Meta Pixel
CNR: --
PENDING

DEVESH DUBEY AND ANUBHA UPADHYAY vs SUPERTECH LIMITED

Case NumberRERA-GRG-7260-2022
Date of Filing--
Case TypeRERA-GRG
Last Hearing7 Apr 2025
StateHaryana
CityGurgaon
Year of Filing2022

Party Details

Petitioner
  • DEVESH DUBEY AND ANUBHA UPADHYAY
Respondent
  • SUPERTECH LIMITED

Case Summary

DEVESH DUBEY AND ANUBHA UPADHYAY filed Case No. RERA-GRG-7260-2022 in the Haryana Real Estate Regulatory Authority (RERA) against SUPERTECH LIMITED. The case has undergone 13 hearings over 2 years and 1 month. The case is currently pending. 13 orders have been issued in this matter.

Hearing History (13)

  • 7APR 2025
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN

    Detailed order will follow.  Matter stands disposed off.

    Stage: DISPOSED

  • 11MAR 2025
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN

    Matter to come up on 07.04.2025 (3-00 PM) for final arguments/orders.

    Stage: PENDING

  • 10DEC 2024
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN

    The present complaint has been received on 14.11.2022. Reply not received by the respondent.  The respondent is directed to file reply within 2 weeks with an advance copy to the complainant. The counsel appearing on behalf of M/s Supertech Ltd. states that the company is still under moratorium vide orders dated 25.03.2022 passed by the Hon’ble NCLT. Matter to come up on 11.03.2025 for further proceedings.

    Stage: PENDING

  • 2SEP 2024
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN

    The counsel for the complainant requests  to file an application to implead   M/s Sarv Realtors  as necessary party as the assets and liabilities of the projects “ Hues” are transferred to  M/s Sarv Realtors in a Suo Moto complaint No.5802/2019 by the Authority vide orders dated 29.11.2019.  The counsel for the complainant shall file an application for impleadment  of  M/s Sarv Realtors   within a period of 15 days in the Authority after supplying a copy to all the respondents who shall file reply within next 15 days in the Authority after supplying a copy to the counsel for the complainant. Matter to come up on 10.12.2024 for further arguments.

    Stage: PENDING

  • 12AUG 2024
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA

    Due to administrative exigency,  the matter is adjourned to 02.09.2024 for the purpose as already fixed.

    Stage: PENDING

  • 8JUL 2024
    Hearing

    Judge: ASHOK SANGWAN VIJAY KUMAR GOYAL SANJEEV KUMAR ARORA

    Matter is adjourned to 12.08.2024.

    Stage: PENDING

  • 1JUL 2024
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA

    Due to administrative exigency,  the matter is adjourned to 08.07.2024 for the purpose as already fixed.

    Stage: PENDING

  • 27MAY 2024
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA

    Due to administrative exigency, the matter is adjourned to 01.07.2024 for the purpose as already fixed.

    Stage: PENDING

  • 19APR 2024
    Hearing

    Judge: SANJEEV KUMAR ARORA

    Since the IRP - respondent No.1  who stepped the shoes of Promoters as per orders of the Hon’ble NCLT, did not timely complied  with the directions of the Authority dated 12.01.2024 which was to be complied within 15 days, the Authority  hereby imposes  a penalty of Rs. One Lakh as per provision of section 63 of the Act, 2016.    Shri Hitesh Goel - IRP present  in person stated that no separate books of account of each project were being maintained  uptil 25 March 2022  i.e.  the date when the moratorium was imposed.   Further stated that even now no separate books  of account is being  maintained for each project , only MIS is being prepared  and hence they have not filed QPRs.  IRP further stated that he has taken the charge of company Supertech  Ltd. on  as is where is basis and since no separate balance sheets of each project  used to be prepared,  hence,  he could not do the compliances of the directions which were pending for compliance prior to his  appointment  as  IRP of the company and further since June, 2022 he has tried to maintain separate bank account of each project of the company. Further stated that since the registration of  most of Gurugram projects have already been elapsed  and  renewal of the same/extension of the same is still pending. Although they had moved an application  No.1172 of 2022 dated 06.02.2023 for extension which was rejected by the authority on 14.11.2023 on account of non-compliances of various deficiencies pointed out by the Authority and non-payment of fee for extension payable to RERA, as per  copy of the acknowledgement  being filed today in the registry of the authority. Further stated that assets and liabilities of M/s Sarv Realtors and M/s  DSC Estate  Developers  after imposition of moratorium have not been transferred to the management of those  companies as he is unable to do so the same as moratorium is going  on the whole company of Supertech Ltd. and there is no direction w.r.t the same from Hon’ble NCLT. Further stated that  they have enclosed with the affidavit Annexure-J from page 82 to 89 which is details of transfer entries dated 31.03.2020 passed on to M/s Sarv Realtors and M/s DSC Estate Developers.  IRP further stated that there was an interim order from Hon’ble NCLAT Delhi after submissions of resolution proposal by the ex-promoters of the company i.e. Supertech Ltd. which is still pending for decision and next date of hearing is 03.05.2024 and once that proposal gets through/approved by NCLT  only then further process of revalidation of licence and renewal of RERA registration shall be taken up.   Shri Mohit Arora director of M/s Sarv Realtors and M/s  DSC Estate  Developers is present in person and filed authorization letter and copy of DIN and counsel of M/s Sarv Realtos Ltd. and M/s DSC Estate Developers have filed Power of Attorney.  Mr.Mohit Arora agreed and stated that they had taken over  M/s Sarv Realtors and M/s  DSC Estate  Developers   from M/s Supertech Limited and now they are running the projects and  bank accounts of  these are being managed  by them.   The counsels for the complainant (s) states that since the IRP has not filed the QPR and has not updated the status of the project,  they are unable to know the factual position of the project.   Further stated that  since the IRP entered into the shoes of promoter in June,  2022  and  had been assigned the power of supervision of each and every project of Supertech Ltd. and he must do the compliances.   The counsels for the complainants further stated that IRP  as well as management of M/s Sarv Realtors and M/s  DSC Estate  Developers  are not disclosing the exact status of the projects Hues and Azalia. Further stated that as per affidavit filed by IRP, if the projects Hues and Azalia already stands transferred to M/s Sarv Realtors and M/s  DSC Estate  Developers on 31.03.2020 then why M/s Sarv Realtors and M/s  DSC Estate  Developers are not doing compliances, The Authority must direct them to do the same in the interest of the allottees.   The counsel for M/s Sarv Realtors and M/s  DSC Estate  Developers  and Mr.Mohit Arora states at bar that they have received all the assets and liabilities of the project “Hues and Azalia” in March 2020.   Shri Rohit Arora - the counsel on behalf of M/s Sarv Realtors and M/s  DSC Estate  Developers further brought attention of the authority towards para No.5 page 79 of the order of the authority dated 29.11.2019 which is reproduced as under:-   (v) All the  assets and liabilities including customer receipts and project loans of whatsoever nature, in the Project “Supertech Hues and Azalia” in the name of Supertech Ltd be shifted to Sarv Realtors Pvt Ltd/DSC and others. However,  even after  the rectification, Supertech Ltd.  will continue to remain jointly responsible for the units marketed and sold by it and shall be severally responsible if Sarv Realtors Pvt. Ltd/DSC and others fail to discharge its obligations towards the allottees.   IRP of the company stated that the director of M/s Sarv Realtors and M/s  DSC Estate  Developers will file the exact status  of the project as they have already committed during the proceedings that they have taken over the project on 31.03.2020 from M/s Supertech Ltd.  The Authority hereby directs the authorized director of M/s Sarv Realtors and M/s DSC Estates to   clarify the exact status of QPRs and updated  status of registration of the project Hues and Azalia in the shape of affidavit and that they shall  apply  for registration /extension of these projects within next 20 days .  In case they have not filed the reply to the complaint cases, in which they are impleaded,  they will have to file the reply within 15 days.   Part arguments heard. Matter be put up before the full bench on 27.05.2024 at 3.00 PM for further arguments.

