Meta Pixel
CNR: --
DISPOSED

VED PRAKASH vs ILD MILLENNIUM PVT. LTD

Case NumberRERA-GRG-164-2019
Date of Filing--
Case TypeRERA-GRG
Last Hearing10 Feb 2023
StateHaryana
CityGurgaon
Year of Filing2019

Party Details

Petitioner
  • VED PRAKASH
Respondent
  • ILD MILLENNIUM PVT. LTD

Case Summary

VED PRAKASH filed Case No. RERA-GRG-164-2019 in the Haryana Real Estate Regulatory Authority (RERA) against ILD MILLENNIUM PVT. LTD. The case has undergone 16 hearings over 3 years and 3 months. The case was disposed of on 10 Feb 2023. 9 orders have been issued in this matter.

Hearing History (16)

  • 10FEB 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The present complaint has been filed on 31.01.2019 and reply on behalf of respondent was received on 18.01.2023. Succinct facts of the case as per complaint and annexures are as under: S. N. Particulars Details 1. Name and location of the project ILD Spire Greens, Sector 37 C, Gurgaon, Haryana 2. Nature of the project Residential group housing project  3. Project area 15.4829 acres 4. DTCP license no.                    13 of 2008 dated 31.01.2008 5. Name of licensee M/s Jubiliant Malls Pvt. Ltd. and 3 others 6. RERA Registered/ not registered Registered For 64621.108 sq mtrs for towers 2,6 and 7 vide no. 60 of 2017 issued on 17.08.2017 up to 16.08.2018 7. Apartment no. 1004, 10th floor Tower 7 (page no. 30 of complaint) 8. Unit area admeasuring 1355 sq. ft. (page no. 30 of complaint) 9. Date of builder buyer agreement 28.10.2014 (page no. 28 of complaint) 10. Due date of possession 28.10.2017 [as per possession clause] Note: Grace period is not allowed. 11. Possession clause   10.1 POSSESSION  “The Developer based on its present plans and estimates and subject to all just exceptions, contemplates to complete the construction of the said Building/said within three years from the date of execution of this agreement, with grace period of six month, unless there shall delay or there shall be failure due to reasons mentioned in Clauses 11.1, 11.2, 11.3 and Clause 41 or due to failure of Allottee(s) to pay in time the price of the said Unit along with other charges and dues in accordance with the schedule of payments given in Annexure-C or as per the demands raised by the Developer from time to time or any failure on the part of the Allottee(s) to abide by all or any of the terms or conditions of this Agreement. 12. Total sale consideration Rs. 66,92,755/- (as per agreement on page no. 31 of complaint) 13. Amount paid by the complainants Rs. 57,02,336/- 14. Occupation certificate 02.07.2021 15.  Offer of possession Not offered   The counsel for the complainant states that respondent is saying in its reply at page 6 that possession was offered vide letter dated 22.09.2021 through email whereas no such mail has been received so far by the complainant. The counsel for the respondent states that there is no evidence available with them regarding the service of above said mail or any postal receipt regarding the offer of possession. Although the OC has been received on 02.07.2021 that too almost 3 years after the due date.  The counsel for the complainant states that  they filed the complaint on 31.01.2019 for seeking refund as there was inordinate delay in the completion of the project.    The counsel for the respondent states that since the OC of the project has been received, the respondent is willing to hand over the possession. However, the counsel for the complainant states that in the reply at page 11, the respondent himself has stated that work of the concerned tower where the unit of the complainant is situated is almost complete and possession shall be offered very soon. The counsel for the complainant stated that they are no more willing and cannot be forced to wait endlessly. In the light of above facts,  the refund is allowed alongwith prescribed rate of interest i.e. 10.60% per annum from the date of deposit of amount till its realization.   Matter stands disposed off.  Detailed order will follow. File be consigned to the registry.

    Stage: DISPOSED

  • 18JAN 2023
    Hearing

    Judge: VIJAY KUMAR GOYAL ASHOK SANGWAN

    Matter to come up on 10.02.2023 for final arguments.

