Meta Pixel
CNR: --
DISPOSED

VEENA BHATIA AND MANONEET BHATIA THROUGH POWER OF ATTORNEY HOLDER VEENA BHATIA vs ANSAL PHALAK INFRASTRUCTURE PVT. LTD.

Case NumberRERA-GRG-4729-2020
Date of Filing--
Case TypeRERA-GRG
Last Hearing1 Jun 2023
StateHaryana
CityGurgaon
Year of Filing2020

Party Details

Petitioner
  • VEENA BHATIA AND MANONEET BHATIA THROUGH POWER OF ATTORNEY HOLDER VEENA BHATIA
Respondent
  • ANSAL PHALAK INFRASTRUCTURE PVT. LTD.

Case Summary

VEENA BHATIA AND MANONEET BHATIA THROUGH POWER OF ATTORNEY HOLDER VEENA BHATIA filed Case No. RERA-GRG-4729-2020 in the Haryana Real Estate Regulatory Authority (RERA) against ANSAL PHALAK INFRASTRUCTURE PVT. LTD.. The case has undergone 26 hearings over 2 years and 3 months. The case was disposed of on 1 Jun 2023. 16 orders have been issued in this matter.

Hearing History (26)

  • 1JUN 2023
    Hearing

    Judge: RAJINDER KUMAR

    Vide separate order of even date, complaint stands disposed of. File be consigned to the records.

    Stage: DISPOSED

  • 12MAY 2023
    Hearing

    Judge: RAJINDER KUMAR

    Order is not ready.                      To come on 01.06.2023 for order.

    Stage: PENDING

  • 20MAR 2023
    Hearing

    Judge: RAJINDER KUMAR

    ORDER IS NOT READY.                           TO COME ON 12.05.2023 FOR ORDER.

    Stage: PENDING

  • 30JAN 2023
    Hearing

    Judge: RAJINDER KUMAR

    ORDER IS NOT READY.                           TO COME ON 20.03.2023 FOR ORDER.

    Stage: PENDING

  • 11JAN 2023
    Hearing

    Judge: RAJINDER KUMAR

    ORDER IS NOT READY.                           TO COME ON 30.01.2023 FOR ORDER.

    Stage: PENDING

  • 20DEC 2022
    Hearing

    Judge: RAJINDER KUMAR

    Order is not ready.                           To come on 11.01.2023 for order.

    Stage: PENDING

  • 29NOV 2022
    Hearing

    Judge: RAJINDER KUMAR

    Order is not ready.                             To come on 20.12.2022 for order.

    Stage: PENDING

  • 16NOV 2022
    Hearing

    Judge: RAJINDER KUMAR

    Order is not ready.                            To come on 29.11.2022 for order.

    Stage: PENDING

  • 20OCT 2022
    Hearing

    Judge: RAJINDER KUMAR

    Order is not ready.                         To come on  16.11.2022

    Stage: PENDING

  • 7OCT 2022
    Hearing

    Judge: RAJINDER KUMAR

    Order is not ready.                  To come on  20.10.2022 for order.

    Stage: PENDING

  • 14SEP 2022
    Hearing

    Judge: RAJINDER KUMAR

    It is submitted by learned counsel for complainant that she has already argued the matter and written submissions have also been filed. Learned counsel for respondent seeks one week’s time to file written submissions on behalf  of respondent. Allowed.                To come on 07.10.2022 for orders.

    Stage: PENDING

  • 22AUG 2022
    Hearing

    Judge: RAJINDER KUMAR

    None for complainant.  Issue notice to same for next date.                           To come on  14.09.2022 for further proceedings.

    Stage: PENDING

  • 15JUL 2022
    Hearing

    Judge: RAJINDER KUMAR

    Adjudicating Officer on leave, adjourned to 22.08.2022.

    Stage: PENDING

  • 28APR 2022
    Hearing

    Judge: RAJINDER KUMAR

    Learned counsel for respondent requests for short adjournment to advance arguments, though he joined online. Allowed.                          To come on 15.07.2022 for arguments.