    Stage: PENDING

  • 12JAN 2024
    Hearing

    Judge: SANJEEV KUMAR ARORA

    On the last date of hearing, authority directed IRP to submit a copy of claims admitted by him. The same have been submitted and uploaded on the website of the Authority. The counsel for the complainant states that as per the order dated 29.11.2019 passed by the authority  in suo motu No.5802/2019 M/s Supertech Ltd. had to comply with certain directions w.r.t transfer of assets and liabilities to Sarv Realtors and DSC and others  which perhaps has not been complied with till date and further stated that  RC of  project Hues and Azalia has already expired on 31.12.2021. It was further stated that as per directions of the authority vide its order dated 29.11.2019 it was clearly mentioned that  Supertech Ltd. will continue to remain jointly responsible for the units marketed and sold by it and shall be severally responsible if Sarv Realtors and DSC and others failed to discharge its obligations. The counsel for the complainant further submitted an email dated Jan. 23, 2023  which states that change of promoter from Supertech Ltd. to Sarv Realtors does not affect any rights of the allottees and further draws attentions towards the mail dated 04.10.2023 which is sent by Mr. Hitesh Goyal IRP of Supertech Ltd. which states that project Hues is a part of Serv Realtors Pvt. Ltd. which is a different company and not a part of Supertech Limited.,  therefore,  the allottees of said project should reach out to the concerned team of Sarv Realtors Pvt. Ltd. Further draws attention of the authority towards mail dated 14.06.2022 sent to authority as well as by the IRP  which states that in compliance of the order dated 29.11.2019,  all the assets and liabilities of the project were transferred from Supertech Ltd. to Sarv Realtors and M/s DSC Estate Developers Pvt. Ltd. on 31.03.2020,  therefore,  the projects are not assets of corporate debtors, hence Project Hues is not covered under insolvency proceedings. The authority hereby directs the IRP to file an affidavit within 15 days, with an advance copy to the complainants,  to confirm the facts given in the mail dated 14.06.2022 w.r.t the assets and liabilities having been transferred to Sarv Realtors and DSC Estate Developers Pvt. Ltd and IRP must be present on the next date of hearing in person to clarify the status of the projects which are covered under CIRP and which are not covered under CIRP and is further directed to file  QPRs and pending details which have not yet been filed in the authority of various projects. Further,  one of  the directors of Sarv Realtors and DSC Estate Pvt. Ltd. duly authorized by the Board, should also put in personal appearance to clarify the status of the project,  direction is being given to safeguard the interests of the allottees of these projects. Arguments heard. Matter to come up on 19.04.2024 for further arguments.

    Stage: PENDING

  • 6OCT 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The counsel for the respondent  and the IRP present  in person as per directions of the authority state that they have already filed the affidavit as well as status of construction of various projects, as per  the directions of authority  vide its order dated 25.08.2023.  The affidavit was filed on 27.09.2023  and the construction status report was filed on 03.10.2023. The copy of the same has been handed over to all the concerned parties still if counsel of any concerned party has not received the same, the counsel for the respondent is hereby ready to  hand over the copy of the same to the concerned complainant or his counsel. IRP present  in person stated that moratorium is applicable on all the projects of Supertech Ltd. and the same had been granted by Hon’ble NCLT New Delhi on its order dated 25.03.2022. Further stated that an appeal was filed against this order by the Suspending Directors before Hon’ble NCLAT in appeal No.406 of 2022 which is still pending before the Hon’ble NCLAT.  However an interim order was passed in that appeal stating that  CoC was restricted to ECO village-II and all other projects of Supertech Ltd. were to be constructed under the supervision of IRP alongwith the assistance of ex-management employees and workmen vide its order dated 10.06.2022. Further on 12.09.2022 the Hon’ble NCLAT Delhi further passed an order “CIRP order has not been stayed, the moratorium is continuing”.  Further, stated that the orders dated 10.06.2022  of NCLAT  was challenged before Hon’ble SC which was heard  by the Hon’ble SC and an interim order was issued upholding the orders dated 10.06.2022 of NCLAT. This interim order was passed by the Hon’ble SC on 11.05.2023 and it was further listed for hearing on 24.08.2023 but on that date due to any reason, the matter could not be taken up and the next date of hearing is still not notified.  Further stated that the NCLAT is continuously hearing the appeal and the next date of hearing is 19.10.2023.  Further stated that Hon’ble NCLAT vide its order dated 5.07.2023 categorically stated after taking into consideration the orders of Hon’ble SC that   “In view of the fact that it is IRP who is under control of the entire CIRP in all projects,  it is necessary that the status report which is submitted in the Court should be put on the website of the Supertech so that it can be assessed by everyone”. Further the counsel for the complainant in CR No.1730 of 2023  and CR No.2144/2021,  424/2022 and some other complaints states that project Azalia and Hues are not covered in the list of the projects in which moratorium is continuing,  hence those should be taken up separately. Further IRP present in person states that  he has already admitted the claims of various allottees from the projects Azalia and Hues as treating them  as contingent liability of the corporate debtor i.e. Supertech Ltd.  The counsel for the complainants states that they are not aware about the claims being asked for by the IRP of Supertech in case of the projects of Azalia and Hues.  The counsel for the respondent and IRP present  in person states that the claim of projects Azalia and Hues were admitted by him after the order dated 14.10.2022 of Hon’ble NCLAT. IRP present in person further states that they are still accepting the claims of allottees of Azalia and Hues for the purpose of verification. The authority hereby directs IRP to submit a copy of the claims admitted by him within a period of 15 days and the same may be uploaded  on the website of the authority also. Complainants are free to file the response to the affidavit filed by IRP within 15 days. IRP to be present before the authority and co-operate as and when required just to safeguard interest of the allottees and subject to final directions of the Hon’ble NCLAT and Hon’ble SC. Arguments heard. Since the matter is sub-judice before the NCLAT and Hon’ble SC it is being adjourned to 12.01.2024 for further proceedings.

    Stage: PENDING

  • 25AUG 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    Matter is adjourned to 06.10.2023.

    Stage: PENDING

  • 1MAR 2023
    Hearing

    Judge: ASHOK SANGWAN

    The counsel for the complainant states that even though respondent company is under NCLT proceedings and moratorium has been announced,  it shall be the duty of the Resolution Professional to respond the complaints and be liable on behalf of the company to comply with the orders of the authority. Therefore,  notice be issued to the Resolution Professional for the next date with detailed status of the project and response to the complaint. The counsel for the complainant further states that section 14 of IBC moratorium can only operate against civil courts and execution petitions lying in civil courts and there is no bar of proceedings in quasi judicial forum. With regard to this, counsel for the complainant wishes to submit citations.             In view of the above,  the Resolution Professional is requested to assist the authority on the next date of hearing.                                    Matter to come up on  25.08.2023 for further proceedings.

    Stage: FIRST HEARING

Orders (13)

Judgement DetailsView full order PDF ↗

ARER, URUGRAI/ BEFORE THE HARYANA REAL ESTATE REGULATORY AUTHORITY, GURUGRAM Order rcserved o ll,O3.ZOZs Order pronounce d oft 07.O4.2OZ\ M/s Sn RV Realtors I,rivatc Limitcd. "Supertech Hucs", Sector- 68, Gurugram, Haryana Casc title Appearance cR/72601 2022 cR/7312/2024 CORAM: Shri Arun Kumar Shri Vijay Kurnar Goyai Shri Ashok Sangwan Ilajinder Mohan Dhar & Usha Nehru V/s M/s Supertech L jmited (lt:1), M/s SARV Realtors Private Limited ( R:2) Devesh Dubey & Anubha Upadhay V/s M/s Superrech Limited (ll:1), M/s SARV Realtors Private Limited IR:2) Ajay Jalali & I,riyanka la1a1i V/s N4/s Supertech Limired IR:1), M/s SARV Itealtors I)rivate l,imited (R:2) Sh. lJimanshu Gautam (Complajnants) Sh.