    Stage: PENDING

  • 29NOV 2022
    Hearing

    Judge: VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA

    The present complaint has been filed on 31.01.2019 and no reply has been received till now.  On the last date of hearing dated 31.08.2022 Advocate Shri Pankaj Chandola had appeared and was directed to file reply/written submission with a cost of Rs. 5,000/- to be paid to the complainant. The authority allowed time to file the reply but despite specific direction it has failed to comply with the orders of the authority. Case has been called out but none has appeared on behalf of the parties. Reply has not been filed by the respondent till date.  The respondent is directed to file reply within 15 days in the registry with an advance copy to the complainant with cost of Rs.10,000/- to be paid to the complainant failing which defence of the respondent shall be struck off. Matter to come up on 18.01.2023 for further proceedings.

    Stage: PENDING

  • 31AUG 2022
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL

    File was been received from the Adjudicating Officer in view of the judgment dated 11.11.2021 passed by the Apex Court in case titled as M/s Newtech Promoters and Developers Pvt Ltd Versus State of U.P. and Ors. (2021-22(1) RCR(Civil) 357) wherein it was held that the matters regarding refund and interest under sec. 18(1) are to be decided by the authority and matters regarding adjudging compensation to be decided by the adjudicating officer.                 The complaint was received on 31.10.2019 and the reply on behalf of respondent has not been received till date. It is matter of regret that even after getting so many opportunities the respondent has not filed reply. Last opportunity is granted to respondent to file reply/written submission, within one week with an advanced copy to the complainant failing which the matter would be proceeded ex parte. The respondent is also directed to pay cost of Rs. 5,000/- to the complainant.                Matter to come up on 29.11.2022  for arguments and order.

    Stage: PENDING

  • 4MAR 2022
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL

    MATTER IS ADJOURNED TO 31.08.2022.

    Stage: PENDING

  • 1SEP 2021
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL

    MATTER IS ADJOURNED TO 04.03.2022.

    Stage: PENDING

  • 21MAY 2021
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL

    MATTER IS ADJOURNED TO 01.09.2021

    Stage: PENDING

  • 5APR 2021
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR VIJAY KUMAR GOYAL

    MATTER IS ADJOURNED TO 21.05.2021.

    Stage: PENDING

  • 21JAN 2021
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR VIJAY KUMAR GOYAL

    MATTER IS ADJOURNED TO 05.04.2021

    Stage: PENDING

  • 13OCT 2020
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR

    MATTER IS ADJOURNED TO 21.01.2021

    Stage: PENDING

  • 20AUG 2020
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR

    MATTER IS ADJOURNED TO 13.10.2020.

    Stage: PENDING

  • 26MAY 2020
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR

    MATTER IS ADJOURNED TO 20.08.2020.

    Stage: PENDING

  • 7APR 2020
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR

    MATTER IS ADJOURNED TO 26.05.2020.

    Stage: PENDING

  • 18FEB 2020
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR SUBHASH CHANDER KUSH

    CASE IS ADJOURNED TO 07.04.2020.

    Stage: PENDING

  • 18DEC 2019
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR SUBHASH CHANDER KUSH

    Case is adjourned to 18.2.2020.

    Stage: PENDING

  • 5NOV 2019
    Hearing

    Judge: K K KHANDELWAL SAMIR KUMAR SUBHASH CHANDER KUSH

    THE CASE IS FIXED FOR HEARING ON 18.12.2019

    Stage: FIRST HEARING

Orders (9)

Judgement DetailsView full order PDF ↗

HARERA ffiGURUGRAM Complaint No.

164 of2019 BEFORE THE HARYANA REAL ESTATE REGULATORY AUTHORITY, GURUGRAM Complaintno. | 164 ofZOlg First date ofhearing: 0S,11.2019 Date of decision ,t IO,OZ.ZOZT Ved Prakash S/o Amar Singh R/o: Mohalla Kasthe Wala, Ward no.

6, Sohna- Gurugram Complainant Versus M/s ILD Millennium pvt.

Ltd.

