of an advance or loan or in any other form, by any deposit taker with a promise to return whether after a spectfied period or otherwise, either in cash or in kind or in the form of a specified service, wifh or without any benefit in the form of lnterest bonus, prortt or in any other form, but does not include [. an amount received in the course of, or for the purpose of, business and Page 22 of 30 (L HARERA MGURUGRAIV1 Complaint Nos. and 707 of 2022 &70A of 2022 bearing a genuine connection to such business including- ii. qdvance received in connection with consideration ofdn immovable property under an agreement or dffangement subject to the condition that such advance is adjusted against such immovable property as specified in terms of the agreement or arrangement 20.

A perusal of the above-mentioned definition of the term 'deposit' shows that it has been given the same meaning as assigned to it under the Companies Act,2013 and the same-plovides under section 2(311 includes any receipt by way of deposit or loan or in any other form by a company cateloyies of but does not include such cateloyies of a{nount as may be prescribed in consult in consultation with the Reserve Bank of tndia.

Similarlv rule 2fcl of the ank of lndia.

Similarly rule 2[c] of the Companies (Acceptance (of DepositsJ Rules, 2014 defines the meaning of deposit which includes any :ejpt of money by way of deposit or loan or in any other form by a company but does not include. ( tl i. as an advance, accounted for in any manner whatsoever, received in connection w[th considerotion for an immovable property i[. as an advance received and as allowed by any sectoral regulotor or in accordance with directions ofCentral or State Government; 21.

So, keeping in view the above-mentioned provisions of the Act of 2019 and the Companies Act 2013, it is to be seen as to whether an allottee is entitled to assured returns in a case where he has deposited substantial amount of sale consideration against the allotment of a unit with the builder at the time of booking or immediately thereafter and as agreed upon between them. fN/ Page 23 of 30 ffi ffi HARERA GURUGRAM 22.

The Government of India enacted the Banning of Unregulated Deposit Schemes Act, 2019 to provide for a comprehensive mechanism to ban the unregulated deposit schemes, other than deposits taken in the ordinary course ofbusiness and to protect the interest oFdcpositors and for matters connected therewith or incidental thereto as defined in section 2 [4) of the BUDS Act 2019 mentioned above.

23.

It is evident from the perusal ofsection 2(4)(1)(iil ofthe above-mentioned Act that the advances received in connection with consideration of an immovable property under an agreement or arrangement subject to the condition that such advances are adjusted against such immovable IE \) property as specified in terms of the agreement or arrangement do not fall within the term of deposit, which have been banned by the Act of 2 019.

24.

Moreover, the developer is also bound by promissory estoppel. estoppel.

As per this doctrine, the view is that if any person has made a promise and the promisee has acted on such promise and altered his position, then the person/promisor is bound to comply with his or her promise.

When the builders failed to honour their commitments, a number of cases were filed by the creditors at different forums such as Nikhil Me hta, Pioneer Urban Land and Infrastructure which ultimately led the central government to enact the Banning ofUnregulated Deposit Scheme Act, Z0l9 on3l.07 .2019 in pursuant to the Banning of Unregulated Deposit Scheme Ordinance, 2018.

However, the moot question to be decided is as to whether the Complaint Nos. and 707 of 2022 &7oB of 2022 h/ Page 24 of 30 ffi HARERA GURUGRAM Complaint Nos. and 707 of 2022 &708 of 2022 schemes floated earlier by the builders and promising as assured returns on the basis of allotment of units are covered by the abovementioned Act or not.

A similar issue for consideration arose before Hon'ble RERA Panchkula in case Baldev Gautam VS Rise Projects Prlvate Limited (RERA-PKL-2068-2079) where init was held on 11.03.2020 that a builder is liable to pay monthly assured returns to the complainants till possession of respective apartments stands handed over and there is no illegality in this regard.

25.

The definition of term 'deposit' as given in the IIUDS Act 2019, has the same meaning as assigned to it under the Companies Act 2013, as per section 2(4)(iv)(iJ i.e., explanation to sub-clause (iv), ln pursuant to powers conferred by clause 31 of section 2, section 73 and 7 6 read with sub-section 1 and 2 ofsection 469 ofthe Companies Ac|201,3, the Rules with regard to acceptance of deposits by the companies were framed in the year 2014 and the same came into force on 01.04.2014.

The definition I l{t ofdeposit has been.given under section 2 (c) of the above-mentioned Rules and as per clause;ii (b), as. i (b), as. alirance, acioynted for in any manner whatsoever received in connection with consideration for an immovable property under an agreement or arrangement, provided such advance is adjusted against such property in accordance with the terms ofagreement or arrangement shall not be a deposit.

Though there is proviso to this provision as well as to the amounts received under heading 'a'and'd' and Page 25 of 30 p ffi& HARERA Complaint Nos. and 707 of 2022 &708 of 2022 GURUGI?AI/ the amount becoming refundable with or without interest due to the reasons that the company accepting the money does not have necessary permission or approval whenever required to deal in the goods or properties or services for which the money is taken, then the amount received shall be deemed to be a deposit under these rules.

However, the same are not applicable in the case in hand.'l'hough it is contended that there is no necessary permission or.approval to take the sale consideration as advance and would be considered as deposit as per sub-clause 2[xv)(b) but the plea advanced in this regard is devoid of merit.

First of all, there is exclusion clause to section 2(xiv)(bJ whlch provides that unless specifically excluded under this clause.

Earlier, the deposits received by the companies or the builders as advance were considered as deposits but w.e.f .29.06.2016, it was provided that the money received as such would not be deposit unless specifically excluded under this clause.

