PRATIBHA SINGH SIDHU THROUGH SPA HOLDER RAHUL TREHAN vs PAREENA INFRASTRUCTURE PVT LTD

Case NumberRERA-GRG-3587-2024
Date of Filing--
Case TypeRERA-GRG
Last Hearing27 Jan 2026
StateHaryana
CityGurgaon
Year of Filing2024

Party Details

Petitioner
  • PRATIBHA SINGH SIDHU THROUGH SPA HOLDER RAHUL TREHAN
Respondent
  • PAREENA INFRASTRUCTURE PVT LTD

Case Summary

PRATIBHA SINGH SIDHU THROUGH SPA HOLDER RAHUL TREHAN filed Case No. RERA-GRG-3587-2024 in the Haryana Real Estate Regulatory Authority (RERA) against PAREENA INFRASTRUCTURE PVT LTD. The case has undergone 15 hearings over 1 year and 4 months. The case is currently pending. 16 orders have been issued in this matter.

Hearing History (15)

  • 27JAN 2026
    Hearing

    Judge: ARUN KUMAR PHOOL SINGH SAINI

    Detailed order will follow. Matter stands disposed of.

    Stage: DISPOSED

  • 6JAN 2026
    Hearing

    Judge: ARUN KUMAR PHOOL SINGH SAINI

    Order reserved. Matter to come up on 27.01.2026   for pronouncement of order.

    Stage: RESERVED

  • 24DEC 2025
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN PHOOL SINGH SAINI

    Due to administrative exigencies, the case is adjourned to 06.01.2026 for the purpose as already fixed.

    Stage: PENDING

  • 26NOV 2025
    Hearing

    Judge: ASHOK SANGWAN

    Matter to come up on 24.12.2025 for pronouncement of order.

    Stage: PENDING

  • 19NOV 2025
    Hearing

    Judge: ASHOK SANGWAN

    Due to administrative exigencies, the matter is adjourned to 26.11.2025 for the purpose as already fixed.

    Stage: PENDING

  • 15OCT 2025
    Hearing

    Judge: ASHOK SANGWAN

    Order reserved. Matter to come up on 19.11.2025 for pronouncement of orders.

    Stage: RESERVED

  • 10SEP 2025
    Hearing

    Judge: ASHOK SANGWAN

    Matter to come up on 15.10.2025 for final arguments.

    Stage: PENDING

  • 13AUG 2025
    Hearing

    Judge: ASHOK SANGWAN

    Since the Hon’ble Member is  on leave,  hence the matter  is adjourned to 10.09.2025 for the purpose as already fixed.

    Stage: PENDING

  • 9JUL 2025
    Hearing

    Judge: ASHOK SANGWAN

    Matter to come up on 13.08.2025 for final arguments.

    Stage: PENDING

  • 7MAY 2025
    Hearing

    Judge: ASHOK SANGWAN

    Matter to come up on 09.07.2025 for final arguments.

    Stage: PENDING

  • 26FEB 2025
    Hearing

    Judge: ASHOK SANGWAN

    Since 26.02.2025 has been declared holiday on account of Maha Shivratri, hence, the mater is adjourned to 07.05.2025 for the purpose as already fixed.

    Stage: PENDING

  • 27NOV 2024
    Hearing

    Judge: ASHOK SANGWAN

    Due to administrative reason, the matter is adjourned to 26.02.2025 for the purpose as already fixed.

    Stage: PENDING

  • 26SEP 2024
    Hearing

    Judge: VIJAY KUMAR GOYAL

    The present complaint was received on 06.08.2024 and registered as complaint bearing no. 3587 of 2024. On 13.08.2024, the counsel for the complainant has filed an application u/s 36 of Act bearing no. MA No. 537 of 2024 and is seeking directions to restrain the respondent no.1 to create any third party right on the unit under question.   On last date of hearing (i.e., 12.09.2024), the complainant was directed to clarify the actual amount paid against the unit allotted and the respondent was given one more last opportunity to file the reply on application u/s 36 of the Act. The counsel for the complainant is filing the payment plan in the registry within one week. The counsel for the complainant states the respondent has unilaterally cancelled the unit on 21.02.2024. Further states that they had already paid an total amount of Rs.1,12,05,206/- to the respondent no.1 & 2 against two allotted units, out of which half of the amount (i.e., Rs.56,02,603/-) was being paid against the unit under question in the present complaint against total sale consideration of Rs.77,77,417/-. Further states that a similar matter  bearing CR no.3585/2024 is pending before the  bench  of Shri Ashok Sangwan, Hon’ble Member and is listed on 27.11.2024 and in that matter the Authority had already directed  the respondent to maintain status-quo on the unit of the complainant till next date of hearing and requested to restrain the respondent to create any third party rights and further requested for transferring the present matter to the same bench. In view of the above, the respondent is directed to maintain status quo on the unit of the complainant till the next date of hearing and the present matter is also  transferred to the bench  of Shri Ashok Sangwan, Hon’ble Member. Matter to come up on 27.11.2024 for further proceedings.

    Stage: PENDING

  • 12SEP 2024
    Hearing

    Judge: VIJAY KUMAR GOYAL

    The present complaint was received on 06.08.2024 and registered as complaint bearing no. 3587 of 2024. On 13.08.2024, the counsel for the complainant has filed an application u/s 36 of Act bearing no. MA No. 537 of 2024 and is seeking directions to restrain the respondent no.1 to create any third party right on the unit under question. The counsel for the complainant states that they had paid an amount of Rs.1,12,00,000/- (approx.) w.r.t. two unit in the same project and total sale consideration is Rs.77,77,418/- for each unit. The counsel for the complainant to clarify the actual amount paid by them w.r.t. the unit under question. One more opportunity to the respondents to file reply to the application. Matter to come upon 26.09.2024 for further proceedings.

    Stage: PENDING

  • 29AUG 2024
    Hearing

    Judge: VIJAY KUMAR GOYAL

    The Hon’ble Member is on leave, hence, the matter is adjourned to 12.09.2024 for the purpose as already fixed.

    Stage: FIRST HEARING