HARERA GURUGRAM vs COUNTRYWIDE PROMOTERS PVT LTD
Party Details
- HARERA GURUGRAM
- COUNTRYWIDE PROMOTERS PVT LTD
Case Summary
HARERA GURUGRAM filed Case No. RERA-GRG-5651-2023 in the Haryana Real Estate Regulatory Authority (RERA) against COUNTRYWIDE PROMOTERS PVT LTD. The case has undergone 6 hearings over 2 months. The case was disposed of on 28 Mar 2024. 6 orders have been issued in this matter.
Hearing History (6)
- 28MAR 2024Hearing
Judge: SANJEEV KUMAR ARORA
Sh. Rahul Sharma (AGM-compliance) appeared on behalf of the promoter. The AR of the promoter submits that there are total 8 towers in the project and for 6 towers, OC has been obtained on 10-02-2014. OC was applied on 17-05-2017 for the remaining 2 towers namely A, B and convenient shopping before coming into force of Haryana Real Estate (Regulations and Development) Rules, 2017. He further states that for the remaining 8 villas for which OC has not been obtained, the phasing for these 8 villas has been applied on 16-02-2024 in the competent authority. Further, an affidavit along with board resolution has also been submitted on 14-03-2024 declaring that after the receipt of approval of phasing, they shall get the revised building plan of villas and they shall apply for registration of this part of the project area measuring 838 sq.m. the director of the company has submitted an affidavit declaring that this part of the project is unlaunched and no third party rights have been created on the said part of the project. Remaining developed area for which OC has been obtained is handed over to RWA. Therefore, the matter stands disposed of.
Stage: DISPOSED
- 14MAR 2024Hearing
Judge: SANJEEV KUMAR ARORA
Sh. Rahul Sharma (AGM-compliance) appeared on behalf of the promoter. The AR has filed the affidavit which needs to be examined. Further, they had applied for phasing for the unregistered part of the project which contains 8 villas area measuring 838 sq,m, on 16-02-2024 and after the receipt of approval of phasing, they shall get the building plan revised and shall apply for registration of project. Matter to come up on 28-03-2024 at 10:00 A.M.
Stage: PENDING
- 7MAR 2024Hearing
Judge: SANJEEV KUMAR ARORA
Sh. Rahul Sharma (Manager-compliance) appeared on behalf of the promoter. The AR filed the reply on 05-03-2024 which needs to be examined. Matter to come up on 14-03-2024 at 10:00 A.M.
Stage: PENDING