Meta Pixel
CNR: --
PENDING

ASHOK SINGAL vs OCEAN SEVEN BUILDTECH PVT. LTD.

Case NumberRERA-GRG-4817-2021
Date of Filing--
Case TypeRERA-GRG
Last Hearing19 Nov 2024
StateHaryana
CityGurgaon
Year of Filing2021

Party Details

Petitioner
  • ASHOK SINGAL
Respondent
  • OCEAN SEVEN BUILDTECH PVT. LTD.

Case Summary

ASHOK SINGAL filed Case No. RERA-GRG-4817-2021 in the Haryana Real Estate Regulatory Authority (RERA) against OCEAN SEVEN BUILDTECH PVT. LTD.. The case has undergone 14 hearings over 2 years and 10 months. The case is currently pending. 13 orders have been issued in this matter.

Hearing History (14)

  • 19NOV 2024
    Hearing

    Judge: VIJAY KUMAR GOYAL ASHOK SANGWAN

    Order pronounced. i.               The termination of the allotted unit is set aside. ii.             The respondent is directed to re instate the allotted unit or if the same is not available then allot an alternate unit of the same size, similar location and same price as originally booked by the complainant and execute the BBA within a period of 60 days. iii.          The respondent/promoters are directed to pay interest to the complainant against the paid-up amount at the prescribed rate of 11.10% p.a. for every month of delay from the due date of possession i.e., 30.05.2022 till actual handing over of possession or offer of possession plus two months after obtaining occupation certificate from the competent authority, whichever is earlier, as per section 18(1) of the Act of 2016 read with rule 15 of the rules.             Detailed order will follow. Matter stands disposed off.

    Stage: DISPOSED

  • 12NOV 2024
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN

    Order not pronounced today. Matter to come up on 19.11.2024 for pronouncement of order.

    Stage: PENDING

  • 3SEP 2024
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN

    The present complaint was filed on 06.12.2021. Despite multiple opportunities to the respondent, the respondent has failed to file reply and in view of the same, the defence of the respondent was struck of by the authority vide order dated 08.12.2023. It was further ordered that interim orders for not creating third party rights in respect of the unit of the complainant shall remain in force. The succinct facts of the case are as under: S. No. Particulars Details 1. Name of the project Expressway Towers, Sector 109, Gurugram, Haryana. 2. Project area 7.5 Acres 3. Nature of the project Affordable housing project 4. DTCP license no. 06 of 2016 dated 16.06.2016 License valid till 15.06.2021 Licensed area 7.5 acres License holder Sh. Shree Bhagwan C/o M/s Ocean Seven Buildtech Pvt. Ltd. 5. HRERA registered/ not registered Registered vide no. 301 of 2017 dated 13.10.2017 HRERA registration valid up to 12.04.2022 (Including 6 months COVID extension) 6. Building plan approval dated 26.09.2016 7. Environment clearance dated 30.11.2017 8. Allotment letter issued in favour of complainant on 20.05.2017 (Page no. 49 of complaint)  9. Unit no. 1601, 16th floor, Tower 2 (Page no. 58 of complaint)  10. Unit admeasuring 644 sq. ft. of carpet area along with 100 sq. ft. of balcony area [Page no. 58 of the complaint] 11. Builder buyer agreement 25.05.2019 [Page no. 53 of complaint] 12. Possession clause as per clause 5.2 of the agreement The Company shall sincerely endeavour to complete the construction and offer the possession of the said unit within five years from the date of the receiving of license (“Commitment Period”), but subject to force majeure clause of this Agreement and timely payment of installments by the Allottee(s), However In case the Company completes the construction prior to the period of 5 years the Allottee shall not raise any objection in taking the possession after payment of remaining sale price and other charges stipulated in the Agreement to Sell. The Company, on obtaining certificate for occupation and use by the Competent Authorities shall hand over the said unit to the Allottee for his/her/their occupation and use, subject to the Allottee having complied with all the terms and conditions of the said Policy and Agreement to Sell and payments made as per Payment Plan. It is further agreed by the Allottee that the Developer shall not be liable for delay in completion of construction, in case of force majeure condition and/or the delay is caused due to non-completion of construction of said Complex/building/unit. In the event if a number Allottee(s) are not paying due installments on time or a number of Allottee(s) has withdrawn their application after allotment of unit or a number of units has been cancelled due to nonpayment of due installments or otherwise… [Page 65 of complaint] 13. Possession clause 1(IV) of the Affordable Housing Policy, 2013 All such projects shall be required to be necessarily completed within 4 years from the approval of building plans or grant of environmental clearance, whichever is later. This date shall be referred to as the “date of commencement of project” for the purpose of this policy. The licenses shall not be renewed beyond the said 4 years period from the date of commencement of project. 14. Due date of possession 30.05.2022 (calculated from the date of environment clearance dated 30.11.2017 being later + 6 months as per HARERA notification no. 9/3-2020 dated 26.05.2020 for the projects having completion date on or after 25.03.2020)   15. Total consideration  Rs.26,26,000/- [As per clause 4.1 of BBA at page no. 58 of complaint] 16. Amount paid by the complainant Rs.27,15,144/- [As alleged by the complainant at page no. 9 of complaint]    17. Occupation certificate Not obtained 18. Offer of possession Not offered 19. Cancellation notice 02.09.2021 (Page no. 108 of complaint) 20. Legal notice send by the complainant with regard to restoration of allotment of the subject unit 01.10.2021 [Page no. 113 of complaint] 21. Reply to the aforesaid legal notice send by the complainant 10.10.2021 (Page no. 117 of complaint) The counsel for the complainant states that he is seeking possession of the allotted unit and the construction of the project is yet not been completed. The counsel for the respondent states that the complainant is defaulter due to non-payment of outstanding dues. Arguments  heard. Order reserved. However in the interest of justice, the respondent may file written arguments within a period of 2 weeks with an advance copy to the counsel for the complainant. Matter to come up on 12.11.2024  for pronouncement of order.

