Meta Pixel
CNR: --
PENDING

MR RUPAK KUMAR LOHIT AND MRS VEEPSA BHATIA LOHIT vs BPTP LTD.

Case NumberRERA-GRG-7694-2022
Date of Filing--
Case TypeRERA-GRG
Last Hearing22 Aug 2025
StateHaryana
CityGurgaon
Year of Filing2022

Party Details

Petitioner
  • MR RUPAK KUMAR LOHIT AND MRS VEEPSA BHATIA LOHIT
Respondent
  • BPTP LTD.

Case Summary

MR RUPAK KUMAR LOHIT AND MRS VEEPSA BHATIA LOHIT filed Case No. RERA-GRG-7694-2022 in the Haryana Real Estate Regulatory Authority (RERA) against BPTP LTD.. The case has undergone 13 hearings over 2 years and 3 months. The case is currently pending. 14 orders have been issued in this matter.

Hearing History (13)

  • 22AUG 2025
    Hearing

    Judge: VIJAY KUMAR GOYAL

    Matter is disposed of.

    Stage: DISPOSED

  • 25APR 2025
    Hearing

    Judge: VIJAY KUMAR GOYAL

    RE-OPENED

    Stage: RE-OPEN/PENDING

  • 28MAR 2025
    Hearing

    Judge: VIJAY KUMAR GOYAL

    Order reserved. Matter to come up on 25.04.2025 for pronouncement of order.

    Stage: RESERVED

  • 28FEB 2025
    Hearing

    Judge: VIJAY KUMAR GOYAL

    Vide Resolution dated 26.02.2025, a request has been received from the District Bar Association Gurugram regarding suspension of work on 28.02.2025 on account of annual election of District Bar Association Gurugram. In view of the above, the matter is adjourned to 28.03.2025  for the purpose as already fixed.

    Stage: PENDING

  • 24JAN 2025
    Hearing

    Judge: VIJAY KUMAR GOYAL

    The present complaint has been received on 21.12.2022 and the reply was received on 29.12.2023. The respondent is willing to settle the matter alongwith handing over possession after adjustment of DPC and other reliefs and a copy of email already sent to complainant has been handed over. The counsel for the complainant will seek instructions from the complainant. Matter to come up on 28.02.2025 for further proceedings.

    Stage: PENDING

  • 25OCT 2024
    Hearing

    Judge: VIJAY KUMAR GOYAL

    The present complaint has been received on 21.12.2022 and the reply was received on 29.12.2023. The proxy counsel for the respondent requests for an adjournment as the main arguing counsel is not well. In view of the work suspension call by District Bar association, Gurugram vide Resolution No.3577  dated 25.10.2024,  it has been requested not to pass an adverse order, the matter to come up on 24.01.2025 for further proceedings.

    Stage: PENDING

  • 9AUG 2024
    Hearing

    Judge: SANJEEV KUMAR ARORA

    Case has been called out but  no one has appeared on behalf of the complainant today. One last and final opportunity is granted to the complainant to appear and to argue the matter. Matter to come up on 25.10.2024 for further proceedings.

    Stage: PENDING

  • 12JUL 2024
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The counsel for the complainant states that respondent has not paid the previously imposed cost. However the counsel for the respondent has just now handed over the demand draft of previously  imposed cost to the counsel for the complainant during proceedings. The counsel for the complainant requests for a short adjournment to argue the matter. Request is allowed. Matter to come up  on 09.08.2024 for further proceedings.

    Stage: PENDING

  • 12APR 2024
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The present complaint has been received on 21.12.2022 and the reply was received on 29.12.2023. The proxy counsel for the complainant states that the main arguing counsel is not available today to argue the matter and seeks adjournment. Request is allowed. Matter to come up on 12.7.2024 for further proceedings.

    Stage: PENDING

  • 5JAN 2024
    Hearing

    Judge: HARISH GUPTA

    As per order dated 13.10.2023, respondent was directed to file reply within one week i.e. by 20.10.2023 alongwith advance copy to complainant with total cost of Rs. 15,000/- (5000/- previous cost  + 10,000/-) . Ms Anshika, proxy counsel for the respondent submitted that reply  on behalf of the respondent  was filed in the authority on 29.12.2023 and today cost is not being paid.  Adjournment requested on behalf of the respondent for payment of cost. At this stage, Ms Meenal Khanna proxy counsel for the complainant highly objected for grant of time for payment of cost. Ld. Proxy counsel for the complainant further submitted that reply was filed by the respondent on 29.12.2023 in the registry of the authority and same  is against the order dated 13.10.2023 by which the respondent was supposed to file reply by 20.10.2023. Ld proxy counsel for the complainant further submitted that till today   hard copy of reply not  supplied to the complainant. Further stated that  as reply was filed on behalf of the respondent after due date and as cost of Rs. 15000/- not paid by respondent so  defence of the respondent may be strucked off. Keeping in view the contentions of the Ld proxy counsels for the parties, now the matter is  listed before the authority on 12.4.2024 for further proceedings/orders .

    Stage: PENDING

  • 13OCT 2023
    Hearing

    Judge: ASHOK SANGWAN

    Vide preoceeding dated 19.05.2023, the counsel for the respondent had filed an application for mediation alongwith requisite fee,  mediation application was allowed.  Both the parties were directed to appear before the Adjudicating Officer on 13.07.2023 but none was present on behalf of the complainant and file was sent back to the Authority for further proceedings. Previous cost of Rs. 5000/- not paid by the respondent. Counsel for the respondent states that reply shall be submitted within a week. The counsel for the respondent is directed to file reply within one week  20.10.2023 along with an advance copy to the complainant with additional cost of Rs. 10,000/- to be paid to the complainant. Last opportunity is being granted. In case reply is not filed within the time allowed, the defence of the respondnet shall be  struck off. Matter to come up  on 05.01.2024   for further proceedings.

    Stage: PENDING

  • 13JUL 2023
    Hearing

    Judge: RAJINDER KUMAR

    None is present on behalf of complainant. In the absence of complainant, matter could not be settled between the parties. Let the file be sent back to the Authority for further proceedings.                            Parties be directed to appear before the Authority on 13.10.2023, i.e. date already fixed.