Regd.

Office at: - 901, Sohna Road, Near Subhash Chowk, D1 Block Malibu Town, Sector-47, Gurugram, Haryana Respondent COMM: Shri Sanjeev Kumar Arora APPEAMNCE: Shri Sushil Yadav Member Shri Himanshu Singh Advocate for the complainant Advocate for the respondent ORDER 1.

The present complaint dated 31.01.2019 has been filed by rhe complainant/allottee under section 31 of the Real Estate (Regulation and Development) Act, 2016 (in short, the Act) read with Rule 28 ofrhe Haryana Real Estate (Regulation and Development) Rules, 2017 (in short, the RulesJ for violation of section 11(4) (a) of the Act wherein it is inter alia prescribed that the promoter shall be responsible for all obligations, responsibilities and functions under the provision of the Act or the rules and regulations made there under or to the allottee as per the agreement for sale executed inter se.

A.

Unit and proiect related details Page 1 of 14 HARERA MGURUGRAM Complaint No.

164 of 2O7g 2.

The particulars of unit details, sale consideration, the amount paid by the complainant, date of proposed handing over the possession, delay period, if any, have been detailed in the following tabular form: S.

No.

Heads Information 1.

Name and location of the proiect ILD Spire Greens, Sector 37 C, Gurgaon, Haryana 2.

Nature ofthe project Residential group housing project 3.

4.

Project area 15.4829 acres 13 0f 2008 dated 31.01.2008 DTCP license no.

5.

Name of license holdei- ta M/s ]ubiliant Malls pvt.

Ltd. and 3 others 7.

6.

RERA Registered/ registered not Registered For 64621.108 sq mtrs for towers 2,6 and 7 vide no.60 of 2017 issued on 17.08,2017 up to 16.08.2018 Apartment no. rtment no.

1004, 10th floor Tower 7 (page no.

30 of complaintl B, Unit measuring 1355 sq. ft. (page no.

30 ofcomplaint) 28.L0.2014 (page no.

28 ofcomplaint) 9.

Date of builder buyer agreement 10.

Possession clause 10.1 POSSESSTON "The Developer based on its present plans and estimates and subject to all just exceptions, contemplates to complete the construction of the said Building/said within three years from the date of execution of this agreement, with grace period of six month, unless there shall delav or there Page 2 of 74 ffiHARERA ffi, eunuennvr B.

Complaint No.

764 of 2019 I shall be failure due to reasons mentioned in Clauses 7L.L, 1i..2, | 11.3 and Clause 4t or due to failure of Allottee[s) to pay in time the price of the said Unir along with other charges and dues in accordance with the schedule of payments eiven in ] Annexure-C or as per the demands raised by rhe Developer from time to time or any failure' on the part of the Allotree(s) to abide by all or any of the terms or conditions of this Agreement. (emphasis supplied) 11.

L2.

Total sale consideration Rs.66,92,755/ - (as per agreement on page no.31 ofcomplaintJ Amount paid by the complainant Rs.57,02,336/ - (as alleged by complainant) 13.

Due date ofpossession 71,.02.201.8 Icalculated as per possession clausel 1_4.

Occupation certificate 02.07.2027 (page no.

20 ofreply) 15.

Offer ofpossession 22.O9.2027 (page no.

23 ofcomplaint) Facts ofthe complaint That on the representations made by the respondent, the complainant made booking on 06.07.ZOl2 of a unit and paid a booking amount of Rs.

2,00,000/-.

The respondent issued provisional allotment letter dated 28.10.2014 to him and allotted the above-mentioned unit.

Page 3 of14 HARERA ffi GURUGRAM 6.

164 of 2019 4.

That as per clause 10.1 of the said agreement, the respondent was under an obligation to handover the possession of the flat booked by the complainant, within 3 years from the date of execution of agreement i.e. ement i.e., on or before 28.10.2017 with an additional grace period of six months i.e.,28.04.2018.

That as on 20.72.201,4 the complainant had already made a total payment of Rs.

