HARERA vs ANSAL HOSUING AND CONSTRUCTION LTD
Party Details
- HARERA
- ANSAL HOSUING AND CONSTRUCTION LTD
Case Summary
HARERA filed Case No. RERA-GRG-5907-2019 in the Haryana Real Estate Regulatory Authority (RERA) against ANSAL HOSUING AND CONSTRUCTION LTD. The case has undergone 13 hearings over 6 years. The case is currently pending. 10 orders have been issued in this matter.
Hearing History (13)
- 22JAN 2026Hearing
Judge: N/A
Stage: PENDING
- 18DEC 2025Hearing
Judge: ASHOK SANGWAN
The matter adjourned on 22.01.2026.
Stage: PENDING
- 27NOV 2025Hearing
Judge: ASHOK SANGWAN
Sh. Ashok Sharma, Sh. Amandeep Kadyan (Advocate) and Sh. Dushyant Arora are present on behalf of the respondent. The AR and the counsel for M/s Oriane Developers Pvt. Ltd. state that a residential group housing project on 10.10 acres (License no. 42 of 2013) was being developed by the respondent who had applied for registration with the RERA Authority on 08.01.2019 which was found complete in all respect on 07.10.2019. However, thereafter no RC was issued. Further, due to financial difficulties the project was sold to M/s Perfect Megastructure Pvt. Ltd. in Oct 2022. They further informed that all allottees of the project have been settled either by way of transfer or refund and information for discontinuation of project was submitted to the Authority on 30.05.2024. An affidavit dated 24.02.2024 of the authorised signatory of the company has been placed on record in this regard. A copy of the COD permission granted by DTCP in favour of M/s Perfect Megastructure Pvt. Ltd. dated 21.11.2023 has been placed on record. A perusal of the earlier proceedings reveals that the Authority had directed that a notice to be issued to M/s Perfect Megastructure Pvt. Ltd. during the proceedings dated 10.07.2024. It is further seen from the file that vide their letter dated 21.08.2024, M/s Perfect Megastructure Pvt. Ltd. have stated that an application for registration of project shall be submitted once the company obtains a license and approval of construction maps from the competent Authority and other such clearances. In view of the above the following is directed: (i) A public notice be issued regarding the affidavit submitted by M/s Oriane Developers Pvt. Ltd. w.r.t the abandonment of the project and settlement of all claims. (ii) A notice be issued to M/s Perfect Megastructure Pvt. Ltd. to come present and update the status of the project land. (iii) A letter be issued to DTCP, Haryana for intimating the status of approval of building plans w.r.t the license no. 42 of 2013. The matter to come up on 18.12.2025.
Stage: PENDING
Orders (10)
- 18DEC 2025orderView Order ↗
Order No: N/A
- 27NOV 2025orderView Order ↗
Order No: N/A
- 6NOV 2025orderView Order ↗
Order No: N/A