Ilhrigu Dhami IRespondent no.1) l\4 s. lsha Dang (Respondenr no.

2) Sh.

Ajay kumar Singh IComplainants] Sh. tlhrigu Dhami IRespondent no.1) l\4 s. lsha I)ang (llcspon(lcnt no.2l Sh.

Ilimanshu Gautam (Complainants) Sh.

Bhrigu Dha mi IRespondent no.1J Ms. lsha Dang (Respondcnt no.2J Chairman Member Member 1, ORDER 'l'his order shail dispose of 3 compraints titled above fired before this Authority under section 3i of the Real Bstate (llegulation and Development) Act, 20.16 (hereinafter referred as "the Act") read with rule 2U of the Haryana Real Flstatc Complaint No.

5847 of 2022 and 2 others Page 1 ol26 NAMI OF ]'HE BUILDER PROIECT NAME J S.

No, Case No. | ,li*jie*)ioi 2.

3. ffiHARERq ffieunuenAu Complaint No.

5847 of 202 2 and 2 others (llegulation and Development) Ruies,2017 (hereinafter referred as,.the rules,,J forviolationofsectionll[4](a)oftheActwhereinjtisinteraliaprescribedthat the promoter shall be responsible for all its obligations, responsibilities and functions to the allottees as per the agreement for sale executed inter se parties. 'l'he core issues emanating front them are similar in nature and the complainant(s] in the above referrecl matters are allottees of the project, namely, "Supertech Ilues", Sector- 68, Gurugram, Ilaryana being developed by the respondent/pr pondent/promoter i.e., M/s SARV Realtors pvt.

Ltd. private t,imited. .l'he terms and conditions of the allotment Ietter, buyer,s agreements, fulcrum ofthe issue involved in all these cases pertains to failure on the part of the promoter to deliver timely possession ofthe units in question seel(jng award ofrefund of the entire paid up amount along with interest and other reliefs.

The details ofthe complaints, unit no., date ofagreement, possession clause, due date ofpossession, totalsale consideration, total paid amount, and relielsought are given in the table below: Proiect Name and Location nroject'arei negistratite are. f'la tuie-of tne p roi ect : DTCP license no. and oth "supe.iectr ttuei;- Seci* OB, cut 55.5294 acres 32.83 acles lii!!!!t"c-r:lI er details 8ram.

DTCP License No.

Valid up to Area admeasurin Name oflicensee Holder 89 of 2014 dated 08.08.2014 07.08.2024 10.25 acres DSC Estate Developer Lrd.

106 of 2013 dated 26.72.2073 25.12.2017 '13.74 acres Sarv Realtors Pvt.

Ltd.

107 of 2013 dared 26.12.2013 134 of 2014 dared 26.0A.2014,___ 135 of 2014 dated 26.08.2074 25.12.2017 25.0A.2024 ,5.08.20;; 13.75 acres 4-85 acres Sarv Realtors Pvt.

Ltd. tsc E'irre D;r;lop;'- L!q, DSC Estate Developer Ltd.

136 oF 2014 dared 26.08.2014 25.0A.2024 s.Bta;;s DSC Estate Developer t,rd. l Prt.

I - Pvt.

2.

3.

Pvt.

Page 2 ol26 HARER,.. _G!BqGRAt\ lA Registerea stered not l]:flfl:l:l *,.'li^. ," r82 or20r7 dared o4.os.2ot? v aro up to 31.12.2021 I D, and n certifi te as Int session r buyer's a , li,::,:,:.:-,! :ip, rrnit: 1he posses5ion uJ tht i:::'::ii''''.0'lt le qiven b Lhe AttoLtee/'hy t.n^e_L::1.::! ,by,l:tty 20t8.

However, rhis p, rt,,,,1 Lun oe extended Ior o furrher ora monrhs. ., rce period o/ 6 1' Po,ss,e.xi,on ol .lhp ltnit: 1he pe.,:p55bt1 61 111, i;::'::::':::ni" h: oyy"n-rv, the Attotrec/\ t,v ,!^"-, !:, r, nl by epi i t,, ii ;' ; ;';;;;;:', ;:,', pcrrcd.con be axtt.nded for 0 lurther grqce period oI6 months. y371;'t'1" n,"*.".

1" n,"*.".ttin ol Lhe un it sha bc eNcn tn 42 !!,)!):::.lt r,rrember 20 t 7 or axtettdcd 7erto,1 Cr No- 1,372- 2024 Complaint no., unit no. and iiii AIlotlncnt o,t...1,"r*,,,r! hy the aqrecmcnt. ir;;;;;',;" develobPr hor.h,, ^^-- - ,rr_, 1 g 1. i ) : i " :i;l i: ; :;:,,, : ;! :,;,, ; " : :,, :ir, :.::!.lil r rr.o:toy in ha n d inst uve rpossess?ua uJ tne untl beyond the oiven nernd plus Lhe groce ,^u.r:oa of U months inct upLo ra.he o11e, letter,l l^osscfsio, or octuql physrcol pus.session whtchevr.t ts eorlipr.

Casc title, Date of filing ofcomplaiIt and reply status cxlsa+zpozi Ra,inder [4ohan Dhar & Usha Nehnl V/s Supertech Limited And M/s SARV Realtors Private Limited DOF: t2.09.2022 Due dare of possession Totat sale consideration and Totat amount paid by the complainant in Rs.

TC: 1,04,65,21A / - {As per payment plan at page 1B of comptajnrl i B7,20,12a/.

Lener And BI]A 1701,171r toor, Tower O 1765 sq fr. [Supcr area ) lPagc 17 of conrpiaintl atsA 27.01.2016 JPage 16 ot conrplarntl lanuary , ZOlg (As per clause I ol the buycr,s dovcloper agfeenrent:by luly 2018 plus 6 Ntonth grace period) I Cr No.

5847 - 2022 Page 3 of 26 Complainr No.

SB47 of 2022 and 2 others l c; ru".1 ) zzdo. ) J zozz I * HARER, #* eunuennu Complaint No.

5847 of2022 and 2 others Reply by R2 tsARV): 23.12.2024 45 otcomplain z ca/tzeo/zozi t)cve\h Duhey & Anu bhr tiprdhay V/\ Supc.reLh Limrred And M/s SARV Realrors Prvare Lin)rred DOF: 1411.2022 Reply by R1[SARV): 02.04.2025 rsU1, 15th floot Tower t- 1180 sq. ft. (Superarea) JPage 24 ot complaintl auA I otober,2o- 20.08.2ota I tAs per ctau\e i 1 oI rhe buyer's tPagr 2.1,,i ] devetopcr compla'nrl i agrecment. hy Aprit20t7 i plus 6 Monrh grace period) TC: 47,45,7AO /. [As per paymenr p at pagc 25 ol complajnti 77,31,676/. lAt page 39 of complaintl r I cR/t.tlz/202a ) 0201, z"d itoor, i Tower p i AlaY lalalr & ] Pn!dn,{r jrta,i v/s i rzr,s ,q r, I r4/, Supc o(h ] tsuper,real t_rrnrred And M/s I sARv RPrlror\ ] lr,e" tool , Pnva lp Lrmr(i.d co. mr(i.d co.nplarnll l DOF:09 04 2024 Rcpty by Rl(sARvl: i | 27 oe2o24 ] Reliefsn"oh' I BI}A l ) 2s.07.2014 | ,,"ru ,, u, complaintl 31.05.2018 (As per clause 25 olrhe huyer's developer agrccmcntiby November 2017 plus 6 Month gracc period) TC: 1,36,43 ,935 / - lAs per paymenr pl at page 20 ol complajntl 4434,617 /.