    Stage: PENDING

  • 19MAY 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The present complaint was filed on 21.12.2022 and registered as complaint no. 7694 of 2022. As per the registry, complainant has sent copy of complaint through speed post as well as through email and proof regarding having the delivery of the complaint made to the respondents were submitted by the complainant as available in the file. The registry of the authority also sent a notice along with a copy of the complaint through speed post. Registry has also sent the notice along with a copy of the complaint through email at the following email addresses [email protected] [email protected] [email protected] The same is shown to have been delivered on the above email address as per the report available in the file. It is proper service of the notice. The counsel for the respondent has filed an application for mediation alongwith requisite fee,  the proxy  counsel for the complainant states that the complainant has not received the reply, hence a direction be given to file the reply. Mediation application is allowed.  Both the parties are directed to appear before the Adjudicating Officer on 13.07.2023.  However, no reply has been received on behalf of the respondents till date. The counsel for the respondent is directed to file reply within two weeks after the mediation if at all it fails. Matter to come up  on 13.10.2023   for further proceedings.

    Stage: FIRST HEARING

Orders (14)

Judgement DetailsView full order PDF ↗

ffiHARERA S- euRuenRvr Complaint No.

7694 of 2022 and another BEFORE THE HARYANA REAL ESTATE REGULATORY AUTHORITY, GURUGRAM Date of Decision: -25.O4.7.025 NAME OF THE BUILDER BPTP Limited & Country Wide Promoters Private Limited PROIECT NAME "Terra", Sector- 37-D, Gurugram Haryana S.

No.

Case No.

Case title Appearance 1. cR/7694/2022 Rupak Kumar Lohit and Bipasha Bhatia Lohit VS.

BPTP Limited & Country Wide Promoters Private Limited Adv.

Priyanka Agarwal (Complainant) Adv.

Harshit Batra (Respondent) 2. cR/7902/2022 Astha Bhatia Reddy and Sudheer Ponnathota Reddy VS.

Harshit Batra (Respondent) CORAM: Shri Vijay Kumar Goyal Member ORDER 1.

The order shall dispose off both the complaints titled as above filed before this authoriry under section 31 ofthe Real Estate (Regulation and Developmentl Act,2076 (hereinafter *eferred as "the Act'') read with rule 28 ofthe Haryana Real Estate (Regtrlation and Developmentl Rules, 2017 (hereinafter referred as "the rules").

Since the core issues emanating from them are similar in nature and the complainant(sJ in the above referred matters are allottees of the projects, Terra", Sector- 37-D, Gurugram Haryana being developed by the same respondent- promoter i.e.

BPTP Limited.

The terms and conditions of the builder buyer's agreements that had been executed betlveen the parties interse are also similar.

The fulcrum of the issue involved in all these cases Page 1of30 HARERA GURUGRAM Complaint No.

7694 of 2022 and another pertains to failure on the part of the respondent/promoter to pay delay possession charges as per the terms of the builder buyers agreement, seeking possession along with interest and other reliefs.

2.

The details of the complaints, reply status, unit no., date of allotment letter, date ofagreement, due date ofpossession, offer ofpossession and relief sought are given in the table below: Possession clause 5. clause 5.1 The Seller/Confirming Party proposes to offer possession of the Unit to the Purchaser(sJ within e Commitment Period.

The Seller/Confirming Party shall be additionally entitled to a Crace Period of 180 days after the expiry of the said Commitment Period for making offer ofpossession ofthe said Unit.

1.6 "Commitment Period" shall mearL subject to, Force Majeure circumstances; intervention ofstatutory authorities and Purchaser(sl having timely complied with all its obligations, formalities or documentati requested by Seller/Confirming Party, under this Agreement and nc any part of this Agreement including but not limited to the ents ofthe sale consideration as per the payment plan opted, Development Charges [DC).

Stamp duty and other charges, the Seller/Confirming Party shall offer the possession of the Unit to the Purchaser[s] within a period of42 months from tie date ofsanction ofthe building plan or execution of Flat Buyer's Agreement, whichever is later.

Occupation certificate not received yet.

Sr.

Complaint No./Date of filing/ Reply status Unit/shop no. and r Date of execution ofbuilder buyer's agreement Due date of posscssion Basic Sale Price t Paid-up 1 cR/7694/202 2 Filling on: 21.12.2022 RRr- 29.12.2023 T-22-2002 Tower 22 1998 sq. ft. lAs per page no.46 ofreplyl 2213 sq. ft. - as per possession (increase is 10.s0h) 17 _!2_2012 77.72_2076 Rs.

1,04,89,500/- las per page no.

47 of reply) Rs.1,33,16,S00/- as per S0A dated 17-07 -2022 on page 76 ofthe complaint Rs.

1,30,69,43? /- (as per SOA dated 11.07 .2022 on paBe 76 of complaint) Offer of possession: - 13.10.2023 Page 2 of30 tL I cR/?902/202 2 Filling 2t.72.2022 RR:- 29.r2.2023 T-22-2102, Tower 22 1998 sq. ft. [As per page no.46 ofreplyl 2213 sq. ft. - as per offer of possession (increase is 10.s%) 28.01.2013 28.0t.2017 Rs.1,04,89,500/- [as per page no.

47 of replyl Rs.

1,22,?

8,824 / - (as per page 26 of complaint) Offerof possession:- 13.70. n:- 13.70.2023 Relief Sought by the complainants: - ] :'_-:-,I" l"'*"9"nt ro pay detay-cd possession charges on paid dmounr ntj acluat po\session. z urrerr rne respondenl to qua\h pLC char8es.

1.

Dire(t the respondent lo qua\h r-e cost ofincrease in super Jred wlthout ln(reaslng carpet arer.

4.

Direct the respondent to quash club membership charge; as club has "ot U."" io"""tru.tua.

5.

Direct the respondent ro quash holding charges.

HARERA GURUGRAN/ Complaint No.

7694 of2022 and another 3.

The facts of all the com are similar, Out of the above-mentioned case, the particulars of lead case CR/7694/2022 Rupak Kumar Lohit and Bipasha Bhatia Lohit VS, BPTP Limited & Country Wide promoters private Limited are being taken into consideration for determining the rights of the allottee(s).

Proiect and unit related details The particulars of the project, the details of sale consideration, the amount paid by the complainants, date of proposed handing over the possession, delay period, if any, have been detailed in the following tabular form: A, 4. s.N.

Particulars Details 1.

Name of the project - Terra", Sector- 37-D, Guruaram 2.

Nature of proiect Group Housing Towers Page 3 of30 fr HARERA GURUGRAM Complaint No.7694 of 2022 rnd another 3.

RERA registered/not registered Register 299 of 2 ed )17 dated 13.10 2077 4.

DTPC License no.