    Stage: PENDING

  • 7APR 2022
    Hearing

    Judge: RAJINDER KUMAR

    Objections are filed by respondent against  application of the complainant, seeking relinquishment some of her  prayers.                     Applicant wants to relinquish all of her prayers in complaint except prayer  at coluumn No. 9 and 10.  It is stated that to deal with said prayers, this forum has no jurisdiction. She has already filed a separate complaint before the Authority seeking delayed possession charges(DPC).                  Application is opposed by the respondent stating that complainant cannot withdraw these prayers at the stage, when his client(respondent) has already filed an application under Order VII Rule 11 of CPC.                 Even if such an application is filed by the respondent to reject  the complaint, it is well settled that complainant/plaintiff/petitioner is master of his case. Same  can withdraw any prayer as she/he wants. No reason to restrain the complainant  from withdrawing  some  of her reliefs, sought  in this complaint. Application is allowed.                      Counsel for respondent seeks short adjournment for final arguments. Allowed.                      To come on 28.04.2022 for remaining arguments.

    Stage: PENDING

  • 22MAR 2022
    Hearing

    Judge: RAJINDER KUMAR

    An application has been filed on behalf  of complainant with a request   to relinquish  certain  prayers. As per learned counsel for respondent, the same has  not received copy  of this application. Learned counsel for complainant undertakes  to supply copy of the same again although copy of this application is claimed to have  been emailed  at the address of learned counsel representing  the respondent.                          To come  on 07.04.2022 for consideration of  application.

    Stage: PENDING

  • 4MAR 2022
    Hearing

    Judge: RAJINDER KUMAR

    Arguments heard in part being advanced by learned counsel for complainant. As per him, his client insists only  for prayer mentioned in relief clause No. 9 and 10. Short adjournment is requested to file an application in this regard or to give statement. Allowed.                            To come  on   22.03.2022 for further arguments.

    Stage: PENDING

  • 11JAN 2022
    Hearing

    Judge: RAJINDER KUMAR

    Respondent  has already been proceeded ex-parte. As per learned counsel for complainant, this is  simply a case for compensation as possession of impugned unit has already been taken over by the complainant. Learned counsel for respondent submits even if the respondent is proceeded ex-parte, he has  right to advance arguments.                               To come on  04.03.2022 for further proceedings/arguments.

    Stage: PENDING

  • 16DEC 2021
    Hearing

    Judge: RAJINDER KUMAR

    THE MATTER IS ADJOURNED TO 11.01.2022

    Stage: PENDING

  • 15NOV 2021
    Hearing

    Judge: RAJINDER KUMAR

    It is pointed out that the Apex Court while deciding Civil Appeal No(s) 6745-6749 of 2021 dated  11.11.2021 in case titled M/s Newtech Promoters and Developers Pvt Ltd. Vs State of UP & Ors Etc.   has given some directions about jurisdiction between the Authority and the Adjudicating Officer inter se, regarding jurisdiction  of cases relating to refund and  compensation.                          Be put up for further proceedings on 16.12.2021.

    Stage: PENDING

  • 14OCT 2021
    Hearing

    Judge: RAJINDER KUMAR

    Arguments heard. 2.                        To come on 15.11.2021 for order.

    Stage: PENDING

  • 6SEP 2021
    Hearing

    Judge: RAJINDER KUMAR

    As per learned counsel for respondent, complainant has taken possession of unit and thus this complaint becomes infructuous. 2.                  None has appeared on behalf of complainant. Issue notice to complainant for next date. 3.                  To come on 14.10.2021.

    Stage: PENDING

  • 27AUG 2021
    Hearing

    Judge: RAJINDER KUMAR

    Although, the case was fixed for final order today. During consideration, it is noted that on previous date, it was pointed that complainant has already taken possession of allotted unit.  Although  the complainant had sought relief of refund. A clarification in this regard is required. 2.                    Learned counsel for respondent  filed an application seeking recall of order dated 10.02.2021  by which the same was proceeded ex-parte. Copy supplied. 3.                  To come on 06.09.2021 for further proceedings.