IAs per statemenr ( account on page 33 complaintl paSe ntl ian 1. 'l'he facts of all the complaints filed by the complainant(s)/alloftee(sJ are similar.

Out of the above-mentioned case, the particulars of lead case CR/5547/2022 titled as Ra_rrnder Mohan Dhar and llsha Nehru V/s M/s Supertech limited And M/s SARV Reoltors private Limited are being taken into consideration for dctermining the rights of the allorteeIsJ.

Proiect and unit related details Litigation Charges A.

Page 4 of26 5.

The particulars of the project, the details of sale consideration, the amount paid by the complainant, date ofproposed handing over the possession, delay period, if any, have been detailed in the following tabular form: CR/5847/2022 titled as Rajinder llohan Dhor and Usha Nehru V/s M/s t uperlglh ljrnlei 4n4_ry1$4!y !9lltors Priuote Limited S.

No.

Particulars Details 1.

5.

Name of the project Supertech Hues, Sector-68, Gurgurgram Project area 55.5294 acres Nature of_p1o_pqt RERA registered/not Grolpllousing Colony *HARERA ffi eunuennirl 6. o.

9. registered -__ Validity Status Name of licensee Unit no.

Unit measuring nate of S"o*i.g- 27.01.201.6 Registered vide registration no.

182 of 2017 dated 04.09.2 017 3t.72.2021.

1.06 &L07 of 2013 dated 26.1.0.201.3 25.72.201,7 Sarv llealtors Pvt.

Ltd. & ors.

1 1?oi" 1?,, n"o",T il I (Lqg r_o lZql sorlrtbrnt) 1765 sq. ft. (Super area) (Page no.

17 of complaint) qcl99!

9!!

10.

Possession clause Page no-.12 of complaintl 27.07.2016 (Page 16 of complaint) 1. 'fhe possession ol the allotted unit sholl be given to the ollottee /s by the company by July 2018.

However, this period can be extended for a further groce period of 6 months.

6 months. leee 1-9,of l\e !Srnp!qt!!l Ilate of B u ilder execution of developer lJue oate ol possesslon _] lulyZUIUr bmonthS: lanuarylU Total saf e consideration Rs.

1 ,0+,65,218 /- (page lti of complaint) Total amount paid by the I1s.87,20,128/- " t.

74. complainant | (page 36 to 44 of complaint) Occupqtioncertificate Notobtaincd Offer olpossessiot I Not offcrcd Complaint No.

5847 of 2022 and 2 others DTPC License no.

ValidiW status 15.

Page 5 of 26 11 1 n1 B.

6. ffi HARERA ffi eunGnnvr complaint No.

5847 of 2022 and 2 others Facts ofthe complaint 'l'he complainants have made the following submissions in the complaint: - That on 26.12.2013 DGTCP, Ilaryana has granted License Number 106 & 107 to the Respondent No.2 i.e.

Sarv Realtors Pvt t,td (1000/o subsidiary of Supertech Ltd) for Group Housing Scheme o n 27 .493 acres.

That on 27.01.2016, the complainants Mr.

Rajinder Mohan Dhar and Mrs.

Usha Nehru booked a residential flat bearing unit no.

R0380O01707/ Flal 1701 in Tower - 0 admeasuring 1765 sq. ft. in the project named "supertech Hues" situated in Sector 68, Gurugram. 'fhal on 27 .01.201,6, builder buyer agreement was entered into between thc parties wherein as per clause 24, the developer should offer possession of unit by July, 2018 with a grace period of6 months. 'fhat the respondent no.

1 demand ed Rs.87 ,20,128 /- from the complainant at the time of booking out of the total consideration amount of Rs,1,03,56,074l-.

That out ofthe total cost ofthe said unit a sum of Rs.

B7 ,2O,l2B l- has already been paid by the complainant till date but the construction ofthe flat is still incomplete.

Even the tower containing the flat has not been constructed yet and there is no hope of offering the possession even after a delay of almost 3.5 years. 'l-hat the undue delay by the respondent no.

1 in offering the possession to complainant caused great monetary loss to the complainants in terms ofthc interest payable on the above said amount. id amount.

That even after payment of more than 84% of the total consideration amount, the builder raised another demand of the amount of Rs.

16,35,946/- vide letter dared 04.04.2 01u.

II, I.

III.

IV.

VI.

VII.

Page 6 of 26 ffi uRnrR:, ffieunuenRu complaint No.

5847 of 2022 and 2 others VIII. 'Ihat the demand of complete consideration amount without even constructing the flat as per construction plan is arbitrary' illegal' unjustified' mischievous, fraudulent, against the principle of natural iustice and against the interests of the complainants IX.

That despite repeated calls, meetings and emails sent to the respondents' no definite commitment was shown for timely offering the possession of the flat and no appropriate action was taken to address the concerns and grievances ofthe complainant.

Thus, the respondents not only breached the builder buyer agreement but also cheated the complainants and as a result of this misconduct of the respondents, the complainants lost their faith on him and no Ionger want to continue with this project and want refund ofthc amount paid by them till the present date along with the interest as per provision of Section 12 and Section 18 of the RERA Act, 2016' X. 'lhat both the complainants are senior citizens and repeated calls' meetings and correspondences with the respondent no 1 and multiple visits to know the actual construction status not only caused loss to the complainants in terms of time, money and energy but also caused mental agony to them xl. .lhat the cause ofaction arose in favour ofthe complainants and against thc respondents from the date of booking of the said units and it further arose when respondents failed/neglected to deliver the flat within a stipulated time period. '[he cause of action further arose when the respondents have not completed the proiect with the assured facilities and amenities lt further arose and it is continuing and is still subsisting on day-to-day basis as the respondents have not fulfilled thei illed their obligations as per the buyer's agreement.

C.

Relief sought by the complainant: - Page 7 of 26 m HARERi #- eunuennu 7.

The complainants have sought following relief(s): II.

To direct the respondent to refund the whole amount paid by the complainants to the respondent along with the interest @ 240lo per annum (rate at which respondent charges interest from the complainant) counted from the date of deposit to the date of realisation of refund.

To direct the respondent to pay Rs.

1,50,000/- cost of litigation.

8.

0n the date of hearing, the Authority explained to the respondent/promoter about the contraventions as alleged to have been committed in relation to section 11(4) (a) ofthe act to plead guilty or not to plead guilty.

No reply has been submitted by the respondent no.1 ie., M/s Supertech t'td However, the counsel for respondent no. t has stated that the respondent no.1 is under CIRP vide order dated 25.03.2022 passed by the Hon'ble New Delhi in case no.

II)-204/ND/2021 titled as lJnion Bank ol Indid Versus M/s Supertech Limited a\d moratorium has been imposed against the respondent no l company under section 14 of the lBC, 2016 Therefore, no proceedings may continue against the respondent no.

1 D, Reply by the respondent no, 2 10, The respondent is contesting the complaint on the following grounds:- i. 'lhe respondent no.

2 is one ofthe leading real estate developers in the State of Haryana and NCR.

It has several proiects across the state, and as such has built a great reputation for having the hiShest quality of real cstate developments. 'fhe respondent no.

2 has been represented in the instant proceedings by its authorized representative, Ms.

Isha Dang One of its marquee projects is the Azalia, located in Sector 68, Gurugram, and Haryana. ii.

That the respondent no.2 was issued license bearing no's 106 and 107 dated 26]'22073 and license no's.

135 and 136 of 2014 dated 26 08 2014 Complaint No.

5847 of 2022 and 2 others I.

9. hers I.

9.

Page I of26 * HARER^ S*eunuenaHl Complaint No.

5847 of 202 2 and 2 others for developing the said land. 'l'hat in furtherance of the same, the Answering Respondent and M/s.

Supertech Ltd. had entered into two Joint Development Agreement's dated 25.04.2014 and 26.08.201 4 respectively.