83 of dated 05.04.2C 2008 08 )4 of 24.1,0.2( 2077 dated 11 Validitv status 04.04.2C 25 23.L0.2( 19 Name oflicensee SUPER PVT.

LTI others BELTS ,and3 COUNTI PROMO' rnd 6 ot YWIDE 'ERS PVT LTD ters -$ Licensed area es 19.7 4 7.

Unit no.

T -22-20 lAs Der r ,1vl 8.

Unit measuring 1998 sq. [As per f 2273 sq. ft.

I of ret offer er ris 10.5%) ,ly] of possession Y 17 .1,2.2C 9. of FIat Date of execution buyer's agreement 1 of rel rly) 10 Date of building plan 2L.09.2C lAs stat€ t2 I by the respon( ent in his replvl 11.

Possession clause Posse 5. e Posse 5.1 T) propose to tht Commit Seller/Ct addition islon e Seller/Conl e to offer posses Purchaser(s nent Pe, nfirming Par tlly entitled to a irming PaW sion ofthe Unit ) within e iod.

The y shall be Grace Period of Page 4 of 30 v HARERA GURUGRA[I Complaint No.7694 of2022 and another 180 dqys after the expiry of the said Commitment Period for maktng offer of possession ofthe said Unit.

7.6 "Commitment Period" shall mean, subject to, Force Ma jeure circumstances; intervention of stqtutory authoities and Purchaser(s) having timely complied with all lfs obligotions, formalities or documentation, as prescribed/requested by Seller/Confirming Party, under this Agreement and not being in default under any part of this Agreement including but not limited to the timely payment of instalments of the sale consideratlon as per the pdyment plan opted, Development Charges'(DC).

Stomp duty and other charges, lhe Seller/ Conf; rming Party shall offer the poss€ssion of the Unit to the Purchaser(s) within a period of 42 months Irom the date of sanction of the building plan or execution of Flat Ruyer's Agreement, whichever is later.

72.

Due date of possession 17 .12.201-6 (calculated from the date of execution of buyer's agreemenl i.e., 77 .1,2.2012 being later as the building plan was sanctioned on 27 .09 .2012) Grace period In the present case, the promoter is seeking a grace period of 180 days for finishing work and filing and pursuing the occupanry certificate etc. from DTCP.

Therefore, the grace period is allowed, and the due date ofpossession comes out to be 17 .1.2.2016.

13.

Basic Sale Price Rs.

47 of replyl Page 5 of30 ffiHARERA #-GURUGRAI./ Facts ofthe complaint: The complainants have made the following submissions in the complaint; I That the complainant is a law-abiding citizen and consumer who have been cheated by the malpractices adopted by the Respondent ls stated to be a builder and is allegedly carrying out real estate development. velopment.

Since many years, the complainant being interested in the project because it was a housing project and the complainant had the need to own an own Home for their family.

That one-sided development agreement and inordinate delay in possession has been one of the core concerns of home buyers.

That the previous allottees approached to the respondent for booking of a flat admeasuring 199g Sq ft in BPTP Terra Sector- 37 D, Gurugram and paid booking amount Rs.

7,00,000/- through receipt Nos.

201211400023966 and 2012 / 1400023967 on dated 27.08.2012.

That the complainant was allotted the flat no- T22_ZOOZ,z}th Rs.

1,33,16,500/- as per SOA dated L1,.07 .2022 on page 7 6 of the complaint Total amount paid by the complainant Rs.

1.,30,69,437 /- (as per S0A dated 71.02.2022 on page 76 of complaint Occupation certificate dated Not recei n - lztna l1 Letter of offer of possession dated 13.1,0.2023 as per page no.

81 of reDl I.

II.

III.

Page 6 of30 ffiHAREIA *@*euRuenRv Complaint No, 7694 of2022 and another Floor, Tower 22, admeasuring 1998 Sq ft in project "BpTp Terra" Sector- 37 D, Gurugram.

That the respondent to dupe the complainant in their nefarious net even executed Buyer,s Agreement Signed Betlveen Complainants and M/S BpTp Limited & Countrywide Promoters pvt.

Ltd on dated 17 .1,2.20L2,lust to create a false belief that the project shall be completed in time bound manner and in the garb of this agreement persistently raised demands due to which they were able to extract huge amount of money from the complainants.

That the total cost of the said flat is Rs.7,33,77,226 /- including Basic, Development charges, Club, Firefighting & power Backup installation charge, 20th Floor PLC, IFMS, Car Parking, VAT as per S0A dated 11.07.2022 and also as per Builder Buyer Agreement and out of that sum of Rs.

13,069,437.35/- Paid by the complainants (more than 900/o of Total Sale Considerationl in time bound manner. nd manner.

That it is pertinent mentioned here that according to the statement the complainant paid a sum of Rs 13,069,437.35/- to the respondent till date and only last instalment is remained as per the Payment Schedule [more than 90% of Total Sale Consideration paid by complainant) and paid amount was demanded by the respondent without doing appropriate work on the said project even after extracting more than 900/o amount which is illegal and arbitrary.

That respondent was liable to hand over the possession of a said unit before L4.L2.2016 0ncluding Grace PeriodJ so far IV. vt.

Page 7 of30 HARERA @ cl tDt tcD^l\/ dzd \.,/vt\u\-/t\a1tv VIt. from completion as per FIat Buyer,s agreement clause no 5.1.

That respondent was liable and had committed to hand over the possession of a said unit before 74.06.20L6 so far from completion as per Buyer's agreement clause no 5.1 read with Clause 1.6 of BBA but the builder has still not offered the possession of the said Unit and has neither obtained the required OC till date.

As per construction status and absence of basic amenities respondents will take more time to give physical possession.

That the builder in last 10 years, several times made false promises for possession of flat and current status of project still desolated and raw not even 60 o/o work is completed builder breach the trust and agreement.

That as per section 19 (6) the Real Estate fRegulation and Development) Act,2016 (hereinafter referred to as the Act) Complainant has fulfilled her responsibility in regard to making the necessary payments in the manner and within the time specified in the said agreement.

Therefore, the Complainant herein are not in breach of any of its terms of the Agreement.

VIII.

That Complainant has paid all the instalments timely and deposited Rs.

13,069,437.3 5/-.

437.3 5/-.

That respondents in an endeavor to extract money from Allottees devised a payment plan under which respondent linked more than 20 0/o amount oftotal paid against as a an advance 75% amount linked with the construction of super structure only) of the total sale consideration to the time lines, which is not depended or co_ related to the finishing of flat and Internal development of tu Page 8 of30 Compiaint No.

