MAHAVEER PVC CABLE FACTORY JAGATPUR, CUTTACK vs E.E (ELECT.), CDD-II, TPCODL
Party Details
- MAHAVEER PVC CABLE FACTORY JAGATPUR
- CUTTACK
- E.E (ELECT.)
- CDD-II
- TPCODL
Case Summary
MAHAVEER PVC CABLE FACTORY JAGATPUR and CUTTACK filed Case No. 58/2025 in the OERC on 2 Aug 2025 against E.E (ELECT.) and CDD-II. The case has had one hearing so far. The case was disposed of on 5 Aug 2025. 1 order has been issued in this matter.
Hearing History (1)
- 5AUG 2025Hearing
Judge: N/A
Orders (1)
- 5AUG 2025judgementView Order ↗
Order No: N/A
Judgement DetailsView full order PDF ↗
3 Together, Let us light up our lives ODISHA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN PLOT NO.4, OERC ROAD, SHAILASHREE VIHAR, BHUBANESWAR -751021 TEL.
No.
2721048, 2721049 E-MAIL: [email protected] / [email protected] WEBSITE: www.orierc.org Present: Shri Pradeep Kumar Jena, Chairperson Shri S.
K.
Ray Mohapatra, Member Shri B.
Mohanty, Member Case No.
58/2025 M/s.
Mahaveer Pvc Cable Factory, C/o-Sri Anil Kumar Jain, Plot No.
E1& D1 (P), N.I.E., Jagatpur, Cuttack-754021. ………… Petitioner Vrs.
The Executive Engineer (Electrical), CDD.
No.II, Badamabadi, Cuttack ………… Respondent In the matter of: Application under Section 142 of the Electricity Act,2003 alleging non- compliance of order dated 08.08.2023 of the learned GRF, Cuttack passed in C.C.
Case No.119 of 2023 and order dated 18.08.2021 passed in C.C.
Case No.313/2021 and also order dated 15.11.2021 of the Learned Ombudsman-I passed in C.R.
Case No.152 of 2021.
ORDER Date of Hearing: 05.08.2025 Date of Order: 05.08.2025 This matter is taken up for hearing through hybrid arrangement.
2.
Shri Rabin Kishore Behera, the Authorized Representative of the Petitioner- M/s.
Mahaveer Pvc Cable Factory and Shri Goutam Jayprakash, HoG-Legal, TPCODL along with Ms.
Abhilasha Panigrahi, Lead Associate (Legal), the Respondent-Licensee do appear.
The Memo of compliance order submitted by the Petitioner is taken on record.
3.
The Petitioner has filed the instant petition under Section 142 of the Electricity Act, 2003 seeking execution of the order dated 08.08.2023 of the learned GRF, Cuttack passed in C.C.
4.
The Learned GRF, Cuttack while disposing of C.C.
Case No.
313 of 2021 in order dated 16.11. ted 16.11.2024 had directed as follows: - (i) The Opposite party is directed to stop the levy of transformer loss forthwith if not done already and further directed to withdraw transformer loss for a period of 2 years prior to such effective date as per clause 57 of OERC Distribution Code,2019 and adjust the amount in the future bills of the complainant. (ii) The O.P.is directed to stop levy of meter rent immediately in next billing cycle.
Further the O.P.is directed to refund the excess meter rent recovered since 05/2021 by making adjustment in the future EC bill.
4 (iii) The O.P.is directed to review the SD within15 days of receipt this order under Clause 53 of OERC Distribution Code, 2019 and to refund the revision amount if any as per provisions under Clause 54 of the Code. (iv) The O.P.is directed to serve the revision statement on the above issues the case is disposed of accordingly.
Further, the Learned GRF, Cuttack while disposing of C.C.Case No.
119 of 2023 in order dated 08.08.2023 had directed as follows:- “ i).
The O.P. is directed to with draw the charges for transformer loss from 09/2021 onwards. ii).
The O.P. should intimate the complainant within 15 days of receipt of order and serve revised EC bill in subsequent month.” The Learned Ombudsman-I while disposing of C.R.Case No.
152 of 2021 in order dated 15.11.2021 had directed as follows:- “ The O.P. is directed to withdraw the transformer loss charged on the Petitioner from 04/2018 to 07/2019 as per Para-328 of OERC RST order 2018-19.
This order is in addition to the order dated 18.08.2021 passed by the GRF, Cuttack in C.C.Case No.313/2021” 5.
When the matter is taken up for hearing today, the Representative of the Respondent-Licensee, TPCODL drawing our attention to the affidavit dated 02.08.2025 of the Executive Engineer (Elect.), CDD-II representing the Respondent-Licensee submits for closure of the case on the ground that the direction imparted the above orders have since been carried out. rried out.
It is further submitted that the Petitioner-Consumer’s revised bills have been prepared as per the above orders and served on the Petitioner/Consumer.
6.
The Authorized Representative of the Petitioner participated in the hearing online.
To the query of the Commission, he also admits that the Respondent-Licensee has complied with the above orders and submits that the Petitioner is no longer interested to proceed with this case.
A memo to that effect is also filed by the Petitioner.
7.
In view of the implementation of the order dated 08.08.2023 of the learned GRF, Cuttack passed in C.C.
Case No.119 of 2023, order dated 18.08.2021 passed in C.C.
Case No.313/2021 and order dated 15.11.2021 of the Learned Ombudsman-I passed in C.R.
Case No.152 of 2021, the Commission finds nothing more to proceed in this case.
Consequently, the case is disposed of on full satisfaction of the above orders.
Sd/- Sd/- Sd/- (B.
Mohanty) (S.K.
Ray Mohapatra) (P.
Jena) Member Member Chairperson