That in terms of the said JDA's, M/s.

Supertech Ltd. was to develop and market the project.

The complainant along with many other allottees had approached M/s Supertech Ltd., making enquiries about the proiect, and after thorough due diligence and complete information being provided to them had sought to book unit(s) in the project. 'Ihat, after fully understanding the various contractual stipulations and payment plans for the unit, the complainant executed the allotment letter dated 27 .01.2o1,6 for unit bearing number No.

R0380001 701/ 1701, towcr - O, 17n floor, having a super area of 1765 sq. ft. (approx..) for a total consideration of Rs.

1,09,00,160/- exclusive of applicable charges and taxes. 'fhat in the interim with the implementation of the Act, 2016 the project was registered with the Haryana Real Estate Ilegulatory Authority, Panchkula vide llegistration no. "182 of 2017", dated 04.09.2017 upon Application filed and in the name of Supertech Limited.

That this Authority vide order dated 29.11,2019 passed in Suo Moto complaint bearing no.

580212019, had passed certain directions with respect to the transfer of assets and liabilities in the said projects namely, "Hues & Azalia", to the respondents no.

2 i.e. and M/s.

SARV Realtors Pvt.

Ltd. and M/s DSC Estate Developers Pvt.

Ltd. respectively.

This Authority had further directed that M/s.

Sarv llealtors Pvt.

Ltd. and M/s.

DSC Estate Developer Pvt.

Ltd. be brought on as the promoter in the respective projects iii. vl. vll.

Page 9 of 26 vllt.

HARER Complaint No.

5847 of 2022 and 2 others GURUGRA[/ instead of M/s.

Supertech Ltd.

Certain this Authority are as under; important directions as passed by A. ssed by A. (i)'Ihe registration of the project "Hues" and "Azalia" be rectified and SAIIV Realtors Pvt.

Ltd./DSC and others, as the case may be, be registered as promoters.

B. (v)All the Assets and liabilities including customer receipts and project loans of whatsoever nature, thc project IITJES and Azalia, in the nanlc of Supertech Ltd. be shifted to Sarv Realtors I,vt.

Ltd/ I)SC and others.

However, even after the rectification, Supertech Ltd. will continue to remoin jointly responsible for the units morketed ond sold by it and shall be severolly responsible if SARV Realtors Pvt.

Ltd./DSC And other fail to discharge its obligotions towords the olottees. 'lhat in lieu of the said directions passed by this Authority all asset and liabilitics have becn since transferred in the name of thc rcspondent no.

However, in terms of the said Order, M/s.

Supertech Ltd. still remains jointly and severally Iiable towards the booking/ allotment undertaken by it before the passing of the said Suo Moto Order.

That thereafter the IDA's were cancelled by the consent of the respondent no.2 and M/s Supertech Limited vide cancellation agreement dated 03.10.2019 and the respondent no, 2 fronr there on took responsibly to develop the project and started marketing and allotting new units undcr its ltam e. 'l-hat in terms of the said cancellation agrccmcnt the rcspondent no.

2 and M/s Supertech Limited had agreed that as M/s Supertech Ltd. was not able lx. to complete and develop the project as per the timeline given by this Hon'ble Authority and DTCP, therefore the parties had decided to cancel the J DA's vide cancellation agreement. x.

In the interregnum, the pandemic of Covid 19 has gripped the entire nation since March of 20 20.

The Government of India has itself categorized the said Page 10 of 26 ffi HARERA #-eunuennH,r complaint No. plaint No.

5847 of 202 2 and 2 others event as a 'Force Majeure' condition, which automatically extends the timeline of handing over possession of the apartment to the complainant.

That the construction of the proiect is in full swing, and the delay if at all, has been due to the Government-imposed lockdowns which stalled any sort of construction activity.

Till date, there are several embargos qua construction at full operational level.

Preliminary Objections i.

That the present complaint further deems to be prima facie dismissed as in terms of the own admission of the complainants the BIIA was executed solely with M/s.

Supertech Ltd. and furtehmrore, all payments qua the booking were also made to M/s.

Supertech Ltd. 'l'hus, there is no privity of contract nor any payment made to the respondent no.

2, thus the present complaint deems to be dismissed on this ground alone. ii. 'the present complaint further also deems to be prima facie dismissed for non-joinder of necessary parties.

It is reiterated that in terms of the own admission of the complainant the BBA was executed solely with M/s.

Supertech Ltd. ]'hus, the present complaint deems to be dismissed for non-joinder of M/s.

Supertech Ltd. iii. 'Ihat as M/s.

Supertech t,td. and the respondent no.2 are jointly and severally liable in terms of the Suo Moto Order passed by this Authority for the project in question, thus the present matter cannot proceed further until the said liability qua the allotees is not bifurcated between the respondent no.2 and M/s.

1'he respondent no.2 cannot be made wholly liable for allotments undertaken and monies/ sale consideration received by M/s.

Supertech Ltd. xi.

Page 17 of 26 complainr No.

5847 of 2022 and 2 others vl.

VII. s vl.

VII. ffi HABERI S"eunuenRtr,l That the complaint filed by the complainant is not maintainable in thc present form and is filed on the false and frivolous grounds The bare reading of the complaint does not disclose any cause of action in favour of the complainant and the present complaint has been filed with malafide intention to blackmail the respondent no.2 with this frivolous complaint' 'Ihe delay in construction was on account of reasons that cannot bc attributed to the respondent herein.

The flat buyers' agreements provide that in case the developer/respondent delays in delivery of unit for reasons not attributable to the developer/respondent, then the developer/ respondent shall be entitled to proportionate extension of timc for completion of project.

In view of the force majeure clause, it is clear that the occurrence of delay in case of delay beyond the control of the respondent, including but not limited to the dispute with the construction agencies employed by thc respondent, Covid-19, shortage of labour, shortage of raw materials, stoppage of works due to court orders, etc. for completion of the project is not a delay on account of the respondent for completion of the project' 'lhat with respect to the agreement, the time stipulated for delivering the possession of the unit was on or before luly, 201ti.

However, the buyer's agreement duly provides for extension period of 6 months over alld above the said date. 'Ihus, the possession in strict terms of the buyer's agreement was to be handed over in and around lanuary, 20I 9 l{owever, the said datc was subject to the force majeure clause, i.e. "Clause 43".'l'he delivery of a project is a dynamic process and heavily dependent on various circumstances and contingencies.

In the present case also, the respondent had endeavored to deliver the property within the stipulated time' Page 72 of 26 ff HARERA ffieunuennn,l v[1. nnn,l v[1. 'lhe timeline stipulated under the flat buyer's agreements was only tentative, subiect to force majeure reasons which are beyond the control of the respondent.

The respondent in an endeavour to Finish the construction within the stipulated time, had from time to time obtained various licenses' approvals, sanctions, permits including extensions, as and when required' Evidently, the respondent had availed all the licenses and permits in time before starting the construclion.

Despite the best efforts of the respondent to handover timely possession of the residential unit booked by the complainant, the respondent could not do so due to certain limitations, reasons and circumstances beyond the control of the respondent.

Apart from the defaults on the part of the allottees, like the complainant herein, the delay in completion of project was on account of the following reasons/circumstances like: i.

Implementation of social schemes like National Rural Employment Cuarantee Act ("NREGA") and Jawaharlal Nehru National Urban Ilenewal Mission ("INNURM"), there was a significant shortage of labour/ workforce in the real estate market as the available labour had to return to their respective states due to guaranteed employment by the Central/State Government under NREGA and lNNtlRM Schemes 'l-his created a further shortage of labour force in the NCR region' Large numbers of real estate proiects, including that of the Respondent herein fell behind on their construction schedules for this reason amongst others. 'lhe said fact can be substantiated by newspaper articles elaborating on the above mentioned issue of shortage of lahour which was hampering the construction projects in the NCR region 'l'his certainly was an unforeseen one that could neither have been anticipated Complaint No.

