SHRI MOHAN LAL vs SUPERTECH LIMITED
Party Details
- SHRI MOHAN LAL
- SUPERTECH LIMITED
Case Summary
SHRI MOHAN LAL filed Case No. RERA-GRG-212-2019 in the Haryana Real Estate Regulatory Authority (RERA) against SUPERTECH LIMITED. The case has undergone 37 hearings over 6 years. The case is currently pending. 36 orders have been issued in this matter.
Hearing History (37)
- 27MAY 2025Hearing
Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN
Matter stands disposed of. Detailed order will follow.
Stage: DISPOSED
- 15APR 2025Hearing
Judge: ARUN KUMAR ASHOK SANGWAN
Matter to come up on 27.05.2025 for final arguments.
Stage: PENDING
- 21JAN 2025Hearing
Judge: ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN
The present complaint has been received on 29.01.2019. Reply on behalf of respondent not received yet. On 30.12.2024, the complainant filed an application for the restoration of the complaint, as the Authority had sine die adjourned the matter due to the insolvency proceedings involving certain projects developed by M/s Supertech, which included the project in question, i.e., Supertech Azalia. However, the specific project under the name "Azalia" is not included in the list of projects undergoing insolvency. The original allottee, Shri. Mohan Lal, passed away during the pendency of the complaint and consequently, the rights and duties of the original allottee are now vested in his legal heirs. The legal heirs have already applied for the death certificate of Sh. Mohan Lal and the “legal heir certificate”, and further seek the liberty from the Authority to file the same as and when they are received by them. The complainant has also filed an application on 01.01.2025 under Order 1 Rule 10 of C.P.C. for impleading DSC Estate Developers Limited as respondent in the present complaint was filed by the complainants against the respondent w,r.t the project located at "Supertech Azalia", Sector 2, Sohna, Gurugram, Haryana 722103. The restoration of the complaint is allowed and the counsel for the complainant seeks an adjournment to file the LRs certificate of the deceased complainant- allottee. Request is allowed. Matter to come up on 15.04.2025 for further proceedings.
Stage: PENDING
Orders (36)
- 27MAY 2025judgementView Order ↗
Order No: N/A
- 27MAY 2025orderView Order ↗
Order No: N/A
- 15APR 2025orderView Order ↗
Order No: N/A
Judgement DetailsView full order PDF ↗
,:J.i,-i, q.lH# ffitr 'lrlr .r*.Jllr.i \':;;J i-lARERr:r C;URUGRAM BEFORE THE 1.
Sh,.
Mohan Lal through LR's i.
Suniel Gautam ii.
Meena iii.
Mala Gautam Regdt.
Address: House No.
17 1228, Sector-7, Rohini, North West Delhi, New Delhi-110085 2.
Mr.
Ramesh Kumar Raheja Regdt.
Address: l{ouse No.
139, Huda Sector- 1'L, Panipat, H aryana- 1,321,03 Versus 1.
M/S Supertech Limited Regd. office: 11,4, l.1th floor, Hemkunt Ctrambers,89, Nehru Place, New Delhi-110019 2.
Mi/S Sarv Realtors Pvt.
Ltd Rr:gd. office: 1I4, 11th floor, Hemkunt Chambers, 89, Nehru Place, New Delhi-1 10019 COR,\M: Shri Arun Kumar Shri Vijay Kumar Goyal Shri Ashok Sangwan APPEARANCE: Sh. t{arshit Batra fAdvocate) Sh.
Ethrigu Dhami (Advocate) Sh.
Gaurav Raghav (Advocate) HARYANA REAL ESTATE REGULATORY AUTTIORITY, GURUGRAM Complaint no.
Date of filing: Date of decision 212 of 2Ot9 29.L0.20t9 27.05.2025 Complainants Respondents Chairman Member Member Complainants Respondent no.
1 R.espondent no.
2 ORDER 1. 'l'hat the present complaint has been filed by the complainant/allottees under semion 31 of the Real Estate (Regulation and Development) Act, 2016 Complaint No.
212 ctl'201.9 Page 1 of27 HARER,q GURUGRAM Complaint No.212 of 2019 A.
2. (hereinafter referred as "the Act") read with rule 2B of the Haryana Real Estate (Regutation and Development) R"ule s,2017 (hereinafter referred as "the rules") for vic,lation of section 11,(4)[a) of the Act wherein it is inter alia prescribed that the promoter shall be responsible for all its obligations, responsibilities and functions to the allottees as per the agreement for sale executed inter se parties.
Proiect and unit related details The particulars of the project, the details of sale consideration, the amount paid by the complainants, date of proposed handing over the possession, delay period, if any, have been detailed in the following tabular form: S.
No.
Particulars Details Name of the project Supertech Hues, Sector-68, Gurugram 1221,01 1.
Project area 55. t area 55.5294 acres 2.
Nature of proiect Group Housing ColonY 3.
RERA registered/not registered Registered vide registration no.
1,82 of 201 dated 04.09.201,7 Validity Status 31..12.2021.
4.
DTPC License no.
1_06&1-07 gwt2:?01.3 25.1.2.2017 Validity status Name of licensee Sarv Realtors Pvt.
Ltd. & Ors.
5.
Unit no.
F 1004, 10th floor, Tower V fPase no.
35 of comPlaint) 6.
Unit measuring 1430 sq. ft. super area fPage no.
35 of complaintl -- 7.
Date of Booking 13.10.2013 fPaee no.35 of comPlaint B.
Date of execution of Buyer developer agreement 19.06.20t4 fPage 34 of comPlaint) 9.
Possession clause POSSESSION OF UNIT: ' L Thepossession of the allotted unit sholl be giver to the allottee /s by the company by April 2017 However, this period can be extended for c further grace period of 6 months. fPaee 37 of the comPlaint) l -l -l 1l l l -l I-l l -l lnl 7, I :l Page 2 of 27 ffiHAI]EILA ffiEUNUGRAM complaint No.
212 of 20t9 10.
Due date of possession April 2017 + 6 months = October 2017 1,1,.
