FIRST HEARING

TUSHAR JAIN vs SUNRAYS HEIGHTS PVT. LTD.

Case NumberRERA-GRG-2171-2024
Date of Filing--
Case TypeRERA-GRG
Last Hearing24 Apr 2025
StateHaryana
CityGurgaon
Year of Filing2024

Party Details

Petitioner
  • TUSHAR JAIN
Respondent
  • SUNRAYS HEIGHTS PVT. LTD.

Case Summary

TUSHAR JAIN filed Case No. RERA-GRG-2171-2024 in the Haryana Real Estate Regulatory Authority (RERA) against SUNRAYS HEIGHTS PVT. LTD.. The case has undergone 4 hearings over 9 months. The case is currently pending. 4 orders have been issued in this matter.

Hearing History (4)

  • 24APR 2025
    Hearing

    Judge: VIJAY KUMAR GOYAL

    Matter is disposed of.

    Stage: DISPOSED

  • 9JAN 2025
    Hearing

    Judge: ANU

    File taken up today as I shall be on leave i.e. 09.01.2025 and 10.01.2025, hence the case is adjourned to 24.04.2025 for the same purpose as already fixed.

    Stage: PENDING

  • 5SEP 2024
    Hearing

    Judge: VIJAY KUMAR GOYAL

    The counsel for the respondent has filed  power of attorney today during proceedings and seeks time to file reply. The respondent is directed to file reply within a period of three weeks in the registry of the authority after supplying a copy to the counsel for the complainant failing which cost of Rs. 5000/- shall be imposed and defence of the respondent may be struck off. Matter to come up on 09.01.2025 for further proceedings.

    Stage: PENDING

  • 4JUL 2024
    Hearing

    Judge: VIJAY KUMAR GOYAL

    The present complaint was filed on 20.05.2024 and application u/s 36 by complainant on 31.05.2024. Succinct facts of the case are as under S.No. Particulars Details 1.       Name of the project “Sixty-Three Golf Drive”, Sector 63A Gurugram 2.       Nature of the project Affordable group housing 3.       RERA registered or not registered 249 of  2017 dated 26.09.2017 valid up to 25.09.2022 4.       DTCP license 82 of 2014 dated 08.08.2014 valid up to 31.12.2023 5.       Unit no. B23 (as per demand letter page 20 of complaint) 6.       Unit admeasuring 604.83 sq. ft. (carpet area) (page 20 of complaint) 7.       Buyers agreement Not executed 8.       Possession clause  As per affordable housing policy 2013 1(iv) All such projects shall be required to be necessarily completed within 4 years from the approval of building plans or grant of environmental clearance, whichever is later. This date shall be referred to as the "date of commencement of project” for the purpose of this policy. The licence shall not be renewed beyond the said 4 years from the date of commencement of project. 9.       Date of building plan 10.03.2015 (taken from another file CR/2814/2021 decided on 30.11.2023 of same project) 10.          Date of environment clearance 16.09.2016 (taken from another file CR/5238/2022 of same project) 11.          Due date of possession 16.03.2021  (16.09.2020 plus six months in lieu of covid-19) (calculated from the date of environment clearance) 12.          Total sale consideration Rs.24,66,870/- (as alleged by complainant) 13.          Amount paid by the complainant Rs.23,32,205/- (as alleged by complainant) No relevant document of proof. 14.          Occupation certificate Not obtained 15.          Offer of possession Not offered The complainant filed an application u/s 36 seeking relief to restrain the respondent from cancelling the unit as he has already paid more than 85% of the total sale consideration. Further, the complainant sates that he is ready to pay Rs.3,33,027/- by way of an undated cheque. The counsel for the respondent states that unit is not yet cancelled and a reconcile account statement will be shared with the complainant within a week and the complaint is ready to make the payment of outstanding amount provided no amount shall be charged which is not the part of affordable housing policy.  Further, since about 90% of the basic price has already been paid and hence, the authority hereby issue interim directions for non-cancellation and non-creation of 3rd party rights till next date of hearing. Matter be put up on the date already fixed i.e. 05.09.2024 for further proceedings.

    Stage: FIRST HEARING