5847 of2022 and 2 others Page 13 of26 ffi HARERA ffi eunuennrvt nor prepared for by the respondent while scheduling their construction activities. ctivities.

Due to paucity of labour and vast difference between demand and supply, the respondent faced several difficulties including but not Iimited to labour disputes.

All of these factors contributed in delay that reshuffled, resulting into delay of the Project ii.

That such acute shortage oflabour, water and other raw materials or the additional permits, Iicenses, sanctions by different departments were not in control of the respondent and were not at all foreseeable at the timc of launching of the project and commencement of construction of thc complex..

That the intention of the force maieure clause is to save the performing party from the consequences of anything over which he has no control 'Ihc delay in construction, if any, is attributed to reasons beyond the control of the respondent and as such the respondent may be granted reasonable extension in terms of the agreement.

That the project "HUES" is registered under the Haryana Real Estate Regulatory Authority vide registration certificate no 182 of 2017 dated +.9.2017.

The Authority had issued the said certificate which is valid for a period commencing from 04.09,2017 to -11"12 2021' 'lhat the possession of the said premises under the said BBA was proposed to be delivered by the respondent to the apartment allottee by luly' 201t] with an extended grace period of 6 months which comes to an end by January, 2019.

The completion of the building is delayed by reason of Covid-19 outbreak, non-availability of steel and/or cement or other building materials and/or water supply or electric power and/ or slow Complaint No.

5847 of 2022 and 2 others xI. xll.

Page 14 of 26 HARERA MGURUGRAM xul. down strike as well as insufficiency of labour force which is beyond the control of respondent . 'Ihat the enactment of the Act, 2016 is to provide housing facilities with modern development infrastructure and amenities to the allottees and to protect the interest of allottees in the real estate sector market. or market.

The main intention ofthe respondent is just to complete the project within stipulatcd time submitted before the Authority.

According to the terms of builder buyer's agreement also it is mentioned that all the amount of delay possession will be completely paid/ adiusted to the complainant at the time final settlemcnt on slab ofoffer ofpossession.

Further, compounding all these extraneous considerations, the Hon'ble Supreme Court vide order dated 04.11,2019, imposed a blanket stay on all construction activity in the l)elhi- NCR region.

It would be apposite to notc that the 'Hues' project of the respondent was under the ambit of the stay order, and accordingly, there was next to no construction activity for a considerable period.

It is pertinent to note that similar stay orders havc been passed during winter period in the preceding years as well, i e.

2017- 2018 and 2018-2019.

It is most respectfully submitted that a complete ban on construction activity at site invariably results in a long-term halt in construction activities.

As with a complete ban the concerned Labor is lct ofland the said travel to their native villages or look for work in other states, the rcsumption of work at site bccomes a slow proccss and a steady pace of construction in realized after lon8, period of time. xtv.

That, graded response action plan targeting key sources of pollution has been implemented during the winters of 2017 -1,8 and 2018-19, 'Ihese short-term measures during smog episodes include shutting down powcr Complaint No.

5847 of 2022 and 2 others xv.

Page 15 ol26 ffiHARERA S. eunuennu plant, industrial units, ban on construction, ban on brick kilns, action on waste burning and construction, mechanized cleaning ofroad dust, etc 'l'his also includes Iimited application of odd and even scheme xvi..lhetableconcludingthetimeperiodforwhichtheConstruCtionactivities in the Proiect was restrained by the orders of competent Authority/Court are produced herein below as follows:- S. llows:- S.

Court/Authority & Order Date Titlc Duration 1. ,.

National Green Tribunal 09.1r.2017 I'ress Note by SPCA- Environment Pollution (Prevention and Control) AuthoritY Vardhman Kaushik Union of lndia p."tr Not"-ir.ro.zotg Ban was lift after 10 da ot.rr.zora 10.11.201 3.

Supreme Court-23.1 2,?O18 Three-day ban on induslrial activities in pollution hotspots and construction work 23.72.2078 26.12.201 4.

EPCA/ Bhure lal Comnlittee Order-31.10.201q Complete Ban 01.11.2019 05.11.2 01 oa.11.zors 14.02.202 i+oi.zozo 03.0s.202 5.

Hon'ble Supreme Court 04 .11- .2019 -74.02.2020 M.C Mehta v.

Union of lndia Writ I'etition [c) no.

13029/1985 6.

Government of lndia Lockdown due to Covid 19 7.

Government of lndia Total Lockdown due to Covid- 79 37 weeks (appro 8 weeks \ ?04 ximately) Unfortunately, circumstances have worsened for the respondent and thc real estate sector in general.

The pandemic of Covid 19 has had devastating effect on the world-wide economy.

However, unlike the agricultural and tertiary sector, the industrial sector has been severally hit by the pandemic' iteo ays 8to r18 to B 9to r19 to 0 Ito 20 ,lnI Complaint No.

5847 of 202 2 and 2 others xvll.

Page 16 of 26 Complaint No.

5847 of 2022 and 2 others xvlll. ffi HARER , S* eunuennu 'Ihe real estate sector is primarily dependent on its Iabour force and consequentially the speed of construction.

Due to government-imposed lockdowns, there has been a complete stoppage on all construction activities in the NCR Area till |uIy,2020.

In fact, the entire labour force employed by the respondent were forced to return to their home towns, leaving a severe paucity of labour. 'l'hat the pandemic is clearly a 'l"orcc Majeure'event, which automatically extends the timeline for handing over possession of the apartment. 'lhat the complainant is not entitled for any compensation or refund claimed except for delayed charges, if applicable as per clause 2 read with 24 of the builder buyer agreement.

1 1. ment.

1 1.

Copies of all the relevant documents have been filed and placcd on the record. 'l'heir authenticity is not in dispute.

I{ence, the complaint can be decided on thc basis of these undisputed documents and submission made by the parties.

E.

Jurisdiction ofthe Authority 12.

The Authoriry observes that it has territorial as well as subject mattcr jurisdiction to adjudicate the present complaint for the reasons given below.

E.t Territorialjurisdiction 13.

As per notification no.

1/92/2017-1TCP dated 14.12.2017 issued by'Iown and Country Planning Department, the jurisdiction of Real Iistate Regulatory Authority, Curugram shall be entire Gurugram District for all purpose with officcs situated in Gurugram.

In the present case, the project in question is situated within the planning area of Gurugram llistrict. l'herefore, this authority has complete territorial jurisdiction to deal with the present complaint.

E.ll Subject matter iurisdiction Page 17 of 26 Complaint No.

5847 of 2022 and 2 others 14.

Section 1 1(4) (a) of the Act, 2016 provides that the promoter shall be responsible to the allottee as per agreement for sale.

Section 11(4)(a) is reproduced as hereunder: Section 11 (4) The promoter shall- (o) be responsible for all obligations, responsibilities ond functions under the provisions of this AcL or the rules ond regulations made thereunder or to the allottees os per the agreement for sole, or to the ossocidtion of qllottees, as the case may be, till the conveyqnce of qll the apartments, plots or buildings, as the cqse may be, to the ollottees, or the common areqs to the associotion oI allottees or the competent authority, os the cose moy he: Section 34-Functions of the Authority: 34A ol the Act provides to ensure complionce of the obligations cost upon the promoters, the allottees and the real estote ogents under this Act ond the rules ond regulations mode thereundeL 15. eundeL 15.

So, in view ofthe provisions ofthe Act quoted above, the authority has complete jurisdiction to decide the complaint regarding non-compliance of obligations by the promoter leaving aside compensation which is to be decided by the !

G RA RA[I ARI URUG adiudicating officer if pursued by the complainant at a later stage.

F.

Findings on obiections raised hy the respondcnt no.

1 F.l Objections regarding force maieure.

16.

