Meta Pixel
CNR: --
FIRST HEARING

MS INDIABULLS COMMERCIAL CREDIT LTD vs AMBIENCE PROJECTS & INFRASTRUCTURE PVT. LTD.

Case NumberRERA-GRG-2276-2024
Date of Filing--
Case TypeRERA-GRG
Last Hearing7 Jan 2025
StateHaryana
CityGurgaon
Year of Filing2024

Party Details

Petitioner
  • MS INDIABULLS COMMERCIAL CREDIT LTD
Respondent
  • AMBIENCE PROJECTS & INFRASTRUCTURE PVT. LTD.

Case Summary

MS INDIABULLS COMMERCIAL CREDIT LTD filed Case No. RERA-GRG-2276-2024 in the Haryana Real Estate Regulatory Authority (RERA) against AMBIENCE PROJECTS & INFRASTRUCTURE PVT. LTD.. The case has undergone 3 hearings over 3 months. The case is currently pending. 4 orders have been issued in this matter.

Hearing History (3)

  • 7JAN 2025
    Hearing

    Judge: ARUN KUMAR ASHOK SANGWAN

    The counsel for the applicant/complainant has filed the present complaint which is pending adjudication before this Authority on 21.01.2025.   The counsel for the applicant/complainant has filed an application dated 24.12.2024 and requests that the present application be  allowed for  pre-ponement  of hearing  and to  allow withdraw the complaint with liberty to file fresh  as petition under section 9 of the Arbitration and Conciliation Act, 1996 is pending before the Hon’ble High Court of Delhi. In view of the request made by the Applicant/complainant, the application is taken up today.   In view of the submissions made by the counsel for the applicant/complainant for withdrawal of the complaint,  the complaint is dismissed as withdrawn  in terms of the application filed by the complainant. File be consigned to the registry.

    Stage: DISMISSED

  • 11DEC 2024
    Hearing

    Judge: ANU

    Reply filed on behalf of the respondent in the registry on 26.09.2024 taken on the record. As pleadings are complete so matter is listed before the Full Bench on 21.01.2025 for payment of cost and for final arguments.

    Stage: PENDING

  • 18SEP 2024
    Hearing

    Judge: ANU

    Memorandum of appearance filed on behalf of the respondent. Reply not filed. Adjournment requested. Now the case is adjourned for 11.12.2024.                       Respondent is directed to file reply within three weeks of this order, in the registry with advance copy to the complainant, and in case reply not filed within three weeks of this order then reply be filed with cost of Rs. 5,000/- to be paid to the complainant.

    Stage: FIRST HEARING

Orders (4)

Judgement DetailsView full order PDF ↗

ffiHARERA ffi* oURUGRAM HARYANA REAL ESIAIE REGULAIORY AUIHORIIY GURUGRAM ERqr"n *L-dr<l frt+qrro qTET6-{ur, rJvqr*I rurfi.eq.d. ftxrqT6,frtrd NeW PWD RESI PROCEEDINGS OF THE DAY Tuesday and 07.01.2025 Day and Date CRl2276l2O24 Case titled as Indiabulls Commercial Credit Limited VS Ambience Proiects And Infrastructure Private Limited Complaint No.

Indiabulls Commercial Credit Limited Complainant Shri Gaurav Dua, Advocate Represented through Ambience Projects And Infrastructure Private Limited Sh.

V.Aneesh Raajan & Ms' Prerna Praiapati Adv' Respondent RePresented through Early hearing aPPlication Last date ofhearing Naresh Kumari and HR Mehta Proceeding Recorded bY Proceedings-cum-orders The counsel for the applicant/complainant L,-'Il:d the present complaint which is pending adiudication blior" this Authority on 2t'0L'2025' The counsel for the applicant/complainant has filed an application dated 24'12'2024 and requests that the present "ppfi.',tion be allowed for pre-ponement of hearing and to arow withdraw the complaint with liberty to file fresh as petition under section 9 of the Arbitration and Conciliation Act.

1996 ii pending beforeihe Hon'ble High Court of Delhi. ln view of the request -rJ.

Ly the Applicait/complainant, the application is taken uP todaY.

In view of the submissions made by the counser.for the appricant/complainant for withdrawal of the complaint, the c#plaint is dismissed as withdrawn in terms of the Ashok .l ,, AKr-Kumar Chairman 07.01.2025 Memb Respondent