57,02,336/- out of total basic sale price of Rs. s7,58,7s0/-.

That the complainant made almost full payment of the basic sale price of the allotted unit as early as on 20.L2.2014 and has not been handed over the possession of the unit allotted in the said project.

7.

That complainant waited long enough for the respondent to handover 8.

9. the complete unit in the said project.

Even as on the date of filing ofthe complaint, the respondent has failed to complete the said project in all respects and has further not yet offered the possession to him.

That the complainant has invested all the hard-earned money in the said proiect, in order to get the possession and start residing therein.

However, the respondent clearly failed to honour its commitments under the representations made and also the terms and conditions of the builder buyer agreement dated 28.lO.ZO1,4.

That as on date almost 6 years have passed since the complainant made the booking in the said project of the promoter.

However, till date the respondent has failed to complete the project and handover the possession ofthe allotted unit to the complainant.

The complainant has lost all hope of delivery of possession as said date has long passed.

The complainant is no longer interested in retaining the unit in the said project and which has still not been completed and have lost all trust on the respondent.

Page 4 of 74 HARERA ffi GURUGRAM Complaint No.

164 of 2Ot9 10.

That by not refunding the amount ofthe complainan! the promoter- developer has indulged in unfair trade practise.

C.

Reliefsought by the complainant: 11.

The complainant has sought the following relief: o Refund the amount of Rs.

57,02,336/- with interest @ l8o/o p.a. l8o/o p.a. which rate of interest is equivalent to the rate of interest as charged by the respondent from the customers in the event of delay ln making payments.

Pay compensation of Rs.20,00,000/- to the complainant for undergoing the mental agony and harassment at the hands of promoter developer due to the unfair trade practice and deficient services of gross delay in completing the project and sitting tight on his money. .

Direct the opposite party to compensate the complainant of the legal costs in instituting the present complaint.

12.

On the date of hearing, the authority explained to the respondent/promoter about the contraventions as alleged to have been committed in relation to section 11(4J [a) ofthe Act to plead guilry or not to plead guilty.

D.

Reply by the respondent.

13, That after having keen interest in the pro.iect constructed by the respondent, the complainant decided to book a unit in its proiect and paid a booking amount of Rs.

2,00,000/- to it.

14.

That the respondent vide letter dated 28.10.2014 issued a provisional allotment letter to the complainant wherein allotting flat no.

1004, admeasuring super area 1355 sq. ft. block/tower_ no.

7, floor 16th In Page 5 of 14 HARERA ffiGURUGRAII complaint No.

164 of2O19 the above said project subject to terms and conditions in the final allotment letter/booking form/buyer agreement or any other document.

15.

That on 28.!0.201.4, a builder buyer agreement was executed between the complainant and the respondent wherein allotted unit no.

1004, on 1oth floor, block 4, tower-7, unit type 2 BR, admeasuring 13 55 super area for a total amount payable of Rs.

66,92,755/- and further agreed to pay additional amount of Rs.67,750/-, for preferential location charges.

The complainant was aware ofthe project and was also satisfied with every proposal deemed necessary for its development.

16. pment.

16.

That time was essence in respect to the allottees obligation for making the respective payment and, as per the agreement so signed and acknowledged.

The allottee was bound to make the payment of installment as and when demanded by the respondent.

17.

That the complainant has failed to pay the entire instalment as per the agreed payment schedule.

It is evident that the complainant was well aware of the payment schedule and despite after being aware of the same, he failed to make any such payments on time.

18.

That the respondent has been issued with an occupation certificate vide Memo no.

Zp-370 Vot- IVIAD(RA)/202t/75763 dated0Z.O7.2021 for the tower 6 and 7 of the project of the respondent.

It is further important to mention that the unit of the complainant is in tower -7 of the project and the respondent is making efforts to complete the project as soon as possible and hand over the possession to the complainant in a short span of time.

19.

That as soon as after receiving the occupation certificate for the tower 6 & 7 in the project, the respondent issued offer of possession to the Page 6 of 74 ffiHARERA H,eunu-ennt,r Complaint No.