The respondent-promoter alleged that grace period on account of force majeure conditions be allowed to it. [t raised the contention that the co nstructio n o f the project was delayed due to force majeure co nditions such as demonetization, and the orders of the Hon'ble NGT prohibiting construction in and around Delhi and the Covid-19, pandemic among others, but all the pleas advanced in this regard are devoid of merit.

The flat buyer's agreement was executed between the parties on '27 .01.2016 and as per terms and conditions of the said agreement the due date of handing over of possession comes out to be 30.01.2 019, which was prior to the effect of Covid- 19 on above project could happen.The Authority put reliance judgment of Hon'ble Delhi High Court in case Page 18 of 26 ffi HA] #" eun RERA IUGRAM complaint No.

5847 of 202 2 and 2 others titled as M/s Holliburton Offshore Set'vices Inc.

V/S Vedanta Ltd. & Anr. bearing no.

O.M.P (l) (Comm,) no.88/ 2020 ond LAs 3696-3697/2020 dated 29.05.2020 which has observed that- "59.

The post non-performonce of the Controctor cqnnot be condoned due to the COVID-19 lockdown in March 2020 in lndia.

The Controctor wos in breach since September 2019.

Opportunities were given to the Controctor to cure the same repeoudly- Despite the same, the Contractor could not complete the Project.

The outbreok of o pandemic cannot be used os an excuse for non- performance of o controct for which the deodlines were much before the outbreok itself." 17.

But all the pleas advanced in this regard are devoid of merit. of merit.

Therefore, it is nothing but obvious that the proiect ofthe respondent rvas alrcady delayed, and no extension can be given to the respondent in this regard.'fhe events taking place such as restriction on construction were for a shorter period of time and are yearly one and do not impact on the project being developed by the respondent.

Though some allottee may not be regular in paying the amount due but the interest of all the stakeholders concerned with the said project cannot be put on hold due to fault of some of the allottees.

Moreover, the respondent promoter has already been given 6 months grace period being unqualified to take case of unforeseen eventualities.

Therefore, no further grace period is warranted in account of Covid-19.

Thus, the promoter/respondent cannot bc given any leniency based on aforesaid reasons and the plea advanced in this regard is untenable.

F.ll Obiection regarding CIRP against respondent no.

1 and consequent moratorium against proceedings against respondent no.1.

18.

Respondent no. t has stated that vide order dated 25.0320ZZ passed by the Hon'ble NCL'l', New Delhi Bench in case titled as lJ nion Bank of India Versus M/s Supertech Limited, thc Hon'ble NCl,'I has initiatcd CIIIP respondent no.1 and impose moratorium under section 14 ofthe IBC, 2016.

1'he Authority observes that the project of respondent no.

2 is no longer the assets of respondent no.

I Page 19 ol26 G.

1_9.

HARER,{ Complaint No.

5847 ot 2022 and 2 others W,GURUGRANI and admittedly, respondent no.2 ltas tal(en ovcr all assets and liabilities of the project in question in compliance of the direction passed by this Authority vide detailed order dated 29,11.2019 in Suo-Moto complaint.

HARERA/GGM/ 5802/2019.

Respondent no.2 has stated in the reply that the IDA was cancelled by consent of respondent no.1 and rcspondent no.2 vide cancellation agreement dated 03.10.2019.

In view of the above, respondent no. ondent no.z remains squarely responsible for the performance of the obligations of promoter in the present matter.

So far as the issue of moratorium is concerned, the projects Hues & Azalia stand excluded from the CII1P in terms of affidavit dated 19.04.2024 filed by SI1.

Hitesh Goel, IRP for M/s Supertech Limited.

However, ir has been clarified that the corporate debtor i.e., respondcnt no.1 remains under moratorium. 'l'herefore, even though the Authority had held in the Suo-Moto proceedings dated 29.11.2019 rhat respondent no.

1 & 2 were jointly and severa))y iiable for the project, no orders can bc passcd against respondent no.1 in the mattcr.

Findings on the reliefsoughtby the complainants.

G.l To direct the respondent to refund the whole amount paid by thc complainants to the respondent along with the interest @ 240lo per annum (ratc at which respondent charges interest from the complainant) counted from thc date ofdeposit to the date ofrealisation ofrefund.

In the present complaint, the complainants intend to withdraw from the project and is seeking return of the amount paid by her in respect of subiect unit along with interest.

Sec.

18(1) ofthe Act is reproduced below for rcady reference:- "Section 7B: - Return of omount qnd compensqtion 1B(1). lf the promoter fqils to complete or is unable to give possession of on oportment, plot, or building. - (o) in qccordance wilh Lhe terms of the ogreement Jbr sqle or, as the cose may be, duly completed by the dute specifred therein; or [b) due to discontinuance of his business as o developer on occount of suspension or revocotion of the registration under this Act or fot any other reoson, Page 20 ol26 HARER. complaint No.

5847 of 202 2 and 2 orhers GURUGRAM he shatl be lioble on demand to the ollottees' in cose the allottee wishes to withdtow from Lhe project' without prejudice to any other remedy ovoilable, to return the qmountreceived by him in respect of that opartment, ploL buitding, os the cqse may be, with iitere ith iiterest at such rote os may be prescribed in this behalf including compensotion in the monner os provided undet this Act: Provided thoLwhere qn allottee does not intend to with(lrctw from the projecL, he sholt be ptlid' by the promoter, interest for every month of delay, Lill the handing over oJ the possession' ot such roLe os moy be prescribed" ,,:;:i;;, 20.

As per clause 1 ofthe buyer's developer agreement talks about the possession ol' the unit to the complainants, the relevant portion is reproduce as under:- 7. 'l he Possessirtn of the ollotted unit shall be given to the Allottee/s by the company by luly 20L8. t!owever' this period can be extended Jbr o furthet groce period of 6 months " 21.

Due date of handing over of possession and admissibility of grace period: Asperclauselofthebuyerdeveloperagreemellt,thepossessionoftheallotted unit was supposed to be offered by the July 2018 with a grace period of 6(sixJ months.

Since in the present matter the buyer developer agreemcnt incorporates unqualified reason for grace period/extended period of 6 months in the possession clause accordingly, the grace period of 6 months is allowed to the promoter being unqualified.

Therefore, the due date of possession comes out to be January, 2019.

22.

Admissibility of refund along with prescribed rate of interest: Thc complainants are seeking refund the amount paid by them along with interest prescribed rate ofinterest.

The allottees intend to withdraw from the project aild are seeking refund of the amount paid by them in respect of the subiect unit with interest at prescribed rate as provided under rule 15 of the rules Rule 15 has been reproduced as under: Rule 75.

Prescribed rate of interest' lProviso to section 72, section 18 dnd sub-section (4) and subsection (7) of section 191 Pagez7 otz6 ffi HARERA #"eunuennlr (1) For the purpose of proviso Lo section 12; secLion 18; and sub'sections (4) . ions (4) .id (7) ofsection 19, the "interest ot the rate prescribed" shall be the Stote Bank of tndio highest marginal cost of lending rote +2ak : Provided thot in cose the State Bonk of lndia marginol cost of lending rote (MCLR) is not in use, it shall be replaced by such benchmark lending rates which the State Bonk of lndia moy fix from time to time for lending to the general Public.

23.

The legislature in its wisdom in the subordinate legislation under the provision of rule 15 of the rules, has determined the prescribed rate of interest.

The rate of interest so determined by the legislature, is reasonable and if the said rule is followed to award the interest, it will ensure uniform practice in all the cases' 24.Consequently,asperwebsiteofthestateBankoflndiaie',https://sbicoin'the marginal cost oflending rate [in short, MCI,R) as on date ie, 07'042025 ts 9.107o.

Accordingly, the prescribed rate of interest will be marginal cost ol' lending rate +20lo i.e., tL,tlo/o.

25.

The definition of term 'interest' as defined under section 2[za) of the Act provides that the rate of interest chargeable from the allottee by the promoter' in case of default, shall be equal to the rate of interest which the promoter shall be liable to pay the allottee, in case ofdefault.