Total sale consideration Rs.
1,06,27 ,240 /- (page 36 of complaint) 12.
Total amount paid by the complainants Rs.
28,00,000/- approx.
Paid bY th complainants.
Rs.
48,00,000/- approx. disbursed by th bank.
13, O ccupation certificate Not obtained 14.
Offer of possession Not offered 15, Tripartite agreement 28.07.201,6 e l -J Facts of the complaint The complainants have made the following submissions in the complaint: - a. 'fhat the complainants were allured by the tall claims of the promoter/ developer for world class infrastructure and timely possession of the flat. 'the advertisement and the brochure were shown on the offici,al website. lFacilities like clubhouse and other amenities were shown as an added :advantage to the project, to be booked by the customers. b. 'Ihat the promoter issued an advertisement in newspaper,/electronic media/e-mail and other media inviting the applications for the purpose of flat in the real estate project located in Gurgaon, in the project, in thc pro in thc project named "supertech Hues" at Sector 68, Gurugram, Haryana. c.
That the complainants are a retired government official and from his hard earned savings booked the flat for his son and paid an amount of Rs.
6lacs on L2.10.2Ot3.The respondent, thereafter, prepared the buyers agreement on 19.06 .201,4 i.e. after B months of receiving booking amount. d.
That the complainants were assured that the possession of the unit shall bc given by April, 2017 and the grace period of 6 months shall be given and by gctober, 2017, the possession shall be handed over. 'the clause 24 of thc buyer's agreement is crystal clear giving the date of possession.
I B.
3.
Page 3 of27 ffiHARERFT #" cllRuen[rrl Complaint No.
2L2 of 2019 T'hat the complainants entered the buyer's agreement and opted for tower y and unit no.
1004 was allotted as per complainants' preference looking at the site map and preference location.
The net basic price of the unit was F1s.92,49,240/- and over and above, preference location charges were to be praid, club membership, development charges, electricity installment charges, IFMS charges, parking, power backup and the total anrount was calculated at Rs.1,06,27 ,240/-.
The service tax would have been extra. 'l'he Jlayment plan was construction Iink plan which clear from agreement itself. 'fhat the complainants paid the amount without any delay and honoured the covenants of the agreement and continued to pay as per the construction link plan. '[hat the respondent wrote an e-mail dated 13.06.2016, wherein, the developers promoted a subvention scheme and construction updated was :;hown as on 08.06.2016 that the entire superstructure was complete in pictures. 'Ihat the respondent in order to fool the gullible consumer, introduced a rsubvention scheme, wherein, no EMI will be paid by the consurner till thc possession at no extra cost and the construction update was shown to be that the project is structurally complete. complete.
The complainants got allured with the lucrative offer and entered into a tripartite agreement on '28.07.2016 between the respondent and the complainants and India Bulls Housing Finance Limited and sanctioned a loan of Rs,70 lacs was approved by thc India Bulls Housing Finance Limited and disbursal was of Rs.48lacs approx.
As per conditions, the total loaned/disbursal amount interest would bc paid to the respondent and the respondent shall assume the liability on account of interest payable by complainants to the IHFL during the period referred as liability period.
The subvention period started from August, Page 4 of27 ob' ffiHARERA ffi.
GURUoRAM Complaint No.
212 of 2019 2:.01,6 to February,201,9 (30 months) and the scheme was in February, 2:,019 meaning thereby, the builder has taken 7 5o/o of the total value of thc tunit booked by the complainants. llhat there were many occasions in between the respondent failed to make payment to the IHFL and the recovery agent used to visit home of the complainants and it was an embarrassing situation where the things werc to be clarified that who is liable to pay the amount of EML The respondent is in habit to delaying and defaulting the EMIs. '[hat the subvention shall be over in February,201,9 and the project is already delayed, where the possession was to be handed over after the grace period by |anuary,2O1B and the tower booked by the complainants lor the specific purpose being preferred location looking at the both sidc greener area closer to shopping centre and club house and away from the :road but however, the present situation of the tower is that there is no :structure even standing.
Only the ground level construction is done.'l'here is no likelihood that the project shall be completed within a year and it has already by a year.
The purpose of buying the premises has failed now and complainants wants to withdraw the entire amount deposited by him along with interest. j. terest. j.
That the booking was done with the respondent on 13.10.201-3, when it was not even capacity to take the booking amount and advertised the said project which was in violation to the town and country planning notification but they continued to cheat the complainants by taking the booking amount without having any legal sanctity to accept the booking amount which is in violation of rules and regulations of the town and country planning and complainants have been cheated with the fraudulent act of the respondent company, h. i.
Page 5 of27 UABEB& ffi,GURUGI?AM k.
T'hat the respondent had taken the entire amount and has failed to h.andover the possession in a stipulated time period as specified in thc Lruyer's agreement.
The complainants are left with no option but to seek the refund of the total amount. l.
I'hat the complainants cannot wait indefinite for seeking the possession of the unit booked by him and the entire transaction was in a fraudulent manner as the respondent were not in a capacity to even ilccept the booking amount.
Therefore, the respondent has no right to defend l.hemselves as fraud vitiates everything' m.'fhat the buyer's agreement however does not specify anywhere that in 6ase of failure to deliver the timely possession of the unit, the buyer has the right to seek refund of the entire amount without any forfe:iture' 'l'he promoter has nowhere mentioned any remedial measures to tle taken in case of deficiency or failure of service. 'Iherefore, this agreement is totally unfair and one sided as per section 18 Act 201'6.
Hence, the buyer's agreement violates this, law.
The promoter has accepted that the project has to abide by RI]RA, but there is no evidence of his compliance on this matter even after of RERA enforcement in Haryana' n.
That the agreement clearly mentions about the proportion o1'IISP to bc paid as per construction linked plan floor wise construction and other charges like club house, school, PLC, covered car parking etc' which w c' which was to be paid at the time of offer of possession but the respondents dc=ducted thc same from the deposited amount of the complainants as per construction linked plan and further on seeking explanation, it was informed that the portion of amount was adjusted in other facilities like club house, school, PLC, covered car parking for the project as assured by the developers'l'he respondent/builder adjusting the deposited amount in a secretive manner complaint No.
