Cleanmax Vayu Pvt. Limited vs GETCO

Case Number2527/2025
Date of Filing--
Case Type--
Last Hearing13 Oct 2025
State--
City--
Year of Filing2025

Party Details

Petitioner
  • Cleanmax Vayu Pvt. Limited
Respondent
  • GETCO

Case Summary

Cleanmax Vayu Pvt. Limited filed Case No. 2527/2025 in the Gujarat Electricity Regulatory Commission against GETCO. The case has undergone 4 hearings over 1 month. The case is currently pending. 3 orders have been issued in this matter.

Hearing History (4)

  • 13OCT 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (c) (e) & (f) of EA, 2003 read with Regulations 80 and 82 of the GERC (Conduct of Business) Regulations 2004 seeking directions for extension of time period for commissioning the entire evacuation infrastructure alongwith commissioning of the project till 30.09.2026 due to occurrence of the unforeseen reasons.

  • 7OCT 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (c) (e) & (f) of EA, 2003 read with Regulations 80 and 82 of the GERC (Conduct of Business) Regulations 2004 seeking directions for extension of time period for commissioning the entire evacuation infrastructure alongwith commissioning of the project till 30.09.2026 due to occurrence of the unforeseen reasons.

  • 2SEP 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (c) (e) & (f) of the Electricity Act, 2003 read with Regulations 80 and 82 of the GERC (Conduct of Business) Regulations 2004 seeking directions for extension of time period for commissioning the entire evacuation infrastructure alongwith commissioning of the project till 30.09.2026 due to occurrence of the unforeseen reasons.

  • 20AUG 2025
    Hearing

    Judge: N/A

    Petition under Section 86 (1) (c) (e) & (f) of the Electricity Act, 2003 read with Regulations 80 and 82 of the GERC (Conduct of Business) Regulations 2004 seeking directions for extension of time period for commissioning the entire evacuation infrastructure alongwith commissioning of the project till 30.09.2026 due to occurrence of the unforeseen reasons.

Orders (3)