The relevant section is reproduccd below: "(zo) "interest" meqns Lhe rotes of interest poyable by the promoter or the allottee, as the cose maY be. f:xplonotion. -l:or the purpose ofthis clquse- (i) the rote of interest chorgeoble from the allottee by thc promoLer' in cose of det'auh' sholl be equal to the rote of interest which the promoter sholl be liable to poy the olloLtee, in case ofdefqul' (ii) the interest poyable hy the promatet to the ollottee sholl be from the dote Lhe promoter received Lhe qmount or ony pdrL thereof Lill Lhe (lote the amount or part thereof (|nd interest thereon is relunded' and the interest poyoblc by the ollottee to the promoter sholl be from the date the allottee defoults in poymen in poyment to the pronoter till the date itis poidi' 26.

On consideration of the documents available on record and submissions made by both the parties regarding contravention of provisions of the Act' the Authority is satisfied that the respondent is in contravention of the section Complaint No.

5847 of 2022 and 2 others Page22 of26 Complaint No.

5847 of 2022 and 2 others 11(4)(a) of the Act by not handing over possession by the due date as per the agreement.

By virtue of clause 1 of the agreement executed between the parties on 27.01.20L6.

The due date ofpossession is July 2018.

As far as grace period is concerned the same is allowed for the reasons quoted above 'l'herefore, the duc date ofhanding over possession is January 2019 27. lt is pertinent to mention over here that even after a passage of more than 6 years neither the construction is complete nor the offer of possession of the allotted unit has been made to the allottee by the respondent/promoter' 'Ihe authority is of the view that the allottee cannot be expected to wait endlcssly for taking possession of the unit which is allotted to him and for which he has paid a considerable amount of money towards the sale consideration lt is also to mention that complainant has paid almost 87% of total consideration Further, thc authority observes that there is no document placed on record fronl which it can be ascertained that whether the respondent has applied for occupation certificate/part occupation certificate or what is the status of construction of the project. ln view of the above-mentioned facts, the allottee intends to withdraw from the proiect and are well within the right to do the same in view of section 1B(11 of the Act, 2016.

28.

Further, the Occupation Certificate/Completion Certificate of the project where the unit is situated has still not been obtained by the respondent/promoter' 'l'hc authority is of the view that the allottees cannot be expected to wait endlessly for taking possession of the a n of the allotted unit and for which he has paid a considerable amount towards the sale consideration and as observed by llon'ble Supreme Court of India in lreo Grace Realtech Pvt.

Vs' Abhishek Khonna & Ors., civil appeol no.

57BS of 2019, decided on 11,01.2027 "...-'l'he occupqtion cerLilicote is not ovailable even os on dote, which cleorly omounts Lo defciency of service '['he ollottees connoL be made to ffi HARERA #- eunuennu Page23 of 26 M HARERA ffieunuennnr Complaint No.

5847 of 2022 and 2 others wait indelinitely for possession ofthe apartments allotted to them, nor con they be bound to take the oportments in Phose 1 of the project.....,." 29.

Moreover, the Hon'ble Supreme Court of India in the cases o/ Newtech Promoters and Developers Private Limited Vs State of U.P. and Ors' (supro) reiterated in case of M/s Sana Realtors Private Limited & other Vs Union of India & others SLP (Civil) No.

73005 of 2020 decided on 12.05.20 2 2. observed as under: - "25.

The unquolifed right of the allottee to seek refund referred llnder Section 1B(1)(o) and Section 19(4) of the Act is not dependent on any contingencies or stipulations thereof. lt oppears thot the legislqture hos consciously provided this right of refund on demond as an unconditional absolute right to the ollottee, ifthe promotet foils to give possession of the qpartment, plot or building within the time stipuloLed under the terms of the ogreement regordless of unforeseen events or stoy orders of the Court/ftibunal, which is in either woy not otLributable to the olloLlee/home buyer, the prcnoter is under on obligation Lo relund the amount on demqnd wiLh interest dt the rale prescrihecl by Lhe SLate GovernmenL including compensaLion in the monner provided under the AcL with the proviso that if the allottee does not wish to withdraw from the project, he shall be entitled lor interestfor the period of delay till honding over possession qt the rote prescribed." 30. ibed." 30.

The promoter is responsible for all obligations, responsibilities, and functions under the provisions of the Act of 2016, or the rules and regulations made thereunder or to the allottees as per agreement for sale under section 11(4J(a).

The promoter has failed to complete or is unable to give possession of the unit in accordance with the terms ofagreement for sale or duly completed by the datc specified therein.

Accordingly, the promoter is liable to the allottees, as they wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of the unit with interest at such rate as may be prescribed.

31.

Accordingly, the non-compliance ofthe mandate contained in section 11[4)(a] read with section 1B(1) of the Act on the part of the respondent is established.

As such, the complainant is entitled to refund of the entire amount paid by them PaBe 24 of 26 H b Complaint No.

5847 of 2022 and 2 others at the prescribed rate of interest i.e., @ 11.10%o p.a. (the State Bank of India RA l?AM ABE URUG highest marginal cost of lending rate (MCLR) applicable as on date +2o/o) as prescribed under rule 15 of the Haryana Real Estate (Regulation and Development) llules, 2017 from the date of each payment till the actual date of refund of the amount within the timelines provided in rule 16 of the Haryana Rules 2017 ibid.

G.ll To direct the respondent to pay Rs.

32.

The complainant are seeking above mentioned relief w.r.t. litigation.

Hon'ble Supreme Court of tndia in civil appeal rcs.6745-6749 of 2021 titled as M/s Newtech Promoters and Developers Pvt.

V/s State of Up & Ors. [supraJ, has held that an allottee is entitled to claim compensation & litigation charges under sections 12,14,18 and section 19 which is to be decided by the adjudicating officer as per section 71 and the quantum of compensation & Iitigation expense shall be adjudged by the adiudicating officer having er having due regard to the factors mentioned in section 72.

The adiudicating officer has exclusive iurisdiction to deal with the complaints in respect of compensation & legal expenses H.

Directions of the Authority 33.

Hence, the Authority hereby passes this order and issue the following directions under section 3 7 of the Act to ensure compliance of obligations casted upon the promoter as per the functions entrusted to the authority under section 34(0 of the Act: i.

The respondent no.2 i.e., SARV ltealtors Pvt Ltd is directed to refund the amount received by it from each of the complainant[s) along with interest at the rate of 11.10% p.a. as prescribed under rule 15 of the Haryana Real Estate (Regulation and Development) Rules, 2077 from the date of each payment till the actual date ofrefund ofthe deposited amount.

Page25 of26 HARERA ffiGURUGRAM Complaint No.

5847 of 2022 and 2 others ii.

A period of 90 days is given to the respondent no.

2 to comply with the directions given in this order and failing which legal consequences would follow. iii. 'Ihe respondent no.

2 is further directed not to create any third-party rights against the subject unit before full realization of the paid-up amount along with interest thereon to the complainants, and even il any transfer is initiated with respect to subject unit, the receivable shall be first utilized for clearing dues of allottee/complainant. iv.

No directions are being passed in the matter qua respondent no.

1 in view of the moratorium imposed under section 14 of the IBC in NCLT case IB- 204/ND /2021titled Union Bank of India versus M/s Supertech Limited.

34.

This decision shall mutatis mutandis apply to cases mentioned in para 3 of this order wherein details of paid up amount is mentioned in each of the complaints.

35.

Complaint as well as applications, ifany, stands disposed ofaccordingly.

36.

Files be consigned to registry. ). gistry. ).t ->-2 (Viiay Kumar Goyal) Member (Arun Kumar) Chairman Real Estate Regulatory Authorify, Gurugram {-t' Haryana ok Dated: 2 5.03.202 5 Page 26 of 26