7694 of 2022 and another IX. x. xt.

HARERA GURUGRAM facilities amenities and after taking the same respondent have not bothered to any development rest 5 % lined with offer of possession.

That respondent executed FBA is one sided at the time of offer of possession builder used new trick for extracting extra money from Complainant and forcibly imposed escalation cost, increase in super area, increase in STp, Electrification Charges and other similar charges, extra VAT Charges [opt Amnesty scheme or composition scheme, Extra GST charges etc.

The Respondent will increasing super area of the unit without increasing carpet area ofthe project and they revised building plan without consent from buyers as per DTCP and HARERA Norms builder should require 2,3 buyers' prior consent.

That the respondent has indulged in all kinds of tricks and blatant illegality in booking and drafting of FBA with a malicious and fraudulent intention and caused deliberate and intentional huge mental and physical harassment of the complainant and her family has been rudely and cruelly dashed the savoured dreams, hopes and expectations of the complainant to the ground and the complainant are eminently justified in seeking possession of flat along with delayed penalty.

That the respondent had illegal and unlustified demand towards VAT intimidation attempt to coerce and obtain an illegal and unfounded claim amount.

Respondent have cited case laws, namely the Raheja Development Corporation Case Complaint No.

7694 of 2022 and another x . nother x .

Page 9 of30 ffiHARETA #" eunuenRvr XIII, The complainants are seeking the following relief: The complainants have sought following relief(sl: I.

Direct the respondent to give the physical possession along with interest on prescribed rate of interest.

Direct the respondent quash the cost of increase in super area without increasing carpet area of the unit.

Direct the respondent quash Club Membership Charges Rs.

2,00,000 /-.

Direct the respondent to remove the cost of electrification charges and PLC charges.

V.

Direct the respondent not to charge holding charges.

D.

Reply filed by the respondents.

Complaint No.

7694 of 2022 and another (2005J and the L&T Limited case (2013J, which are broad and general rulings on taxation and works contract, but fail to apply to your frivolous, false, misleading claim.

That these cases have laid down a general principle of law in respect of works contract taxes and has absolutely no bearing in the present matter.

We maintain that the scheme has come in operation through notification of the State of Haryana, and is independent ofthe cited case laws, and is merely to rationalize the taxation on developers as the appropriate assesses.

Respondent applied reasoning in the Note on value added liability is misleading and misconstrued.

That the liability of the VAT is on builder and it is a given under the law.

It is submitted that the cause of action to file the instant complaint has occurred within the jurisdiction of this Authority.

C.

6.

II I.

IV, Page 10 of 30 HARERA W" GURUGRAII 7.

7694 of 2022 and another I.

The respondents have contested the complaint on the following grounds: That the complainants booked a unit vide an application form dared 27.08.2012 by paying a booking amount of Rs.

7,00,000/- vide cheque no.

318118 and 208198.

Pursuant to booking in the said Proiect, a letter dated 19.10.2012 was sent to the Complainants in order to invite the Complainants for the selection of the unit for allotment. allotment.

That subsequent to such invitation, a unit bearing number T- 22 - 2002,2Oth Floor, Tower TZZ, tentatively admeasuring 1998 sq. ft. was selected as per the terms and conditions ofthe Application Form and a letter dated 27.10.2072 was thereby issued in favour of the Complainant confirming the selection of the above- noted unit and consequently, the Allotment ofthe same took place vide Allotment Letter dated 07.),2.2012.lt is submitted that prior to approaching the Respondent No.

1, the Complainants had conducted extensive and independent enquiries regarding theproiect and it was only after the Complainants were fully satisfied with regards to all aspects of the project, that the Complainants took an independent and informeddecision to purchase the unit, un-influenced in any manner by the Respondents.

That the complainants consciously and wilfully opted for subvention-scheme plan asper their choice for remittance of the sale consideration for the unit in question and thereby a tripartite agreement dated 2L.77.2072 and further represented to the respondent no.

1 that they shall remit every II.

III, Page 11 of 30 ffiHARERA #,ounuennl,r IV.

That consequently, a flat buyer's agreement dated 17.L2.2072 was executed betweenthe complainants and respondents.

It is pertinent to mention that the flat buyer,s agreement was consciously and voluntarily executed between the parties and the terms and conditions of the same are binding on the parties.

That it is respectfully submitted that the rights and obligations of allottee as well asthe builder are completely and entirely determined by the covenants incorporated in the Agreement which continue to be binding upon the parties thereto with full force and effect.

That the due date is calculated from the execution of Flat Buyer's Agreement (17.1,2.201,2) being later as the Buildings Plan of the project was sanctioned on?l.O9.201,2.

Thus, the proposed due date for offer of possession comes out to be 17 .'12. e 17 .'12.2076 (including the grace period).

That it is most humbly submitted that the construction of the Unit was hampered due to and was subiect to the happening of the force majeure and other circumstances bevond the Complaint No, 7694 of 2022 and another instalment on time as per the payment schedule.

That the respondent no. t had no reason to suspect bonafide of the complainants.

It is pertinent to mention here that the Respondent has always been responsible for their liability and hence paid all the Pre-EMI as per the agreed terms and conditions of the Agreement.

The bonafde of the Respondents shall be noted that as per the Agreement, the Respondent were only liable to pay the Pre-EMI amount ti1130.06.2015.

VI.

VII.

Page 12 of30 HARERA HR GURUGRAM control of the company, the benefit of which is bound to be given to the Respondent no.1 in accordance with clause 10 r/w 1.17 ofthe Agreement.

At this stage, it is categorical to note that Respondent No.1 was faced with certain force majeure events including but not Iimited to non-availability of raw material due to various orders of Hon,ble punjab & Haryana High Court and National Green Tribunal thereby regulating the mining activities, brick kilns, regulation of the construction and development activities by the judicial authorities in NCR on account of the environmental conditions, restrictions on usage of water, etc.

It is pertinent to state that the National Green Tribunal in several cases related to punjab and Haryana had stayed mining operations including in O.A No.

17l/20L3, wherein vide Order dated 2.11.2015 mining activities by the newly allotted mining contracts by the stateof Haryana was stayed on the Yamuna River bed.

These orders in fact inter_alia continued till the year 201g.

Similar orders staying the mrning operations were also passed by the Hon,ble High Court and the National Green Tribunal in punjab and Uttar pradesh as well. h as well.

The stopping of mining activity not only made procurement of material difficult but also raised the prices of sand/gravel exponentially.