212 of 20L9 Page 6 of27 ffiHARERA #" ouRUGRAM Complaint No.21"2 of 2019 and even as per payment demand Ietters there is no mention of the sanle.
Crn the contrary there is no development/construction of clubhousc, schools etc. for the amount deposited by the complainants.
Thc photographs are attached for ready reference and the E-mail is attached the manner in which amount stands deducted by the developer.
The hruilder did not disclose this break-up from day one as evident from clemand letters and the agreement is even silent about the same.'[hus, thc cteveloper has acted in malafide intension and has violated the RERA Act zrnd its Rules. o. lihat the buyer's agreement is unjustifiable and in violation to business ethics.
It nowhere states anything about failure of services by the promoter, in case they fail to hand over the possession they shall continue to pay compensation for delayed period but the allottee cannot walk out of the project, Therefore, the buyer's agreement is totally one sided protecting the rights of the developers ancl in violation to RERA.
Thus, this Act has :naturally caused a huge fihancial loss and mental stress to me and my family The promoter/developer is liable to pay interest to the allottees as per Rule 15 of Rules ZOl7, as admittedly the developer has failed to givc the possession of the flat booked by the complainants as per terms and condition.
The promoter further failed to comply with the REIIA Act and Haryana RERA rules. p. rules. p.
That the buyer's agreement also has an unfair clause, which states that any delay in paying installment to promoter would lead to 2o/o per month compensation to the promoter, and implies that this is irrespective of any long delay by the promoter to deliver flats.
The complainants have already paid 85% of the total basic cost as per the constructions linke:d payment plan and there was no delay in the installments.
The project is nowhcrc PageT of27 complaint No.
212 of 20L9 nrear completion even after the booking of the flat, it's been more Lhan 41/z y'ears and the time to hand over the flat as per the buyer's agreement is clver.
Hence, the complainants shall be given back the hard-earned money aLlong with interest, compensation and damages q. l'hat the complainants sent the legal notice to the respondents for refund of the deposited amount as they failed to timely deliver possession of the flat as per buyers agreement. the the C.
Reliet'sought by the complainants: - 4.
D.
5. ffiHARERA ffieuntlcRm The complainants have sought following relief(s): I.
D,irect the respondent to refund the amount paid by the complainants along radth prescribed rate of interest from the date of respective deposits till its actual realisation, in accordance with the provisions of the act.
0n the date of hearing, the authority explained to the respondent,/promoter about the contraventiorls as alleged to have been committed in relation to section 11(4) [a) of the act to plead guilty or not to plead guilty.
Reply'by the respondent no.
1 The rr:spondent is contesting the complaint on the following grounds:- a. '['hat the project "supertech Hues" is registered under the Hanyana Real Elstate Regulatory Authority vide registration certificate no. lf:12 of 201,7 clated 4.9.201,7.
The Authority had issued the said certificate which is valid for a period commencing from 04.09.2017 to 31.12.2021.
1.12.2021.
Thus, in view ol' the said registration certificate, the respondent hereby undertakes to complete the said project on or before the year 202L. b. llhat the possession of the said premises is proposed to be delivered by the respondent to the apartment by April, 2017 with an extended grace period of 6 months which comes to by October 201,7.
The completion of the building is delayed by reason of non-availability of steel and/or cement or other building materials and/ or water supply or electric power andf ot" Page B of27 ffiHARERA ffi, eunliGRAM Complaint No.
212 of 20t9 s|:w down strike etc. which is beyond the control of respondent and if non- delivery of possession is as a result of any act and in the aforesaid events, the respondent shall be entitled to a reasonable extension of' time for delivery of possession of the said premises as per terms of the agreement e>lecuted by the complainants and respondent.
The respondent and its olficials are trying to complete the said project as soon as possible and therc is no malafide intention of the respondent to get the delivery of project, dr:layed, to the allottees.
It is also pertinent to mention here that due to orders passed by the Environment Pollution (Prevention & Control) Authority, the construction was / has been stopped for few days due to high rise in Pollution in Delhi NCR.
That due to stagnation, sluggishness, down fall in real estate market, due to demonetisation as well as coming into force of GST, the speed of work/ construction of every real estate sector market has been too slump which r3sults in delay of delivery of possession.
The plea of allotees in all the complaints for refund is not tenable in the eye of law.
Thus, duc to ipsufficient monetary fund as well as huge down fall in the Real Estate market, all the Allottees have planned to seek refund of the invested money. ted money. l'hat the enactment of RERA Act is to provide housing facilities with modern i[evelopment infrastructure and amenities to the allottees and to protect thc interest of allottees in the real sector market.
Thus, the plea/ relief of refund claimed by every allottee is not sustainable in the eye of law rather is a pre-planned to get refund their money to get safe from breach of contract in future fbr making further instalments, by filing such frivolous complaints. 'lhat the respondent also undertakes to complete the project by the year Decembe r 202i. but will give offer of possession to the complainants' 'l'he C. d. e.
Page 9 of27 ffiHARERA ffieunucRAM rerspondent also submit that if the complainants want an early possession, thLe complainants may be given an alternative inventory/ uttit available either in project Araville which is completed or in the Project [lues 'frlwef- A, B, E, F, where date of possession is f une 2020 as per convenience ol'the complainants.
That when the parties have contracted and limited their liabilities, they are bound by the same, and relief beyond the same could not be granted. g.
That the complainants are not entitled for any compensation claimed except for compensation for delayed possession as per clause 2 of the builder buyer agreement Reply by the respondent no.
2 The respondent no.2 implead as partyvide order dated 27.05.2025 is contesting the complaint on the following grounds:- a.
That respondent was issued license bearing no's 106 and 107 dated 26.12.2013 and license no's.
135 and 136 of 2014 dated 26.08.201,4 for developing the said land.
