Meta Pixel
CNR: --
FIRST HEARING

ASHOK KUMAR JAIN AND SUMAN LATA JAIN vs ROSHNI BUILDERS PRIVATE LIMITED

Case NumberRERA-GRG-4426-2024
Date of Filing--
Case TypeRERA-GRG
Last Hearing4 Mar 2025
StateHaryana
CityGurgaon
Year of Filing2024

Party Details

Petitioner
  • ASHOK KUMAR JAIN AND SUMAN LATA JAIN
Respondent
  • ROSHNI BUILDERS PRIVATE LIMITED

Case Summary

ASHOK KUMAR JAIN AND SUMAN LATA JAIN filed Case No. RERA-GRG-4426-2024 in the Haryana Real Estate Regulatory Authority (RERA) against ROSHNI BUILDERS PRIVATE LIMITED. The case has undergone 4 hearings over 4 months. The case is currently pending. 4 orders have been issued in this matter.

Hearing History (4)

  • 4MAR 2025
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN

    Matter is disposed of.

    Stage: DISPOSED

  • 25FEB 2025
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN

    Due to lack of quorum, the matter is adjourned to 04.03.2025 for the purpose as already fixed.

    Stage: PENDING

  • 19NOV 2024
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN

    The present complaint has been received on 13.09.2024 and registered as complaint no. 4426 of 2024 but the reply is not received on till date. The proxy counsel for the complainant seeks a short adjournment as the main arguing counsel is not available today.  Request is allowed as the counsel for the respondent has no objection to it. Matter to come up  on 25.02.2025 for further proceedings.

    Stage: PENDING

  • 10OCT 2024
    Hearing

    Judge: VIJAY KUMAR GOYAL

    The present complaint has been received on 13.09.2024 and registered as complaint no. 4426 of 2024 but the reply is not received on till date. The counsel for the complainant has filed an application on 13.09.2024 under section 36 and 37 of the Act of 2016 requesting to direct the respondent not to lease out the commercial space of the complainants and execution of conveyance deed in favour of the complainants as the stamp duty and registration charges have already been paid by the complainants. On 04.10.2024, the counsel for the respondent has filed a reply to the application filed by the complainants in which it is mentioned that the leasing out of the unit is as per clause 1.19 of the buyer’s agreement and lease facilitation agreement dated 31.01.2024. The counsel for the complainant is seeking directions to the respondent not to lease out the unit , to reconstruct the wall of the unit and also to execute the conveyance deed in favour of the complainant. The counsel for the complainant states that physical possession of the unit has been handed over on 31.1.2024 (page 84 of the complaint) and fitting and fixtures in is in accordance with the plans and specifications mentioned in the buyer agreement. The counsel for the complainant further states that  they have received the letter of proposal for leasing out of the unit  on 8.4.2024 but the complainant refused to accept the same  vide e-mail dated 28.7.2024. The counsel for the respondent states that the relief sought by the complainant in the application u/s 36 of the Act, is same as the relief sought in the main complainant and this application may not be allowed.  Further states that proposal to lease out the unit is as per agreed  terms and conditions of the  BBA and facilitation agreement dated 31.1.2024. Part arguments heard. Matter to come up before Full bench on 19.11.2024 for further proceedings.

    Stage: FIRST HEARING