It was almost Z years that the scarcity as detailed aforesaid continued, despite which all efforts were made and materials were procured at 3_4 times the rate and the construction continuedwithout shifting any extra burden to the customer, The time taken by the Respondent No.1 to Page 13 of30 Complaint No.

7694 of 2022 and another HAREl?A P*GURUGRAM develop the project is the usual time taken to develop a proiect of such a large scale and despite all the force majeure circumstances, the Respondent No.1 completed the construction of the Project diligently and timely, without imposing any cost implications of the aforementioned circumstances on the Complainants and demanding the prices only as and when the construction was being done.

It is to be noted that the development and implementation of the said Project have been hindered on account of several orders/directions passed by various authorities/forums/courts, before passing of the subjective due date o[offer ofpossession.

IX.

That additionally, even before the normalcy could resume, the world was hit by the Covid-19 pAndemic.

That the covid-19 pandemic resulted in serious challgnges to the 0projectwith no available labourers, contractors etc. for the construction of the Project.The Ministry of Home Affairs, GOI vide notification dated March 24, 2020 bearing no, 40-3 /2020-DM-I(A) recognized that India was threatened with the spread ofCovid- 19 pandemic and ordered a completed lockdown in the entire country for an initial period of 21 days which started on March 25, 2020.

By virtue of various subsequent notifications, the Ministry of Home Affairs, GOI further extended the lockdown From time to time and till date the same continues in some or the other form to curb the pandemic. pandemic.

Various State Governments, including the Government ofHaryana have also enforced various strict measures to prevent the pandemic Page 14 of30 ffiHARERA ffi aTRUcRAtr/ second wave of Covid-19 pandemic and again all the activities in the real estate sector were forced to stop.

It is pertinent to mention, that considering the wide spread of Covid-19, firstly night curfew was imposed followed by weekend curfew and then complete curfew.

That during the period from 1.2.04.2021 to 24.07.202L, each and every activity including the construction activity was ba4ned in the State.

This has been followed by the recent wave brought by the new covid variantin the country.

Therefore, it is safely concluded that the said delay in the seamless execution of the project was due to genuine force majeure circumstances and the said period shall not be added while computing the delay.

Furthermore, it needs to be seen that the development of the Unit and the Project as a whole is largely dependent on the fulfilment of the allottees in timely clearing their dues.

That the due date of offer of possession was also dependent on the timelypayment by the Complainants, which, the Complainants failed to do.

The demands were raised as per the agreed payment plan however, despite the same, the Complainants have delayed the payment against the Unit.

That the total sales consideration of the unit was Rs.

1,68,98,075.3 3/- out of which the Complainantshad/have only made payment of Rs.

1 ,30 ,69 ,437 .35 / - That it was the obligation of the Complainants to make the Page 15 of30 Complaint No.

7694 of 2022 and another includingimposing curfew, lockdown, stopping all commercial activities, stopping allconstruction activities.

Despite, after above stated obstructions, the natlon was yet again hit by the X. xt. ffiHARERA #" eunuennl,r XII, XIII, payments as per the adoptedpayment plan and agreed terms and conditions of the agreement. agreement.

That the timelypayment of the sales consideration of the unit was the essence of the Agreementexecuted between the parties as per clause 7 of the Agreement.

That in case of default by the Complainants, the Complainants bound to make the payment of interest.

That this obligation has also been noted in the RERA, 2016.

It is submitted that the demand letters were raised as per the agreed payment plan however, the Complainants had continuously delayed in making the due payments, upon which, various payment request lstters and reminder notices were also served to the Complainants from time to time.

That the Project and attained the in-principal Occupation Certificate from the concerned Authority vide MEMO No.

Zp- 437-tV /PA(DR)/2023/31681 d,ated, 27.09.2023 and hence offered the possession of the unit to the Complainants vide Notice for Offer of Possession dated 13.10.2023.

At this stage, it is pertinent to mention here that all the claims put forth by the Complainants in the present complaint are wrong and frivolous and hence the present complaint is liable to be dismissed.

That the Complainants, in the present case, has relied on the Offer of possession of an allottee of another tower in same Project.

It is pertinent to mention here that no demand as alleged in the Offer of possession of another allottee has been raised by the Respondent, till date.

That in any case whatsoever, no reliance can be placed on such offer of another allottee or demands raised from anV other allottee.

Page 16 of30 Co m pfa i nt N o.

769 4 o f 2022 and another ffiHABERA ffi ounuennl,l xv.

7694 of2022 and another XIV.

It is imperative to mention here that as per Clause 4.1 of the BBA, the Complainants acknowledged the fact that the building plans ofthe proiect are subject to change till the stage of grant of Occupation Certificate and hence are indicative in nature and may undergo change during the course of construction as required by the statutory authority. authority.

Moreover, the Complainants also agreed to the fact that in case the Super Built up area of the unit exceeds +/- 15% of the original booked area, the same shall be intimated to the Complainants in writing.

The relevant Clause 4.1 and 4.1(c) is reiterated hereunder.

8.

Copies of all the relevant documents have been filed and placed on the record.

Their authenticity is not in dispute.

Hence, the complaint can be decided on the basis of these undisputed documents and submission made by the parties.

Jurisdiction of the authority The authority observes that it has territorial as well as subject matter jurisdiction to adjudicate the present complaint for the reasons given below: E.

I Territorial iurisdiction 10.

As per notification no.7/92/2017-tTCp dared t4.12.2077 issued by Town and Country Planning Department, Haryana the iurisdiction of Real Estate Regulatory Authority, Gurugram shall be entire Gurugram District for all purpose with offices situated in Gurugram.

In the present case, the pro.iect in question is situated within the planning area of Gurugram District, therefore this authority has completed territorial jurisdiction to dealwith the present complaint. page 17 of30 E.

9.

HARERA gP GURUGRAIV E.

II Subiect-matter iurisdiction 1.1.

Section 11(aJ(aJ of the Act provides that the promoter shall be responsible to the allottee as per agreement for sale.

Section 11[4] (aJ is reproduced as hereunder: Section 77 (4) The promoter shall- (a) be_ -responsib,le for att obligations, responsibilities and Ju LLtons under the provisions ofthis Act or the rules and regulations made thereunder oi to tn" auixi"i oi'i, ne agreementfor sale, or to the dssociation ofollottee{, as the case may be, till the conveyance of .all tn, iporti"rtr, ptol^ or buitdings, as the casi may nL: ,o ,n"Ztuiii"i,''i, tn" common areas to the associahn of allottees or the ^ . or the ^ .competent authoriry, as the cos" roy i"; Section J4_Functions oI the Authoriry; J4U) of the Act provides to ensure coipliance of the obti.qations cost upon the promoters, the ollottees ora'tni ,io,t" "rt t" agents under this Act and the rules and reguiotiinu made thereunder.