In furtherance of the same, the respcrndent and respondent no.
1, i.e.
M/s.
Supertech Ltd. had entered into two foint Development Agreement's dated 25.04.2014 and dated 26.08.201.4 respectively.
In terms of the said IDA's the respondent no.
2 was to develop and market the said Project.
That the complainants along with many other allottees had approachecl the respondent no. ondent no.
1, making enquiries about the proiect, and after thorough ctue diligence and complete information being provided to them had sought to book an apartment in the said project.
Consequentially, after fully understanding the various contractual stipulations and payment plans for the said apartment, the complainants executed the buyer developer agreement dated L9.06.20L4 only with 111 complaint No.
212 of 2019 E.
6. b. c.
Page l0 of 27 HARERE W* GURUGI?AM for an apartment being number no.Y / 1004, 1Oth floor, having a super area of 1430 sq. ft. (approx.J for a total consideration of Rs.
1.,06,27,240 /-.
That in the interim with the implementation of the Act,2016 the project was registered with the Hon'ble I{aryana Real Estate Regulatory Authority, Panchkula vide Registration no. "!82 of 2017", dated 04.09.2017 upon Aapplication filed and in the name of R1.
That the Authority vide order dated 29.11.201"9 passed in Suo Moto complaint no.
5802/ 201,9, had passed certain directions with respect to the transfer of assets and liabilities in the said projects namely, "Hues & Azalia", to the answering Respondent (M/s SARV Realtors Pvt.) Ltd. and M/s.
DSC Estate Developer Pvt.
Ltd. respectively.
The Authority had further directed that M/s.
Sarv Realtors Pvt.
Ltd. and M/s.
Ltd. be brought on as the promoter in the project instead of M/s.
Supertech l.td. certain important directions as passed by the Authority are as under: . (i) The registration of the project "Hues" and " Azalia" be rectified and SARV Realtors Pvt.
Ltd./DSC and others, as the case may be, be registered as promoters . . [v) All the assets and liabilities including customer receipts and project loans of whatsoever nature, the project LIUES and AZALIA, in the name of Supertech Ltd. be shifted to Sarv Realtors Pvt. [,td/ DSC and others.
However, even after the rectification, Superech Ltd. erech Ltd. will continue to remain jointly responsible for the units marketed and sold by it and shall be severally responsible if SARV Realtors Pvt.
Ltd./DSC and others fail to discharge its obligations towards thc allottees.
Complaint No.
212 of 2019 d. e, Pagellof27 ffiHARERU S*GURuennM Complaint No.
212 of 2019 In lieu of the said directions passed by this l{on'ble Authority all asset and liabilities have been since transferred in the name of the Answering respondent company.
However, in terms of the said Order, M/s' Supertech Ltd. still remains jointly and severally liable towards the booking/ allotment undertaken by it before the passing of the said Suo Moto Order' 'that thereafter the said JDA'S were cancelled by the consent of both parties vide cancellation agreement dated 03.10.2019 and the answering respondent from there on took responsibly to develop the project and started marketing and allotting new units under its name. 'Ihat in terms of the said cancellation agreement the respondent and I11 had agreed that as R1 was not able to complete and develop the project as per the timeline given by the Authority and DTCP, therefore the parties had decided to cancel the f DA's vide the said cancellation agreement' h.
In the interregnum, the pandemic of Covid L9 has gripped the entire nation since March of 2020.
The Government of India has itself categ,orized the said event as a'Force Majeure' condition, which automatically extends thc timeline of handing over possession of the apartment to the complainants' That the possession date was much before the passing of the Suo Moto 0rder, further the alleged MoU or loan documents have been executed between the complainants and R1 and R2 only and the party has no privity of contract with either of the parties qua the subject unit.
The respondent cannot be burdened with any liability w.r.t to any Pre-Emi's or any liability arising out of any contract which it was admittedly not privy to' ,. ivy to' ,.
That the construction of the project is in full swing, and the delay if at all' has been due to the government-imposed lockdowns which stalled any sort of construction activitY.
Page 12 of27 HARER$, ffi.
GUI?UGRAM k.
That the present Complaint deems to be dismissed sine-die or dismissed as the R1 company, i.e.
Supertech Ltd. is undergoing Corporate Insolvency resolution Process and therefore all matters like the present one in which Supertech Ltd. is a party deem to be adjourned sine-die or dismissed in lieu of the moratorium imposed upon M/s.Supertech Ltd.
U/s 1,4 of the IBC, 20L6. l.
That even the application seeking impleadment had been wrongly allowed, as once the sole respondent, M/s.
Supertech Ltd. was undergoing insolvency proceedings since 25.03.2022, thus, no proceedings in thc present matter could have continued after the said date.
However, the Authority has wrongly allowed the said application in contravention of the provisions of section L4 IBC, 201.6. m.
The present case deems to be prima facie dismissed as there is no privity of contract between the complainants and the respondent.
Furthermore, despite filing its application for change in promoter, the same has not been allowed till date and the same is still pending adjudication beforc thc Authority.
Thus, no case can proceed against the respondent till the final decision of the said application. n.
The present case is bad for non-joinder of necessary parties as the bank, HDFC limited has not been made a party despite the execution of the tri- partite agreement, wherein the complainants have subrogated his entire right for refund in favor of the Bank. o.
That the present case also deems to be prima facie dismissed as admittedly the BBA was executed solely with M/s Supertech Ltd., all salc consideration was also paid to M/s. id to M/s.
Supertech Ltd,, thus as no salc consideration as paid to the respondent neither any written agreement was signed between the complainants and respondent, the respondent Complaint No.212 of 2019 Page 13 of27 ffiHARERA ffisunuen-nm reiterated that M/s.
Supertech Ltd is jointly liable as per the Suo Moto order.
The present case also deems to be dismissed against the respondent as there is no pleading in the main complaint against the respondent, neither any relief is sought from the respondent.
It is established law that the court cannot grant relief which is over and above the relief claimed by the complainants in his complaint.
That as M/s.