164 of 2019 complainant vide letter Z2-09-ZOZI on e-mail subiect to payment of remaining amount due at his end to it.

20.

That the project of respondent got delayed due to reasons beyond its control.

The major reason for delay for the construction and possession of project is lack of infrastructure in the said area.

The twenty_four_ meter road was not completed on time.

Due to non-construction of the sector road the respondent faced many hurdles.

21.

That due to ban levied by the competent authorities, the migrant labour was forced to return to their native places creating an accurate shortage of labourers in NCR.

22.

That project was not completed within time due to the several other reasons beyond the control of the respondent such as interim orders dated t6.07.2072, 3L.07.2072 and, 21,.08. d, 21,.08.20t2 0f rhe Hon,ble High Court of Punjab and Haryana in CWp NO.

20032/2OOg where ground water extraction was banned in Gurgaon, orders passed by National Green Tribunal to stop construction to prevent emission of dust in month ofApril,2015 and again in November 2016, adversely affecting the progress of the proiect.

23.

That the demonetization and new tax law i.e., GST, affected the development work of the project.

The respondent has intention to complete the project soon for which it is making every possible effort in the interest of allottees of the project.

24.

The Covid-19 pandemic resulted in serious challenges for the project with no available labourers, contractors etc. for the construction of the Project.

The Ministry of Home Affairs, GOI vide notification dated March24,2020 bearing no: 4O-3/2020- DM-l(A) recognized rhat India was threatened with the spread of Covid-19 pandemic and ordered a complete lockdown in the entire country for an initial period of 21 days Page 7 of 14 HARERA ffi.

GURUGRAM Complaint No. t64 of 21tg which started on March 2S,ZO2O.

By virtue of various subsequent notifications the Ministry of Home Affairs, GOr further extended the lockdown from time to time and till date the same continues in some or the other form to curb the pandemic.

Various State Governments, including the Government of Haryana have also enforced various strict measures to prevent the pandemic including imposing curfew, lockdown, stopping all commercial and construction activities.

Pursuant to the issuance of advisory by the GOI vide office memorandum dated May 13, ZOZO, regarding extension of registrations of real estate projects under the provisions of the RERA Act,2016 due to,,Force Ma.ieure,,, the Haryana Real Estate Regulatory Authority also extended the registration and completion date by 6 months for all real estate proiects whose registration or completion date expired and or was supposed to expire on or after March 25,2020.

25. ,2020.

25.

That as development of the proiect delayed due to the reasons beyond the control ofthe respondent.

Hence the complainant is not entitled for refund in any way and the same was agreed into between the parties under clause 7L.1,, 71,.2,11.3 and 40 of the buyers agreemenL 26.

Copies of all the relevant documents have been filed and placed on record.

Their authenticity is not in dispute.

Hence, the complaint can be decided on the basis of those undisputed documents and submissions made by the parties.

E.

Jurisdiction of authority 27.

The authority observes that it has territorial as well as subject matter jurisdiction to adjudicate the present complaint for the reasons given below.

I Territorial iurisdiction Page B of 14 ffiHABERA ffi,eunuennM Complaint No.

764 of 2079 28.

As per nortfication no.

1,/gZ/2017_LTCP dated 14.12.20t7 issued by Town and Country planning Department, the jurisdiction of Real Estate Regulatory Authority, Gurugram shall be entire Gurugram District for all purpose with offices situated in Gurugram.

In the present case, the project in question is situated within the planning area of Gurugram District.

Therefore, this authority has complete territorial.iurisdiction to deal with the present complaint.

II Subiect matter iurisdiction 29.

Section 11(4)(a) ofthe Act, 2016 provides thar the promoter shall be responsible to the allottee as per agreement for sale.