    Stage: PENDING

  • 6AUG 2021
    Hearing

    Judge: RAJINDER KUMAR

    Respondent already proceeded ex-parte. 2.                       It is stated by learned counsel for complainant that possession of allotted unit has already been taken over by the complainant. 3.                     To come on 27.08.2021 for order.

    Stage: PENDING

  • 27APR 2021
    Hearing

    Judge: SUBHASH CHAND GOYAL

    Due to increase in the Covid-19 cases in and around the area of the Authority, the case is not being taken up for hearing. Hence, as per directions of the Hon’ble Authority, it is being adjourned to 06.08.2021 for the proceedings already fixed. 2.         Both the parties be informed accordingly through e-mail.

    Stage: PENDING

  • 10FEB 2021
    Hearing

    Judge: SUBHASH CHAND GOYAL

    None is present on behalf of the respondent. A notice in this regard was sent though e-mail on 29.01.2021, but despite waiting sufficiently none has turned up to contest the matter. So, as such is ordered to be proceeded against ex-parte. 2.          Let the matter be put up on 27.04.2021 for arguments.

    Stage: FIRST HEARING

Orders (16)

Judgement DetailsView full order PDF ↗

ffiI{ARERft ffieunuCnnHr BEFORE RAJENDER KUMAR, ADIUDICATING OFFICER, HARYANA REAL ESTATE REGULATORY AUTHORITY GURUGRAM Complaint no. : 4729 of 2O2O Date of decision : 01.06.2023 Veena Bhatia & Manoneet Bhatia ADDRESS:L-49D First Floor Block-L Saket, Complainants Sector-67, Gurugram, [{aryana Versus M/S Ansal Phalak Infrastructure Pvt.

Ltd.

ADDRESS 1202, Antriksh Bhawan 16, Respondent Kasturba Gandhi Marg, New Delhi-110001 ORDER 1.

This is a complaint filed by Veena Bhatia and Manoneet Bhatia fbuyers) under section 3]. read with section 35,36,37 and 38 of The Real Estate (Regulation and Development) Act, 201.6 (in short, the Act) against respondent/developer (M/s Ansal Phalak Infrastructure Pvt. [,imited).

2.

According to complainants, they were approached by respondent's representative, about a project namely "The Sovereign Floors Esencia" ,(t --_ APPEARANCE: For Complainants: For Respondent: Mr.

Nilotpal Shyam Advocate Mr Deeptanshu fain Advocate A,o ffiI{ARTRfl' #- eunuGRAM located at sector-67, Gurugram, Haryana-1,22001, and were told that it will serve their purpose.

They (complainants) filled up an application form on 07.10.20211 and were allotted a unit by the respondent bearing no.

E-2150 having super area of 2542 sq. ft. in block-E.

3.

That after payment of Rs.

13,00,000/- by them, the respondent executed Floor Buyer's Agreement (FBA) dated 07.11.2011.

As per clause 5.1 of said agreement, the possession of the unit was to be handed over within 30 months, from the date of execution of said agreement.

Total sale consideration was agreed to be Rs.

1,21,,60,000 /- excluding charges such as EDC, IDC, PLC , car parking, etc.

They (complainants) paid a sum of Rs.

1,52,B3,097 /- towards total sale consideration, as per the payment plan.

On 02.1-2.2015, they (complainants) were offered possession of their unit, along with final demand letter.

The occupation certificate for the project was obtained by respondent on 30.08.2016.

Therefore, the possession offered on 02. red on 02.12.2015 was not a legal offer of possession.

The respondent vide email dated 10.06.201.9 offered to pay Rs.

10,00,000/- towards delay possession charges, but the same was not paid till date.