Supertech Ltd. and the respondent are jointly and severally liable in terms of the Suo Moto 0rder passed by Authority for the project in question, thus the present matter catrnot proceed further until the said liability qua the allotees is not bifurcated between both the respondent's.
The respondent in lieu of the CIRP proceedings ongoing against lll company, cannot be made wholly liable for allotments undertaken and monies/sale consideration received by M/s.
Supertech Ltd. r.
That the complaint filed by the complainants are not maintainable in the present form and is filed on the false and frivolous grounds.
The bare reading of the complaint does not disclose any cause of action in favour of the complainants and the present complaint has been filed with malafide intention to blackmail the respondent with this frivolous complaint.
That the delay if at all, has been beyond the control of the respondent and as such extraneous circumstances would be categorised as'force majeure', and would extend the timeline of handing over the possession of the ttnit, and completion the project.
That the delay in construction was on account of reasons that cannot be attributed to the respondent.
The buyer's agreements provide that in casc the developer/respondent delays in delivery of unit for reasons not complaint No. plaint No.
212 of 2019 cannot be ordered to refund any amounts, if any, by the Authority.
It is p. q.
S.
Page 14 of27 ffiHARERE ffi- GURUGRAM attributable to the developer/respondent, then the developer/ respondent shall be entitled to proportionate extension of' time for completion of said project.
The relevant clause, i.e. "clause 43 under thc heading "General terms and conditions" of the "agreement".
The respondent seeks to rely on the relevant clauses of the agreement at thc time of arguments in this regard.
In view of the forece majeure clause, it is clear that the occurrence of delay in case of delay beyond the control of the respondent, including but not limited to the dispute with the construction agencies emplolrefl by thc respondent, Covid - 19, shortage of labour, shortage of raw materials, stoppage of works due to court orders, etc. for completion of the project is not a delay on account of the respondent for completion of the project.
That with respect to the present agreement, the time stipulated for delivering the possession of the unit was on or before fune, 201,9.
However, the buyers' agreement duly provides for extension period of 6 months over and above the said date.
Thus, the possession in strict terms of the buyer's agreement was to be handed over in and around December, 20Ig.However, the said date was subject to the force majeure clause, i.c. "Clause 43". w.
That despite the best efforts of the respondent to handover timely possession of the residential unit booked by the complainants, the respondent could not do so due to certain limitations, reasotrs and circumstances beyond the control of the respondent.
Apart from thc defaults on the part of the allottees, like the complainants herein, the delay in completion of project was on account of the following reasons/circumstances like: complaint No,212 of 20t9 u.
V.
Page 15 of27 ffiHARERA #-GURUGRAM Complaint No. plaint No.212 of 2019 r Implementation of social schemes like National Rural Employment Guarantee Act ["NREGA") and fawaharlal Nehru National ljrban Renewal Mission ("JNNURM"), there was a significant shortage of labour/workforce in the real estate market as the available labour had to return to their respective states due to guaranteed employment by the central/State Government under NREGA and JNNURM schemes.
This created a further shortage of labour force in the NCR region.
Large numbers of real estate projects, including that of the respondent herein, fellbehind on their construction schedules for this reason amongst others.
The said fact can be substantiated by newspaper articles elaborating on the above mentioned issue of shortage of labour wnicrr was hampering the construction projects in the NCR region.
This certainly was an unforeseen one that could neither have been anticipated nor prepared for by the respondent while scheduling their construction activities. o That such acute shortage of labour, water and other ravv materials or the additional permits, licenses, sanctions by different departments were not in control of the respondent and were not at all foreseeable at the time of launching of the project and commencement of construction of the complex.
The respondcnt cannot be held solely responsible for things that are not in control of the respondent.
That the intention of the force majeure clause is to save the performing party from the consequences of anything over which he has no control' It is no more res integra that force majeure is intended to include risks beyond the reasonable control of a party, incurred not as a product or result of the negligence or malfeasance of a party, which have a materially Page 16 of 27 HARER& ffi" GURUGRAM adverse effect on the ability of such party to perform its obligations, as of external forces or Where the intervening circumstances are specifically contemplated. templated.
Thus, in light of the aforementioned it is most respectfully submitted that the delay in construction, if any, is attributable to reasons beyond the control ofthe respondent and as such the respondent ntay be granted reasonable extension in terms of the allotment letter. l'hat the project "HUES" is registered under the Haryana Real Estatc t{egulatory Authority vide registration certificate no.
IBZ of 2017 dated 4.9.2017.
The Authority had issued the said certificate which is valid for a period commencing from 04.09.20t7 to 31'.1,2.2021.
Ithat the possession of the said premises under the said BtlA was proposed to be delivered by the respondent to the apartment allottee by June, 201,9 with an extended grace period of 6 months which comes to an end by December,2019.
The completion of the building is delayed by reason of Covid-19 outbreak, non-availability of steel and/or cement or other building materials and/or water supply or electric power an<ll or slow rlown strike as well as insufficiency of labour force which is beyond the r:ontrol of respondent. c. 'Ihat the enactment of the Act, 2016 is to provide housing facilities with modern development infrastructure and amenities to the allottees and to protect the interest of allottees in the real estate sector market. 'f he main intention of the respondent is just to complete the project within stipulated time submitted before the Authority.
According to the terms of builder buyer's agreement also it is mentioned that all the amount of delay possession will be completely paid/ adjusted to the complainants at thc time final settlement on slab of offer of possession. complaint No.
212 of 20t9 where non-performance is caused by the usual and natural consequences b.
Page1^T of27 ffiHARER& ffi.
GURUGRAM Further, compounding all these extraneous considerations, the llon'ble Supreme Court vide order dated 04.11.201,9, imposed a blanket stay on all construction activity in the Delhi- NCR region.
CR region.
It would be apposite to note that the 'Hues' project of the respondent was under the ambit of the stay order, and accordingly, there was next to no construction activity for a considerable period.
It is pertinent to note that similar stay Orders have been passed during winter period in the preceding years as well, i.e.2017 - il01B and 2018-2019.