12.

So, in view of the provisions of the Act of 2016 quoted above, the authority has complete jurisdiction to decide the complaint regarding non-compliance of obligations by the promoter leaving aside compensation which is to be decided by the adjudicating officer if pursued by the complainant at a later stage.

Findings on the obiections raised by the respondents: Obiection regarding delay in completion of construction due to force maieure conditions, ofproiect 13.

The respondents raised the contention that the construction of the pro,ect was delayed due to force majeure conditions such as the orders of the National Green Tribunal, Hon,ble Environment pollutlon (Prevention and Control Authority], Haryana State pollution Control page 18 of30 F.

F.t t J Complaint No.

269+ nrzouz..,r "ll,Ill_-l 14. ffi HARERA #- aLnuennl,r 15.

Complaint No, 7694 of 2022 and another Board, Hon'ble Supreme Court prohibiting construction in and around Delhi and the Covid-19 pandemic among others, but all the pleas advanced in this regard are devoid of merit.

In the present matter, the builder buyer's agreement was executed between the parties on U.12.2072.

Therefore, the due date of handing over of possession is taken from the clause 5.1 read with 1.6 of the agreement and the delivery date stipulated from the delivery period in the agreement comes out to be 17.1,2.201-6.

The events suchas the orders of the National Green Tribunal, Hon'ble Environment pollution (Prevention and Control Authority), Haryana State pollution control Board, Hon'ble Supreme Court prohibiting construction in and around Delhi among others were for a shorter duration of time and were not continuous as there is a delay of around five ye nd five years and even happening after due date of handing over of possession.

Though some allottees may not be regular in paying the amount due but the interest of all the stakeholders concerned with the said project cannot be put on hold due to fault of some of the allottees.

Thus, the promoter- respondents cannot be granted any leniency for aforesaid reasons.

It is well settled principle that a person cannot take benefit of his own wrongs.

As far as delay in construction due to outbreak of Covid-19 is concerned, Hon'ble Delhi High Court in case titled as M/s Halliburton Offshore Services Inc.

V/S Vedanta Ltd. & Anr. bearing no.

O.M. p (t) (Comm.) no.8A/ ZO2O and I.

As 3696-3697 /2020 dated 29.05.2020 has observed that: 69, The past non-performance of the Contractor cannot be condoned due to the COVID-19 lockdown in March 2020 in t4/ Page 19 of30 ffi HARERA #.arRuGRAu Complaint No.

7694 of 2022 and another India.

The Contractor was in breach since September 2079.

0pportunities were given to the Contractor to cure the same repeatedly.

Despite the same, the Contractor could not complete the Project.

The outbreak of a pandemic cannot be used ds an excuse for non-performance of a contrdct for which the deadlines were much before the outbreak itself." 16.

The respondent was liable to complete the construction ofthe project and the possession ofthe said unit was to be handed overby 17.12.2076 and the respondents are claiming benefit of lockdown which came into effect on 2 3.03.2 020 whereas the due date ofhanding over ofpossession was much prior to orders of court and the event of outbreak of Covid-19 pandemic.

Therefore, the Authority is of the view that outbreak of a pandemic cannot be used as an excuse for non- performance of a contract for which the deadlines were much before the outbreak itself and for the said reason, the said time period is not excluded while calculating the delay in handing over possession.

G.

Observations ofthe authority 17. hority 17.

Since, common issues with regard to super area, cost escalation, STP charges, electrification charges, taxes viz GST &VAT, advance maintenance charges, car parking charges, holding charges, club membership charges, PLC, development location charges and utility connection charges, EDC/lDC charges, firefighting/power backup charges are involved in all these cases and others pending against the respondents in this project as well as in other projects developed by them.

So, vide orders dated 06.07.2021 and 17.08.2027 a committee headed by Sh.

Manik Sonawane IAS (retired), Sh.

Laxmi Kant Saini CA and Sh.

R.K.

Singh CTP (retired) was constituted and was asked to submit its report on the above-mentioned issues.

The representatives of the allottees were also associated with the committee and a report was Page 20 of 30 HARERA -€P- GURUGRAII Complaint No.

7694 of 2022 and another submitted and the same along with annexures was uploaded on the website of the authority.

H, Findings on the relief sought by the complainants.

G.I.

Directthe respondentsto deliverthe physical possession of the unit along with delay possession charges, G.ll.

Direct the respondent quash the cost of increase in super area without increasing carpet area ofthe unit.

G.lll.

2,OO,O0O/-.

G.lV, Direct the respondent to remove the cost of electrilication charges and PLC charges.

G.V.

18.

In the present complaint, the complainants intend to continue with project and is seeking delay possession charges as provided under proviso to section 18(1J ofthe Act, Sec.

18(1J proviso reads as under: "Section 78: - Return of amount and compensation 18(1). lf the promoter fails to complete or is unable to give possesslon of an apartment plot or building, - Provided that where an allottee does not intend to withdraw from the projecg he sholl be paid, by the promoter, interestfor every month of delay, till lay, till the handing over of the possession, at such rate as may be prescrlbed." 19.

Clause 5 and 1.6 of the buyer's agreement provides for time period for handing over of possession and is reproduced below: Clause 5 POSSESS/ON AND HOLDING CHARGES 5.1 The Seller/confrming Porty proposes to offer possession ofthe I|nit to the Purchaser(s) within the Commitment Period.

The Seller/Confirming Porty sholl be additionqlly entitled to o Grace Pe od of 180 days after the expiry of the said Commitment Period for making offer of possession ofthe soid Unit.

Clquse 1 DEFINITIONS: 1,6 "Commitment Period" shall meqn, subject to, Force Moieure circumstances; intervention of statutory authorities ond Purchaser(s)hoving timely complied with oll its obligations, the the Page 21of30 HARERA W.GURUGRAI/ Complaint No.

7694 of 2022 and another formalities or documentation, as prcscribed/requested by Seller/Confirming Porty, under this Agrcement and not being in default under any part of this Agreement, including but not limited to the timely poyment of instalments of the sale consideration os per the payment plon opted.

Development Charges (DC), Stamp Duty and other charges, the Seller/Confrrming Parq) shall olfer the possession of the Ilnit to the Purchoser's within a period of 42 months from the date of sqnction of the building plon or execution of Flot Buyer's Agreement, whichever is later.