Section 11[4J(aJ is reproduced as hereunder: Section 11(4)(a) Be responsible for oll obligations, responsibilities and functions under the provisions of this Act or the rules ond regulotions made thereunder or to the ollottees qs per the qgreemeitfor sale, or to the ossociation ofollottees, os the cose ma, be, tilt tie convivance ofall the apartments, plots or buildings, ai the cose moy be,-to the allottees, or the common areas to the associotion ol ittottees or the competent quthority, as the cose may be; Section 34-Functions of the Authority: 344 ofthe Act provides to ensure com ensure compliance ofthe obligations cost upon the promoters, the allottees and the riol estate'agents under this Act and the rules and regulotions mqde thereundir.

30.

So, in view ofthe provisions ofthe Ac1 quoted above, ttre autnority tras complete iurisdiction to decide the complaint regarding non_ compliance of obligations by the promoter leaving aside compensation which is to be decided by the adjudicating officer if pursued by the complainant at a Iater stage.

F.

Findings on the obiections raised by the respondent.

F.l Obiection regarding delay due to force maieure.

Page 9 of14 HARERA GURUGRAM Complaint No.

764 of 2019 31 The respondent-promoter raised the plea that the construction ofthe project was delayed due to force maieure condrtions such as nationar lockdown, shortage of labour due to covid 19 pandemic, demonetization, stoppage of construction due to various orders and directions passed by hon,ble NGT, New Delhi, Environment pollution (Control and prevention) Authority, National Capital Region, Delhi, Haryana State pollution Control Board, panchkula and various other authorities from time to time but all the pleas advanced in this regard are devoid of merit.

As per the possession clause 10.1 0f the buirder buyer agreement, the possession of the said unit was to be delivered within three years with grace period of 6 months from the date execution of agreement.

The builder buyer agreement between the parties was executed on 2g.10.2 014.

So, the due date comes out to be 11.02.2018 including grace period of 6 months.

The authority is of the view that the events taking place after the due date do not have any impact on the project being developed by the respondent/promoter.

Thus, the promoter/ respondent cannot be glven any leniency based on aforesaid reasons. [t is well settled principle that a person cannot take benefit of his own wrongs.

G, Findings on the relief sought by the complainant. mplainant.

Relief sought by the complainant: The complainant had sought following relief(sl: i.

Refund the amount of Rs.

57,02,336/_ with interest @ 1gol0 p.a. which rate ofinterest is equivalent to the rate ofinterest as charged by the respondent from the customers in the event ofdelay in making payments.

Page 10 of 14 33.

HARERA M GURUGRAIV Complaint No.

164 of2019 32.

Keeping in view the fact that the allottee complainant wishes to withdraw from the proiect and is demanding return of the amount received by the promoter in respect of the unit with interest on its failure to complete or inability to give possession of the unit in accordance with the terms ofagreement for sale or duly completed by the date specified therein.

The matter is covered under section 1g( 1) ofthe Act of 2 016.

The occupation certificate /part occupation certificate of the buildings/towers where allotted unit of the complainant is situated was received after filing of application by the complainant for return of the amount received by the promoter on his failure to complete or unable to give possession of the unit in accordance with the terms of the agreement for sale or duly completed by the date specified therein.

The complainant-allottee has already wished to withdraw from the project he has become entitled his right under section 19(4J to claim the refund of amount paid along with interest at prescribed rate from the promoter as it failed to comply or unable to give possession of the unit in accordance with the terms of agreement for sale.

Accordingly, the promoter is Iiable to return the amount received by him from the allottee in respect of that unit with interest at the prescribed rate.

This is without prejudice to any other remedy available to the allottee including compensation for which he may file an application for ad.iudging compensation with the adjudicating officer under sections 71 &TZread with section 31(1) of theActof 20L6. ctof 20L6.

Further in the judgement ofthe Hon'ble Supreme Court oflndia in the cases of Newtech Promoters and Developers private Limited Vs State ofU.P. and O rs.20Z|-2O22(L) RCR (c ), 357 reiterated in case 34.

Page 11 of 14 HARERA ffi GUI?UGRAI/ of M/s Sana Realtors private others SLP (Civil) No.

13005 observed as under: Complaint No.

L64 of 201.9 Limited & other Vs of 2020 decided on Union of India & 72.05.2022 it was 25.