    Stage: RESERVED

  • 21MAY 2024
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN

    The present complaint was filed on 06.12.2021. Despite multiple opportunities to the respondent, the respondent has failed to file reply and in view of the same, the defence of the respondent was struck of by the authority vide order dated 08.12.2023. It was further ordered that interim orders for not creating third party rights in respect of the unit of the complainant shall remain in force. Case has been called out but no one has appeared on behalf of the respondent. Matter to come up on 03.09.2024 for further proceedings.

    Stage: PENDING

  • 15MAR 2024
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The matter is adjourned to 21.05.2024 before the full bench for further proceedings.

    Stage: PENDING

  • 8DEC 2023
    Hearing

    Judge: ASHOK SANGWAN

    Matter is adjourned to 15.03.2024.

    Stage: PENDING

  • 20OCT 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The court is adjourned today i.e. 20.10.2023 due to power cut in the HARERA Gurugram office. Matter to come up on 08.12.2023  for the purpose  already fixed.

    Stage: PENDING

  • 28JUL 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The present complaint was filed in 2021. Due to non-appearance of the respondent, a direction vide order dated   03.03.2023 was issued by the authority for issuance of public notice for its presence for this date. The publication has since been made in the newspaper “Dainik Bhaskar” and “Hindustan Times” made by the registry of the authority. The counsel for the complainant states that they have paid 100% of the total sale consideration but still the respondent has cancelled the unit in September 2021.  Further requests that the orders dated 08.03.2022 of the authority regarding non creation of third party rights should continue.  The respondent is hereby directed not to create third party rights as per the directions of the authority dated 08.03.2022 till the final decision of the case. The proxy counsel for the respondent states that main arguing counsel is  not available  due to some other engagement, hence seeking a short adjournment.  Request is allowed. The respondent is directed to file reply alongwith previous cost within a period of 3 weeks with an advance copy to the complainant failing which additional cost of Rs.5000/- shall be imposed upon the respondent.  Last opportunity is being granted. In case reply is not filed within the time allowed, the defence of the respondent may be struck off. The proxy counsel for the respondent states that they have submitted a plan regarding completion of the project in the office of Town and Country Planning Department Chandigarh and as per that, the project is  to be completed within one year i.e  by July 2024. They are further directed to submit the said plan and correspondence with DTCP in the authority also before the next date of hearing. Matter to come up on 20.10.2023 for further proceedings.

    Stage: PENDING

  • 3MAR 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The above complaint alongwith CR bearing Nos. 4218/2021,  4221/2021, 4219/2021,  4222/2021, 4217/2021,  4223/2021, 4504/2021, 7257/2022, 7258/2022, 6185/2022, 7785/2022, 5490/2022, 435/2022, 5300/2022, 5289/2022 and 6812/2022 were filed before the authority seeking delayed possession charges/refund on failure to deliver possession of the allotted unit by the respondent.  The registry had already sent the notices of the above complaints through emails i.e. [email protected] and the same is shown to have delivered on the above email addresses as per the report available in the file. Finally on 14.10.2022,  a notice was sent to the respondent which was duly served upon them on 17.10.2022 at the registered office of the respondent. Despite proper service of notices seeing the interest of a large number of allottees in the project to be developed by the respondent is involved, the  receipt of the notice clearly shows that the respondent is avoiding service to put in appearance.  Let the respondent be served by way of substituted service i.e. by way of publication in newspaper i.e. Dainik Bhaskar and Hindustan Times and the publication expenses shall be borne by the complainant on share basis. Matter to come up on 28.07.2023 for further proceedings.