20.

Due date of possession and admissibility of grace period: The promoter has proposed to hand over the possession of the said unit within a period of 42 months from the date of sanction of the building plan or execution of Flat Buyer's Agreement, whichever is later and further provided in agreement that promoter shall be entitled to a period of 180 days ("Grace Period") after the expiry of the said Commitment Period for making offer of possession of the said unit.

The period of 42 months expired on 17.L2.20L6 (calculated from the date of execution of buyer's agreement i.e., U.72. .e., U.72.2012 being later as the building plan was sanctioned on 2f.09.2012).

Since in the present matter, the BBA incorporates unqualified reason for grace period/extended period in the possession clause.

Accordingly, the authority allows this grace period of 6 months to the promoter at this stage.

21.

Admissibility of delay possession charges at prescribed rate of interest: The complainant is seeking delay possession charges at the prescribed rate.

Proviso to section 18 provides that where an allottee does not intend to withdraw from the project, he shall be paid, by the promoter, interest for every month of delay, ti]] the handing over of possession, at such rate as may be prescribed and it has been prescribed under rule 15 of the rules.

Rule 15 has been reproduced as under: Page 22 of 30 SHARERA ffi arnuenntrr Complaint No.

7694 of2022 and another Rule 75, Prescribed rate of interest- lproviso to section 72, section 78 and sub-section (4) qnd subsection (7) ofsection 791 (1) For the purpose of proviso to section 12; section 18; and sub- sections (4) and (7) of section 19, the "interest at the rate prescribed" sholl be the Stote tsank of lndia highest marginal cost of lending rote +20k.: Providecl thot in case the Stote Bonk oflndia morginal costof lencling rate (MCLR) is not in use, it shall be replaced by such benchmqrk lending rates which the Stote Bonk of lndio may fix from time to time for lending to the generolpublic.

22.

The legislature in its wisdom in the subordinate legislation under rule 15 ofthe rules has determined the prescribed rate of interest.

The rate ofinterest so determined by the legislature, is reasonable and if the said rule is followed to award the interest, it will ensure uniform practice in all the cases.

23.

Consequently, as per website of the State Bank of India i.e., https: / /sbi.co.in, the marginal cost of lending rate (in short, MCLR) as on date i.e., 25.04.2025 is 9.10%. is 9.10%.

Accordingly, the prescribed rate interest will be marginal cost of lending rate +Za/o i.e., LL.10V0.

24.

Rate of interest to be paid by the complainant in case of delay making payments- The definition of term 'interest' as defined under section 2(za) of the Act provides that the rate of interest chargeable from the allottee by the promoter, in case ofdefault, shall be equal to the rate of interest which the promoter shall be liable to pay the allottee, in case of default.

The relevant section is reproduced below: "(zo) "interest" meons the rqtes of interest poyable by the promoter or the dllottee, os the czse may be.

Explonation. -For the purpose ofthis clause- O the rdte of interest chargeoble from the allottee by the promoter, in case ofdefoult, shall be equolto the rate ofinterestwhich the promoter shall be liable to pay the allottee, in case ofdefoulq (ii) the interest paydble by the promoter to the allottee shollbefrom the date the promoter received the amount or ony port thereof till the dote the amount or part thereof and interest thereon is refuncled, and the interest pqyable by the allottee to the Page 23 of30 of ln Complaint No.

7694 of 2022 and another 25.

26. ffiHARERA #- aJRUGRAI/ promoter sholl be from the dote the qllottee defaults in payment to the promoter till the date it is paidi' Therefore, interest on the delay payments from the complainant shall be charged at the prescribed rate i.e., 11.10% by the respondent/ promoter which is the same as is being granted to the complainant in case of delayed possession charges.

0n consideration ofthe documents available on record and submissions made by the parties regarding contravention as per provisions of the Act, the authority is satisfied that the respondent is in contravention of the section 11(4J(a) of the Act by not handing over possession by the due date.

By virtue of clause 5 read with clause 1.6 of the buyer's agreement executed between the parties bn U.12. s bn U.12.201,2,the possession of the subject flat was to be delivered witdin a period of 42 months from the date of sanction of building plans or date of execution of buyer's agreement, whichever is later.

For the reason above, the due date of possession is to be calculated from the date of execution of buyer's agreement 17.12.2012 being later and as far as grace period of 180 days is concerned, the same is allowed for the reasons quoted above.

Therefore, the due date of handing over possession comes out to be 17.12.2016.

However, the respondent has failed to handover possession of the subject apartment to the complainant till the date of this order, Accordingly, it is the failure of the respondent/promoter to fulfil its obligations and responsibilities as per the agreement to hand over the possession within the stipulated period.

The authority observes that there is no document on record from which it can be ascertained as to whether the respondent has applied for occupation certificate or what is the status of construction of the project.

Hence, this project is to be Page 24 of30 HARERA GURUGRA[/ Complaint No,7694 of2022 and another treated as on-going pro,ect and the ptovisions of the Act shall be applicable equally to the builder as well {s allottees.

27.

Accordingly, the non-compliance of the fnandate contained in section 11(4J (aJ read with proviso to section 18d1) of the Act on the part of the respondent is established.

As such, the allottee shall be paid, by the promoter, interest for every month ofdelay from due date ofpossession i.e., 17.1,2.2076 till valid offer of possession plus 2 monrhs after obtaining occupation certificate from the competent authority or actual handing over of possession whichever is earlier, as per section 18(1) of the Act of2016 read with rule 15 ofthe rules.

G.ll Increased Super Area 28. r Area 28.

It is contended that the respondents harle increased the super area of the subiect unit without giving any formal intimation, by taking any written consent from the allottees.

On perusal of record, the super area of the unit was 1998 sq. ft. as per the flat buyer's agreement and it was increased by 215 sq. ft. vide letter of offer of possession, resulting in total super area of 221,3 sq. ft.

The authority holds that the super area Isaleable area) ofthe flat in this project has been increased and as found by the committee, the super area of the unit would be revised and increased by the respondent, and they shall pass on this benefit to the complainant/allottees as per the recommendations of the committee.

G.lll Club Membership Charges 29.

The term club membership charges have been defined under clause 1.4 and clause 3.2(a) prescribes the amount ofclub membership charges to be levied, which are reproduced below: 1,4 "Club Membership Chorges" or "CMC" shall neon chorges to be paid by the purchaser(s) to the seller or the maintenance Page 25 of30 * HARERA #* eunuennv Complaint No.