They sent a legal notice to respondent, asking the latter to hand over possession of their unit and to pay compensation, but respondent never replied.

It is further pleaded by the complainants that the respondent has illegally increased area of the unit by 595 sq. ft. i.e.24.5o/o of the area allotted to them.

It amounts major alteration, not permissible under Section 1,4 of Act of 20L6.

Moreover, respondent did not get sanction from competent authority regarding revised building plan . u 4.

5.

Ar'\ , ffiI{ARER ffi eunuGRAM 6.

That Rs.

5,30,0 49 /- has also been charged as cost of escalation.

Clause 2.3 and 3.5 of the FBA are not binding upon them fcomplainants) as these are one -sided, discriminatory and unfair.

Even otherwise, as per clause 3.5 of FBA, the respondent shall have to absorb cost escalation up to 5%.

7.

That, the respondent has charged for preferential location of Rs.

3,84,000 /-.

The unit allotted to them (complainants) is located at the back end of the locality, which is adjacent to a village and hence not a preferential location.

B.

That the respondent has illegally used the electricity connection for the purpose of common maintenance services, while they (complainants) were made to pay electricity bill of Rs.

40,7zr /-.

9.

That they [complainants) have been made to pay IDC/EDC charges and also for covered car parking at the time of allotment, illegally.

As they [complainants) were not legally bound to pay all these charges, the respondent is under legal obligation to return the excess amount.

L0 Contending all this, the complaint sought compensation including delay possession charges (DPC) @ r9o/o p.a. r9o/o p.a.

During the course of proceedings, the complainants filed an application with prayer to Learned counsel for that his clients relinquish all relinquish certain reliefs. applicants/complainants submitted reliefs sought by them, except mentioned in Clause IX and X in prayer Clause (0 of complaint.

The Application was allowed by the authority vide order dated 07.04.2022. ll Neither anyone appeared on behalf of respondent nor any reply was filed despite service of notice, the respondent was proceeded ex-parte, vide order dated L0.02.2021.

Though respondent filed an application dated 27.08.2021 with prayer to recall order dated 1,o.o2.2o2tt{{- % ffiHARER' ffi ounuGRAM respondent neither stressed on it, nor filed any reply against the complaint alongwith said application.

Learned counsel for respondent insisted on rejection of complaint on certain grounds.

An application was also filed in this regard, on 25.0L.2022.

L2 I have heard learned counsels appearing for both of the parties and gone through written submissions filed on behalf of complainants.

L3 It is contended by learned counsel for the respondent that in view of mandate given by the Apex Court in M/s Newtech Promoters and Developers Pvt Ltd.

Vs State of UP & Ors, Etc. case and Civil appeal No(s).

6745-6749 of 2021 this forum (A.O) has no jurisdiction to grant relief of delayed possession compensation.

Even otherwise, as the complainants have already taken possession of their unit, same have no right to claim compensation now.

14 I agree with learned counsel claiming that this forum (AO) has no jurisdiction to try and entertain prayer seeking delayed possession compensation, as sought by complainants in this case.

As stated above, by filing an application, the complainants have relinquished all their claims except for compensation, as described in clause IX and X of the complaint. complaint.

L5 So far as plea that the complainants have taken possession and hence they have no locustandi to file complaint, seeking compensation is concerned, I find no substance in this plea.

Simply to say that possession has been taken over by the complainants, all this does not deprive them fcomplainants) from seeking compensation for wrong which has already been done to them.

Present complaint is thus not liable to be rejected on this ground.

Application filed by respondent in ,t^{' )- F(a this regard is thus dismissed. ffiHARER*- ffi eunuGRAM 16After withdrawal of some of reliefs, complainants are seeking compensation on following grounds:- IX To award Rs.

10,00,000/- [Rupees Ten Lacs only) as compensation for loss of opportunity cost with regard to impugned unit, disproportionate gain and unfair advantage made by respondent comply with regard to complainants money and mental harassment caused to the complainants in view of the inordinate delay in delivery of possession of the impugned unit.