It is most respectfully submitted that a complete ban on construction activity at site invariably results in a long-term halt in construction activities.
As with a complete ban the concerned Labor is let off and the saicl travel to their native villages or look for work in othcr :;tates, the resumption of work at site becomes a slow process and a steady llace of construction in realized after long period of time' 'fhat, graded response action plan targeting key sources of pollution has been implemented during the winters of 201,7-18 and 2018-19, 'l'hese short-term measures during smog episodes include shutting down powcr plant, industrial units, ban on construction, ban on brick kilns, action on waste burning ancl construction, mechanized cleaning of road dust, etc' This also includes limited application of odd and even scheme. 'fhe table concluding the time period for which the construction activities i1 the Project was restrained by the orders of competent Authority/Court are produced herein below as follows.
The table concluding the time periocl for which the construction activities in the Project was restrained by the orders of competent Authority/Court are produced herein below as follows: complainr No.
212 of 2019 d. v.
Page 18 of27 HARER,q Complaint No.
212 of 2019 C;URUGRAM F.
Findings 1.
National Green Tribunal- 08.11.2016 1.0.11.201.6 Vardhman Kaushik vs Union of India 08.
1 1.20 1 6 to 16.L1,.201.6 2.
National Green Tribunal 09.11.2017 Vardhman Kaushik vs Union of India Ban was lifted after 10 days 3.
Press Note by EPCA- Environment Pollution IPrevention and Control) Authority Press Note- 31.10.2018 01.
0.2018 01.11.2018 to 10.1 1.2018 4.
Supreme Court-23.12.20 1B Three-day ban on industrial activities in pollution hotspots and construction work 23.12.20 tB to 2 6,12.20 I I 5.
EPCA/ Bhure lal Committee 0rder- 31,10.2 018 Complete Ban 01.1 1.2019 to 05.1 1.2019 6.
Hon'ble Supreme Court 0 4.1 r.20 1 9 - 1.
4.02.2020 M.C Mehta v.
Union of India Writ Petition (c) no.
13029 1t985 04.11.201.9 to 14.02.2020 7.
Gove:rnment of India l Lockdown due to Covid- L9 24.03.2020 to 03.05.2020 8.
Govtlrnrnent of lndia Lockdown due to Covid- 19 8 nr,eeks in 2021 Total 37 weeks [approximately) on obj raised by the respondent no.
1 F.l Obiections regarding force maieure.
7.
The respondent-promoter alleged that grace period on account of force majeure conditions be allowed to it.
It raised the contention that the construction of the project was delayed due to force majeure conditions such as demonetization, and the orders of the Hon'ble NGT prohibiting construction in and around Delhi and the Covid-19, pandemic among others, but all the pleas advanced in this regard are devoid of merit.
The flat buyer's agreement was Page 19 of27 l I ffiHARER* ffi.GURUGRRrr,I Complaint No.212 of 20L9 executed between the parties on 19.06.2014 and as per terms and conditions of the said agreement the due date of handing over of possession comes out to be Octob er, 2017, which was prior to the effect of Covid-19 on abo'n'e project could happen.
The Authority put reliance judgment of Hon'ble Delhi High Court in case titled as M/s Halliburton Offshore Services Inc.
V/S Vedanta Ltd, & Anr, ,bearing no.
O.M.P (I) (Comm.) no.
SB/ 2020 and LAs 3696-3697/2020 dated 29.05.2020 which has observed that; ti9.
The past non-performance of the Contractor cannot be condoned due to the C0VID-19 lockdown in March 2020 in lndia.
The Contractor was in breach since iieptember 2019.
7pportunities were given to the Contractor to cure the same repeatedly. epeatedly.
Despite the same, the Contractor could not complete the Proiect' The outbreak of a pondemic cannot be used as an excuse for non- performance of a contract for which the deadlines were much before the outbreak itself." B.
But all the pleas advanced in this regard are devoid of merit.
Therefore, it is nothing but obvious that the project of the respondent was already delayed, and no extension can be given to the respondent in this regard.
The events taking place such as restriction on construction were for a shorter period of time and are y.early one and do not impact on the project being developed by the resp6ndent, Though some allottee may not be regular in paying the arnount duc but the interest of all the stakeholders concerned with the said project cannot be put on hold due to fault 9f some of the allottees.
Moreover, the respondent pronroter has already been given 6 months grace period being unqualified to take case of unforeseen eventualities.
Therefore, no further grace period is warranted in account of Covid-19.
Thus, the promoter/respondent cannot be given any leniency based on aforesaid reasons and the plea advanced in this regard is untenable.
F.ll Obiection regarding CIRP against respondent no.
1 and consequent moratorium against proceedings against respondent no.1. g.
During the course of hearing the respondent no. t has stated that vide dated 25.03.2022 passed by the Hon'ble NCLT, New Delhi Bench in case order titled Page 20 of27 ffiHARERE ffi eunuGRAM Complaint No.21.2 of 201,9 as Union Bank of Indla Versus M/s Supertech Limited, the Hon'ble NCLT has initiated CIRP respondent no.1 and impose moratorium under section 14 of the LtsC,2016.
The Authority observes that the project of respondent no.
2 is no longer the assets of respondent no. l" and admittedly, respondent no.2 has taken over all assets and liabilities of the project in question in compliance of the direction passed by this Authority vide detailed order dated 29.11. ted 29.11.20L9 in Suo- Moto complaint.
HARERA /GGNI/ 5502/2OL9.
Respondent no.1 has stated in the reply that the MDA was cancelled by consent of respondent no.L and respondent no.Z vide cancellation agreement dated 03.10.2019. 'l'hereon, respondent no.2 i.e., SARV Realtors Pvt.
Ltd. admittedly took responsibility to devel,rp the project and started marketing and allotting new units under its name, In view of the above, respondent no.1 remains squarely responsible for the performance of the obligations of promoter in the present matter.