The unqualified right of the allottee to seek refund ret'erred under Section 1B(1)(a) qnd Section 19(4) of the Act is not depe-ndent on ony contingencies or stipulations thereof.

It oppeors thqt the legislature hos consciously provided this right of refund on de.oid u, on unconditional absolute right to the ollottee, if the promoter foils to give possession of the apartment, plot or building within t;e time stipulated under the terms ofthe agreement regardless ofunforeseen events or stay orders ofthe Court/Tribunal, which is in either wav not attributoble to the allottee/home buyer, the promoter is undir an obligation to refund the amount on demand with interest ot the rote prescribed by the State Government including compensation in the manner provided under the Act with the proviso thot if the allottee does not wish to withdrow from the projec, he shalt ie entitled Jbr interestfor the period ofdelay till handing over possession at the rote prescribed.

35.

The promoter is responsible for all obligations, responsibilities, and functions under the provisions of the Act of 2016, or the rules and regulations made thereunder or to the allottee as per agreement for sale under section 11(4)[aJ.

The promoter has failed to complete or unable to give possession of the unit in accordance with the terms of agreement for sale or duly completed by the date specified therein. d therein.

Accordingly, the promoter is liable to the allottee, as he wishes to withdraw from the project, without prejudice to any other remedv available, to return the amount received by him in respect of the unit with interest at such rate as may be prescribed.

36 This is without prejudice to any other remedy availabre to the alrottee including compensation for which allottee may file an application for adjudging compensation with the adiudicating officer under section 71 read with section 31[1) ofthe Act of2016.

Page 12 of 14 HARERA MGURUGRAM Complaint No.

1.64 of2019 37.

The authority hereby directs the promoter to return the amount received by him i.e., Rs.

57,02,336/- with interest at the rate of 10.60% (the State Bank of India highest marginal cost of lending rate (MCLR) applicable as on date +2%) as prescribed under rule 1S ofthe Haryana Real Estate (Regulation and Development) Rules,2017 from the date of each payment till the actual date of refund of the amount within the timelines provided in rule 16 of the Haryana Rules 2017 ibid. ii.

Pay compensation of Rs.

ZO,00,OOO/- to the complainant for undergoing the mental agony and harassment at the hands of promoter developer due to the unfair trade practice and deficient services ofgross delay in completing the proiect and sitting tight on his money. iii, Direct the opposite party to compensate the complainant of the legal costs in instituting the present complaint.

38.

The complainant in the aforesaid relief is seeking relief w.r.t compensation.

Hon'ble Supreme Court of India in civil appeal titled as M/s Newtech Promoters and Developers pvt.

V/s State of Up & Ors. (Civil appe al nos.67 45-67 49 of 2021, decided o n tl .1.1 .2021.), has held that an allottee is entitled to claim compensation under sections 12, 14, 18 and section 19 which is to be decided by the ad. by the ad.iudicating officer as per section 71 and the quantum of compensation shall be adjudged by the adjudicating officer having due regard to the factors mentioned in section 72.

The adjudicating officer has exclusive jurisdiction to deal with the complaints in respect of compensation.

Therefore, the complainant is advised to Page 13 of 14 I} HARERA #GuRuGRAM approach the adiudicating compensation Complaint stands di Complaint No.

L64 of ZOlg officer for seeking the relief of dent to comply with failing which legal H.

Directions ofthe authority 39.

Hence, the authority hereby passes this order and issues the following directions under section 37 of the Act to ensure compliance of obligations cast upon the promoter as per the function entrusted to the authority under section 34(0: l.

The respondent/prom is directed to refund the entire amount of Rs.

57,0 the complainant along with prescribed rate of in 0.600/o p.a. as prescribed under rule 15 ofthe tion & Development) Rules, 2017 t till the date ofrefund ofthe dep A period the dire consequen ll.

40.

47.

F,e be consisneffi 'ru}i x kq GURUGR llaryana Real Estate Regulatory Authority, Gurugram Date* L0.o2.2023 amount. ow.

PaEe 14 of 14