X To direct company to pay a cost of Rs.

1,00,000/- fRupees One Lakh only) towards the cost of the litigation.

1-S.During deliberations it is pointed out that possession of unit in question has been handed over to the allottees/complainants on 07.08.2019.

All this is mentioned by the respondent in its application seeking rejection of complaint.

The complainants have sought compensation of Rs.

10 lakhs alleging loss of opportunity, cost with regard to impugned unit, disproportionate gain and unfair advantage by respondent and again compensation for mental harassment caused to them due to inordinate delay in delivery of possession.

As per Clause 5.1 of FBA the respondent undertook to deliver v possession of subject unit within 30 months, withlt an extended period of six months from the date of execution of said agreement [FBA) or clate of sanctiond of building plan, whichever is latter.

16.As stated earlier, FBA was executed between the parties on 07.L t. on 07.L t.20t1, and as per Annexure 3, building plans were approved on 23.01.2013.

Taking the latter dated i.e.

23.01 .20L3, as starting point, 30 months were completed on 23.07.201-5.

Adding 5 more months as extended {'6.

WI.IARER,*' ffi eunuennvr period.'Fhere remained delay of about more than three and half years. ,) Apparently, the allottees/complainants were deprived of their right, during this period causing anxiety and mental harassment to them.

On the other hand, respondent used money paid by the complainants and did not discharge its obligation to complete unit, and hence gained at the cost of buyers/complainants.

L7 Learned counsel for complainants also contended that his clients suffered mental harassment as the respondent sent draft FBA and asked them fcomplainants) to send the same back within 30 days, otherwise their booking of unit will be cancelled.

Moreover, same could have been penalized by forfeiting20o/o of sale consideration i.e. earnest money.

Moreover, complainants would have been made liable /_ to pay brokerage or penalty at rate Rs. l per sq. ft. failing to sendr,4ccl agreement to sell, after their signatures.

His clients i.e. complainants remained under pressure to sign FBA, without properly having gone through the same.

It is further the plea of learned counsel that his clients were forced to take possession by the respondent, without receiving an occrlpation certificate.

The respondent could not have compelled them to take possession, unless the construction was completed and the same i.e. builder had received occupation certificate.

1B I find force in said plea of learned counsel.

To impose such a condition i.e. to sign FBA within 30 days, or to force an allottee to take possession without getting occupation certificate is apparently unfair trade practice, on the Part of a builder.

L9 There is an old proverb "ubi Jus ibi remedium" meaning that where there is right, there is remedy. is remedy.

The allottees had right to get possession of their unit within agreed time, particularly when same had paid (t 'tro ffiHARER.*. ffi eunuenAHl entire sale consideration.

Similarly, the respondent was not justified to force the allottees to impose condition of 30 days to sign, draft of FBA or to take possession without getting OC.

The complainants are thus well within their rights tf^.H, compensation.

20 There is nothing on t..o.aj.rtablish as what exact loss has been suffered by the complainants or what unjustified gain was received by the respondent.

Keeping in view the facts of the case, in my opinion, a sum of Rs.

2 lakh is appropriate amount of compensation, in this regard.

The same is thus allowed to the complainants, to be paid by the respondent.

21 As described above, the complainants have also sought compensation of Rs.

1 lakh towards cost of litigation.

The complainants did not put on file any receipt of fee paid to their counsel.

Apparently, same were represented by an advocate.

The complainants are thus allowed a sum of Rs.

50,000/- as cost of litigation.

The complaint is thus allowed.

Respondent is directed to pay Rs.2,50,000/- to the complainants as compensation within 30 days from today, otherwise same will be liable to pay interest @t\o/o per annum till the date of realization.

Announced in open Court today i.e.

01.06.2023.

File be consigned to the Records. 'tt'U (Rajende ,*r#86 *9 Ha ryana Rear r,,llj HHi:lffiTiiil;,,* Gurugram