So far as the issue of moratorium is concerned, the projects Hues & Azalia stand excluded from the CIRP in terms of affidavit dated 1,9.0+.2024 filed by SFL Hitesh Goel, IRP for M/s Supertech Limited.
However, it has been clarified that the corporate debtc,r i.e., respondent no.2 remains under moratorium.
Therefore, evcn thouE;h the Authority had held in the Suo-Moto proceedings dated 2'9.11..2019 that respondent no.
1 & 2 were jointly and severally liable for the prro;ect, no orders can be passed against respondent no.L in the matter at this stage.
Findings on the relief sought by the complainants.
G.l Direct the respondent to refund the entire deposited amount of the complainants, arnounting to Rs.76,00,000/- with an interest in accordance with Section 1B of the Real Estate Regulation Act, 2Ot6 as thc Respondent is in violation of Clause 1 of Possession of the said Unit of the Buyer Agreement dated L9.06.20L4 and also the respondent has cheated/ defrauded the complainants; On 21.01.2025, the counsel for the complainant informed that the original allottee, Sh.
Mohal Lal, had passed away during the pendency of the complaint.
Cons,equently, the rights and obligations of the original allottee have devolved I'age21 <t'27 G.
10.
11..
HARTR&, Complaint No.
212 of 2019 ffi- C)URUGI?AM upon his legal heirs.
The counsel also sought liberty to file the legal heir certificate and an amended memo of parties, which was subsequently filed on 1,5. ed on 1,5.04.2025.
In the present complaint, the complainants intend to withdraw from the project and is seeking return of the amount paid by her in respect of subject unit along with interest.
Sec.
1B(1) of the Act is reproduced below for ready reference :- " Section 78: - Return of amount ond compensation 1B(1).
If the promoter fails to complete or is unable to give possession of an apartment, plot, or building. - (a) in accordance with the terms of the agreement for sole or, as the case moy be, duly completed by the date specified therein; or (b)due to discontinuance of his business qs a developer on account of suspension or revocation of the registration under this Act or for any other reason, he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without preiudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rote as may be prescribed in this behalf including compensation in the manner as provided under this Act: Provided that where an allottee does not intend to withdraw from the project, he shall be paid, by the promoter, interest for every month of delay, till the handing over of the possessron , at suc:h rate as may be prescribed." (Emphasis supplied) As per clause 1 of the buyer's developer agreement talks about the possession oI the unit to the complainants, the relevant portion is reproduce as Llnder:- ?OSSESSION OF UNIT: - L.
The possession of the unit shall be given to the buyer in 42 months i.e. by April 2017.
However, this period can be extended due to u.nforeseen circum_stances for o further grace period of 6 months [Emphasis Supplied] 13.
Due rlate of handing over of possession and admissibility of grace period: As per clause L of the buyer developer agreement, the possession of the allotted unit vvas supposed to be offered by the April, 2017 with a grace period of 6(six) months. x) months.
Since in the present matter the BBA incorporates unqualified reason for 1,2.
Page22 of27 1,4. ffiHARERA ffi,eunuennHr complaint No.
212 of 201.9 grace period/extended period of 6 months in the possession clause accordingly, the grace period of 6 months is allowed to the promoter being unqualified.
Therefore, the due date of possession comes out to be October, 2017 .
Admissibility of refund along with prescribed rate of interest: 'l'he complainants are seeking refund the amount paid by them along with interest prescribed rate of interest.
The allottee intend to withdraw from the project ancl are seeking refund of the amount paid by them in respect of the subject unit with interest at prescribed rate as provided under rule 15 of the rules.
Rule 1"5 has been reproduced as under: Rule 15.
Prescribed rate of interest- [Proviso to section 72, section 78 and sub-section (4) and subsection (7) of section 191 (1) F-or the purpose of proviso to section 12; section 1B; and sub-sections ft) and (7) of section 19, the "interest ot the rate prescribed" shall be the State Bank of lndia highest marginal cost of lending rate +20/0.: Provided that in case the State Bank of lndia marginal cost of lending rate (MCLR) is not in use, it,shall be replaced by such benchmark lending rates which the State Bank of India may fix from time to time for lending to the general public.
The lergislature in its wisdom in the subordinate legislation under ther provision of rule 15 of the rules, has determined the prescribed rate of interest.'Ihe rate ol' interest so determined by the legislature, is reasonable and if the said rule is follorn,ed to award the interest, it will ensure uniform practice in all the cases.
Consequently, as per website of the State Bank of India i.e., httpS://,sbi."e,p*Jn, thc marginal cost of lending rate [in short, MCLR) as on date i.e., 27.t)5.2025 is 9.LDo,/o.
Accordingly, the prescribed rate of interest will be marginal cost o1' lending rate +20/o i.e., 1L. i.e., 1L.LOo/o.
The clefinition of term 'interest' as defined under section Z(za) of the Act provirles that the rate ol'interest chargeable from the allottee by the promotcr, in case of default, shall be equal to the rate of interest which the promoter shall be liable to pay the allottee, in case of default.
The relevant section is reproduced belornr: 15.
1,6.
1,7, Page 23 of 27 18.
HARERA complaint No.
212 of 201.9 ffiGURUGRAM "(za) "interest" meons the rates of interest poyable by the promoter or the allottee, as the case may be.
Explanation. -For the purpose of this clause- (i) the rate of interest chargeable from the allottee by the promoter, in case of default, shall be equal to the rate of interest which the promoter shall be liable to pay the allottee, in case of default; (ii) the interest payable by the promoter to the allottee shall be frorn the date the promoter received the amount or any part thereof till the date the amount or part thereof and interest thereon is refunded, and the interest payable by the allottee to the promoter shall be from the date the allottee defaults in payment to the promoter till the date it is paid;" On consideration of the documents available on record and submissions madc by both the parties regarding contravention of provisions of the Act, the authority is satisfied that the respondent is in contravention of the section 11[4)(a) of the Act by not hariding over possession by the due date as per thc agreernent.
By virtue of clause 1 of the agreement executed between the partics on 1,9.06.201.4, the due date of possession is calculated from the datc of Execution of Agreement.