A reference in this regard may be given to clause 2 of the First schedule of Regulated Deposit Schemes framed under section 2 (xv) of the Act of 2019 which provides as under:- (2) The following shall also be treated as Regulqted Deposit Schemes under this Act namely:- (a) deposits accepted under any scheme, or on orrongement registercd wtth any regulatory body in lndia constituted or estoblished under q statute; and (b) any other scheme as moy be notified by the Centrol Government under this Act.

26. s Act.

26.

The money was taken by the builder as deposit in advance against allotment of immovable property and its possession was to be offered Page 26 of30 (\, HARERA ffiGURUGRAM Complaint Nos, and 707 of 2022 &708 of 2022 within a certain period.

However, in view oftaking sale consideration by way of advance, the builder promised certain amount by way of assured returns for a certain period.

So, on his failure to fulfil that commitment, the allottee has a right to approach the authority for redressal of his grievances by way offiling a complaint.

27. lt is not disputed that the respondent is a real estate developer, and it had not obtained registration under the.iAct of 2016 for the proiect in question.

However, the proiect in which. i$.iadvance has been received by the it. r. developer from the allottee is an o.Ilgging pro.iect as per section 3 (1) ofthe Act of 2016 and, the same would fall within the jurisdiction ofthe authority for giving the desired relief to the complainant besides initiating penal proceedings.

So, the amount paid by the complainant to the builder is a regulated deposit accepted by the later from the former against the immovable property to be transferred to the allottee later on.

28.

On consideration ofdocuments available on record and submissions made by the complainant and the respondeng the authority is satisfied that the respondent is in contravention ofthe provisions ofthe Act.

The agreement executed between the parties on 1.5.11.2017, the possession ofthe subject unit was to be delivered within a period of 54 months with a grace period of6 months, from 1 September 2017, therefore, the due date ofpossession comes out to be i.e., 01.09.2022- The assured return is payable to the allottees on account of provisions in the BBA.

The assured return in this Page 27 of 30 r, llARERA ffiGURUGRAI/ F.II F.III Complaint Nos. and 707 of 2022 &7OB of 2022 case is payable as per "clause 32 of the agreement". greement".

Clause 32 of the agreement to sell clearly mentioned that the company has agreed to pay Rs.64,891/- per month by way of assured return to the allottee from 25.02.2017 till the date ofissue ofnotice ofpossession ofthe unit.

The said clause further provides that it is the obligation ofthe respondent promoter to pay the assured returns.

It is matter of record that the amount of assured return was paid by the respondent promoter till December 2021 but later on, the respondent refuse{.So.pay the same by taking a plea ofthe Banning of Unregulated Deposit Schemes Act, 2019.

But that Act of 2019 does not create a bar for payment of assured returns even after coming into operation and the payments made in this regard are protected as per section 2[4)(iiiJ of the above-mentioned Act.

29.

The respondent is directed to pay the outstanding accrued assured return amount as per clause 32 of the agreement to sell within 90 days from the date of this order after adjustment of outstanding dues, if any, from the complainant and failing which that amount would be payable with interest @ 8.75% p.a. till the date of actual realization.

Direct the respondent to not illegally offer possession without completion of construction of the super structure of office block as otherwise the same would be contrary to the terms agreed in the unit buyer's agreement.

Directthe respondentto adhere to the terms mentioned in the unit's buyer's agreement along with the annexure A of the agreement and to make offer ofpossession in compliance ofthe said terms.

V Page 28 of 30 I ffi& HARERA GURUGRAM 30.

The respondent has offered the possession of th e unit on22.02.2022 after receiving the occupation certificate d ated 24.L2.2021from the competent authority.

The occupation certificate is granted by the competent authority to the promoter only after the completion of the building when the civic infrastructure is complete.

Therefore, it is a valid offer of possession.

F.IV. ion.

F.IV.

Award the litigation cost to the tune ofRs.50,0OO/- in the favour of the complainant.

31.

The complainants are seeking above mentioned relielw.r.t. compensation.

Hon'ble Supreme Court ollndia in case titled as M/s Newtech Promoters ond Developers Pvt.

Ltd.

V/s State of Up & Ors.

2021-2022(1) RCR (C), 357 held that an allottee is entitled to clainr compensation & litigation charges under sections 12,14,18 and section 19 which is to be decided by the adjudicating officer as per section 71 and the quantum of compensation & litigation expense shall be adjudged by the adjudicating officer having due regard to the factors mentioned in section 72.

The adjudicating officer has exclusive jurisdiction to deal with the complaints in respect of compensation & legal expenses.

F.

Directions ofthe authority 32.

Hence, the authority hereby passes this order and issues the following directions under section 37 of the Act to ensure compliance of obligations cast upon the promoter as per the function entrusted to the authority under section 34(0: Complaint Nos. and 707 of 2022 &70A of 2022 V Page 29 of 30 ffiHARERA # arRuGRA[/ i.

The respondent is directed to pay the arrear ofassured return amount as per clause 32 of the agreement to sell from the date the payment of assured return has not been paid i.e., December 2021 till the date of issue ofnotice of possession ofthe unit. ii.

The respondent is directed to pay the outstanding accrued assured of this order after adju tstanding dues, if any, from the complainant and fail t amount would be payable with interest @ 8.75% realization. iii.

The responde ot the complainant which is not the buil 33.

This decision shall this order.

34.

Complaints stand di Dated: 19.10.202 3 Complaint Nos. and 707 of 2022 &708 of 2022 mentioned in para 3 of copy of this order shall be ,,1;l;*dn Member Haryana Real Estate Regulatory Authority, Gurugram Page 30 of 30 35.