    Stage: PENDING

  • 3NOV 2022
    Hearing

    Judge: VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA

    The Coram is not complete, so the matter is adjourned to 03.03.2023 for the purpose as already fixed.

    Stage: PENDING

  • 6SEP 2022
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL

    The complainant has approached the authority seeking reliefs which cannot be deliberated without the written reply from the respondent. The registry of the authority has sent the notice through speed post as well as through email. Despite a number of reminders due service, the respondent builder failed to put an appearance to the averments made by the complainant. Though on the previous date planning/ engineering wing of the authority was directed to inspect the site and submit its report but that report has been submitted in one project only. In absence of complete details of project and non-appearance of respondent builder the issues for adjudication cannot be dealt effectively. Hence in such a situation the presence of respondent builder to put up its case before the authority is must. Since, the respondent builder is avoiding put in appearance  despite multiple opportunities, the authority in exercise of powers under section 35 of the Act,  2016,   directs the respondent directors with the CFO to appear before the Authority  alongwith relevant record of the case and status of the construction and other development works undertaken in the project and their likely date of completion on the next date of hearing.   A copy of the notice be served  to the respondent through process server of the authority.  Registry is directed to do the needful. The counsel for the complainant has further drawn attention of the authority that  inspite of having paid total consideration amount of the above unit,  the respondent-promoter has issued a cancellation letter dated 02.09.2021 and hence requests that the cancellation may be kept in abeyance.  The restraint order dated 08.03.2022 of the authority for non creation of any third party rights shall continue till further orders.            Matter to come up on 03.11.2022  for further proceedings.

    Stage: PENDING

  • 17MAY 2022
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL

    On the last date of hearing no one was present from the respondent side and the respondent has failed to file reply even on this date. The respondent is directed to file reply within two weeks i.e. by 31.05.2022 in the registry with a copy to the complainant subject to costs of Rs.5,000/-, for not complying with the orders of the authority. Last opportunity is being granted. In case, reply is not filed even at this stage within the time allowed, the defense of the respondent may be struck off.           Since inspite of service of the notice and multiple opportunities,  the respondent has neither filed reply nor put in appearance and hence, the Planning/Engineering Wing of the Authority is directed to inspect the site and to submit status of the project alongwith details of sanction of the building plans, date of grant of environment clearance to work out due date of possession as per Affordable Housing Policy, 2013 which are required to proceed further in the matter on the next date of hearing.              The matter to come up on 06.09.2022 for further proceedings.

    Stage: PENDING

  • 8MAR 2022
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL

    The present complaint was filed on 06.12.2021 and registered as complaint No. 4817 of 2021. As per the registry, complainant has sent copy of complaint along with annexures through speed post as well as through email and proof regarding having the delivery of the complaint along with annexures made to the respondent has been submitted by the complainant as available in the file.  The registry of the authority sent a notice with a copy of the complaint along with annexures through speed post of which delivery confirmed on 13.12.2021 as per the tracking report of the speed post available in the file.  Registry has also sent the notice along with a copy of the complaint through email at following email address: [email protected] The same is shown to have been delivered on the above email address as per the report available in the file.  It is proper service of the notice.            Neither the written reply has been filed b by the respondent nor is putting in appearance. One last opportunity is being granted to the respondent for filing of the reply within two weeks i.e. by 22.03.2022 in the registry with a copy to the complainant. In case reply is not filed within the time allowed, the defense of the respondent may struck off.                 The counsel for the complainant has stated that despite payment of total consideration amount as per Affordable Housing Policy,   the respondent-promoter has issued a cancellation letter dated 02.09.2021 and that there is already a delay of more than six months from the due date of possession.   The respondent-promoter is restrained from creating third party rights in respect of above unit for which the applicant-complainant has already made the full payment to the respondent.  The respondent-promoter is also directed to file complete and updated status of the project regarding construction alongwith expected date of handing over of possession to the allottee alongwith reply.                    Matter to come up on 17.05.2022 for further proceedings.

    Stage: PENDING

  • 5JAN 2022
    Hearing

    Judge: K K KHANDELWAL VIJAY KUMAR GOYAL

    THE MATTER IS ADJOURNED TO 08.03.2022.

    Stage: FIRST HEARING

Orders (13)