As far as grace period is concerned, the same is allowed for the reasons quoted above.
Therefore, the due date of handing over posses;sion is Octob er, 2077 .
It is pelrtinent to mention over here that even after a passage of approx, B years neither the construction is complete nor the offer of possession of the allottccl unit has been made to the allottee e allottee by the respondent/promoter. 'l'he Authority is of the view that the allottee cannot be expected to wait endlessly for taking posse:;sion of the unit which is allotted to him and for which he has paid a consiilerable amount of money towards the sale consideration.
It is also to m€Dtirtn that complainants have paid more than 600/o of total consideration.
Further, the authority observes that there is no document placed on record from which it can be ascertained that whether the respondent has applied for occupation certificate/part occupation certificate or what is the status of construction of the project.
In view of the above-mentioned facts, the allottee 1,9.
Page24 of 27 HARIRII, GURUGRAM Complaint No.
212 of 2019 20. intenrls to',vithdraw from the project and are well within the right to do the same in view of section 1B[1) of the Act,20t6.
Irurther, the Occupation Certificate/Completion Certificate of the project wherc the unit is situated has still not been obtained by the respondent/promoter.'l'he authority is of the view that the allottees cannot be expected to wait endlessly for taking possession of the allotted unit and for which he has paid a consirlerable amount towards the sale consideration and as observed by l-lon'blc Supreme Court of India in lreo Grace Realtech Pvt, Ltd.
Vs.
Abhishek Khanna & Ors:., civil appeal no.
5785 of 2079, decided on 11.01.2021 ",.,, The occupation certrficate is not available even qs on date, which clearly amounts to deficiency of service.
The allottees cannot be made' to woit indefinitely Jor possessron of the opartments allotted to them, nor cen they be bound to take the apartments in Phase L of the project......." Moreover, the Hon'ble Supreme Court of India in the cases of Newtech Promroters and Developers"Private Limited Vs State of U.P. and Ors. (supra) reiterated in case of M/s Sana Realtors Private Limited & other l's llnion of India & others SLP (Civi\ No.
13005 of 2020 decided on 12.05 .2022. .05 .2022. obscrvccl as under: - "25.
The unqualified right of the allottee to seek refund referred Under Section 1B(1)(a) and Section Dft) of the Act is not dependent on ony contingencies or stipulations thereof. lt appears that the legislature ,has consciously provided this right of refund on demand os an unconditional absolute right to the allottee, if the promoter foils to give possession of the apartment, plot or building within the time stipulated under the terms of the agreement regardless of unforeseen events or stay orders of the Court/Tribunal, which is in either way not attributable to the allottee/home buyer, the pyomoter is under an obligation to refund the amount on demand with interest at the rate prescribed by the State Government including compensation in the manner provided under the Act with the proviso thot if the allottee does not wish to withdraw from the project, he shall be entitled for interest for the period of delay till handing over possession of the rate presuibed." 22.
The promoter is responsible for all obligations, responsibilities, and functions under the provisions of the Act of 2016, or the rules and regulations madc 21.
Page 25 ctf 27 HAB_ER& ffi.
GUI?UGRAM H.
Directions of the Authority Complaint No.212 of 2019 thereunder or to the allottees as per agreement for sale under section 1 1 [a) [a). 'l'he promoter has failed to complete or is unable to give possession of the unit in accr:rdance with the terms of agreement for sale or duly completed by the date specified therein.
Accordingly, the promoter no.L is liable to the allottee, as he wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of the unit with interest at such rate as may be prescribed.
23.
Accordingly, the non-compliance of the mandate contained in section 11[ )[a) read with section 18(1) of the Act on the part of the respondent no.1 is established. tablished.
As such, the complainants are entitled to refund of the entire amount paicl by them at the prescribed rate of interest i.e., @ 11 .1}'yo p.a. (thc State Bank of India highest marginal cost of lending rate (MCLR) applicable as on da[e +2o/o) as prescribed under rule 15 of the Haryana Real Estate IRegulation and Development) Rules, 201,7 from the date of each payment till the actual datc of refund of the amount within the timelines provided in rule 16 of the Haryana Rules 2017 ibid.
24.
Hence, the Authority hereby passes this order and issue the following directions under section 37 of the Act to ensure compliance of obligations casted upon the promoter as per the functions entrusted to the authority under section 34[f) of the Act: i. 'the respondent no.2 i.e., SARV Realtors Pvt.
Ltd. is directed to refund thc amount received by it from'the complainants along with interest at the rate of !1".L00/o p.a. as prescribed under rule 15 of the Haryana Real Estate liRegulation and Development) Rules, 2017 from the date of each payment rrill the actual date of refund of the deposited amount.
Page 26 of 27 ffiHARER$q ffieunuennm Out of total amount so assessed, the amount paid by the bank be refunded first to the bank and the balance amount along with interest will be refunded to the complainants.
Further, the respondent no.
3 is directed to get the NOC from the bank and give it to the complainants within a period orf 30 days of this order.
A period of 90 days is given to the respondent no.2 to compl)r with thc directions given in this order and failing which legal consequences would fclllow. iv, The respondent no.2 is further directed not to create any third-party rights a;gainst the subject unit before full realization of the paid-up amount along r,rrith interest thereon to the complainants, and even if, any transfer is initiated with respect to subject unit, the receivable shall be first utilized for clearing dues of allottee/complainants. v. inants. v.
N o directions are being passed in the matter qua respondent nos, 1 in view of the moratorium imposed under section L4 of the IBC in NCL,T case lll- 204lND 12021, titled Union Bank of India versus M/s Supertech [,intited.
Complaint No.212 of Z0L9 ii. iii.
25.
Complaint as well as applications, if any, stands disposed of accordingly.
26.
Files be consi ed to registry.
Sa Mernbe (^-w (Arun Kumar) Chairman Haryana Real Estate Regulatory Authorify, Gurugram Dated: 27.05.2025 Yr Z--> (Viiay Kumar Goyal) Member Page27 of27