7694 of 2022 and another service provider for membership of the club to be developed by the seller/confirming party.

However, aforesaid chorges do not include the usage charges for the club facilities, which sholl olways be poyoble extra by the purchoser[s).

3,2 in addition to the qforesaid cost of property, the purchoser(s) has undertaken and qgreed to poy the Jollowing charges: - q) club membership charges ("CMC") @ Rs.

2'00,000/' per uniL The said issue was also referred to the committee and who after due deliberations and hearing the affected parties, submitted a report to the authority wherein it was observed as under: "...After deliberation, it was agreed upon that club membership will be optional. optional.

Provided if an allottee opts out to avail thisfacility and later approaches the respondent fof membership of the club, then he shall pay the club membership charges as may be decided by the respondent and shall not invoke the terms of FBAi that limits CMC to INR 1.,00,000.00. ln view of the consensus arrived, the club membership may be made optional.

The respondent may be directed to refund the CMC if any request is received from the allottee ln this regard with condition that he shall qbide by the above proviso." lt was also observed, while giving recommendations that in the cases of nominees of projects 'spacio' and 'Park Generation' on issues concerning super area, car parking charges, development charges, cost escalation, advance maintenance, GST & VAT etc. may be implemented in case of the allottee/complainant of 'Terra' proiect also and the respondent may be directed to comply with the same while offering possession.

32.

The authority concurs with the recommendations made by the committee and holds that the club membership charges ICMC) shall be 30.

31.

Page 26 of30 SHARERA #-eunuennH,l optional.

The respondent shall refund the CMC if any request is received from the allottee.

Provided that ifan allottee opts out to avail this facility and later approaches the respondent for membership of the club, then he shall pay the club membership charges as may be decided by the respondent and shall not invoke the terms offlat buyer's agreement that limits CMC to Rs.1,00,000/-.

G.IV Preferential Location Charges: 33.

Both the respondent and the complainants are bound by the terms and conditions of the FBA.

The term PLC has been defined under clause 1.31 and clause 3.1@ prescribes the amount of PLC to be levied, which are reproduced below: 1.31 "Prekrenti.tl Location Charges" orbLC" shqtl meqn the charges payable by the purchaser(s), calculated on super built up areq, in case the unit qllotted to the purchaser(s) has a locqtional advantage. advantage.

There con be more thon one PLC charges applicsble to o unit" "clouse 3.1@ of FBA- Preferential Location Charge ('PLC') all units will attract one or more PLC, as applicoble, due to their locationol advantage, os per the toble below.

However, the total PLC for a unit shq not exceed 120k of BSP.

Prelerential Location Chorges on BSP Corner - 7ak Corner+Club or pork facing 10ok Park Focing - 7ak Ground Floor- Sok First Jloor- 4o/o Second/Third Floor- 3ok 34.

This issue was also referred to the committee and who after due deliberations and hearing the affected parties, submitted a report to the authority wherein it was observed that the PLCs have been Ievied strictly in accordance with the provisions of the clauses referred to Complaint No.

7694 of 2022 and another Page 27 of 3O HARERA GUllUGRAII Complaint No.

7694 of 2022 and another above.

In view of this, the committee recommends that the respondent may be directed to submit an affidavit declaring that PLCS have been Ievied strictly as prescribed in the FBAs executed with the complainant in the project "Terra".

G.V Electrification Charges 35.

In the present complaint, it was contended by the complainant that the respondent has been charging various uniust and unreasonable demands under various heads i.e. electrification charges On the other hand, the respondent submitted that such charges have been demanded by the allottees in terms of FBA.

36.

The authority concurs with the recommendations made by the committee and holds that the term electrification charges, clubbed with STP charges, used in the statement of accounts-cum-invoice be deleted, and only STP charges be demanded from the allottee ofTerra @ Rs.8.85 sq. ft.

Further, the term ECC be clubbed with FFC+PBIC in the statement of accounts-cum-invoice attached with the letter of possession of the allottee of Terra and be charged @ Rs.100 per sq. ft. in terms of the provisions of 2.1 (t) at par with the allottee of Park Generation. eneration.

The statement of accounts-cum-invoice shall be amended to that extent accordingly.

H.

Directions of the authority 37.

Hence, the authority hereby passes this order and issue the following directions under section 37 of the Act to ensure compliance of obligations cast upon the promoter as per the function entrusted to the authority under section 34(0: Page 28 of30 HARERA Complaint No.

7694 of 2022 and another ffiGURUGRAII L The respondent is directed to pay delayed possession charges at the prescribed rate of interest @ll.70o/o p.a. for every month of delay from the due date of possession i.e., 17.12.2016 till valid offer of possession plus tlvo months after obtaining 0C from the competent authority or actual handing over ofthe unit, whichever is earlier, as per section 18(1) of the Act of 2015 read with under Rule 15 ofthe Haryana Real Estate (Regulation and Development) Rules,2017.

The said amount shall be payable after adjusting the Pre-EMl amounts already paid by the respondent to the ll. complainant.

The arrears ofsuch interest accrued from 17.12.2016 till the date of order by the authority shall be paid by the promoter to the lv. allottee(s) within a period of90 days from date ofthis orderas per rule 16(2) ofthe rules.

The respondent/promoter shall handover the physical possession of the allotted unit and execute conveyance deed in favour of the complainant in terms of section 17(1) of the Act of 2016 on payment of stamp duty and registration charges as applicable' The rate of interest chargeable from the allottee by the promoter, in case of default shall be charged at the prescribed rate i'e, ]rl.LOo/o by the respondent/promoter which is the same rate of interest which the promoter shall be liable to pay the allottees, in case of default i.e., the delayed possession charges as per section 2(za) of the Act. v.

The respondent is also directed not to charge anything which is lll. not part of builder buyer's agreement. agreement.

Page 29 of30 *HARERA #-eunl,lennrr,l 39.

40. the complaints.

File be consigned to Dated:25.

7 694 of 2022 vi.

That the Hon'ble Supreme Court vid judgment 74.12.2020 in civil appeal no.

3864-3889 /2 had upheld the order dated 03.01.2 lays in unequivocal terms that no h the allottee to the develoPer.

This decision shall mutatis mutandis app of this order wherein details of paid-up Complaint as well as aPP CDRC, which ding charges payable by to cases men in para 2 ount is men in each of ds disposed accordingly. !,t (v.K.

Regulatory M whereby the 20 passed by 'ble Court n I ( Page 30 of 30