Meta Pixel
CNR: --
PENDING

HIMANI KHARE AND BHARAT KHARE vs OCEAN SEVEN BUILDTECH PVT. LTD.

Case NumberRERA-GRG-8025-2022
Date of Filing--
Case TypeRERA-GRG
Last Hearing19 Nov 2024
StateHaryana
CityGurgaon
Year of Filing2022

Party Details

Petitioner
  • HIMANI KHARE AND BHARAT KHARE
Respondent
  • OCEAN SEVEN BUILDTECH PVT. LTD.

Case Summary

HIMANI KHARE AND BHARAT KHARE filed Case No. RERA-GRG-8025-2022 in the Haryana Real Estate Regulatory Authority (RERA) against OCEAN SEVEN BUILDTECH PVT. LTD.. The case has undergone 8 hearings over 1 year and 3 months. The case is currently pending. 14 orders have been issued in this matter.

Hearing History (8)

  • 19NOV 2024
    Hearing

    Judge: VIJAY KUMAR GOYAL ASHOK SANGWAN

    Order pronounced.   The counsel for the respondent states that  the construction of the project was delayed due to force majeure conditions  which were beyond the control of the company and while calculating the delayed possession charges, the zero period  on account of force majeure circumstances may be allowed as given in the  case of Shri Vardhman Buildcon Pvt. Ltd.  Further states that the DTCP has allowed 9 months grace period on account of Covid-19 which may  also be allowed. The Authority observes that the facts of the above mentioned case do not relate to the present matter and no such zero period on account of force majeure circumstances is allowed by the DTCP Haryana. In view of the above, the  respondent/promoter is directed to pay interest to the complainant(s) against the paid-up amount at the prescribed rate of 11.10% p.a. for every month of delay from the due date of possession i.e., 30.05.2022 till valid offer of possession plus 2 months after obtaining occupation certificate from the competent authority or actual handing over of possession, whichever is earlier, as per section 18(1) of the Act of 2016 read with rule 15 of the rules. Other reliefs shall be part of the main order. Detailed order will follow. Matter stands disposed off.

    Stage: DISPOSED

  • 17SEP 2024
    Hearing

    Judge: VIJAY KUMAR GOYAL ASHOK SANGWAN

    The present complaint was filed on 20.01.2023 and the reply on behalf of the respondent was received on 06.02.2024. On 28.05.2024, the respondent was directed to not to create any third party rights against the allotted unit of the complainants till further order was restrained. The succinct facts of the case are as under: Sr. No. Particulars Details 1. Name of the project Expressway Towers, Sector 109, Gurugram, Haryana. 2. Project area 7.5 Acres 3. Nature of the project Affordable housing project 4. DTCP license no. 06 of 2016 dated 16.06.2016 License valid till 15.06.2021 Licensed area 7.5 acres License holder Sh. Shree Bhagwan C/o M/s Ocean Seven Buildtech Pvt. Ltd. 5. HRERA registered/ not registered Registered vide no. 301 of 2017 dated 13.10.2017 HRERA registration valid up to 12.04.2022 (Including 6 months COVID extension) 6. Building plan approval dated 26.09.2016 7. Environment clearance dated 30.11.2017 8. Allotment letter issued in favour of complainant on 21.09.2017 [Page 17 of complaint] 9. Unit no. 1707, 17th floor, Tower 4 (Page 24 of complaint)  10. Unit admeasuring 645 sq. ft. of carpet area along with 99 sq. ft. of balcony area [Page 24 of the complaint] 11. Builder buyer agreement 28.09.2017 [Page 19 of complaint] 12. Possession clause as per clause 5.2 of the agreement The Company shall sincerely endeavour to complete the construction and offer the possession of the said unit within five years from the date of the receiving of license (“Commitment Period”), but subject to force majeure clause of this Agreement and timely payment of installments by the Allottee(s), However In case the Company completes the construction prior to the period of 5 years the Allottee shall not raise any objection in taking the possession after payment of remaining sale price and other charges stipulated in the Agreement to Sell. The Company, on obtaining certificate for occupation and use by the Competent Authorities shall hand over the said unit to the Allottee for his/her/their occupation and use, subject to the Allottee having complied with all the terms and conditions of the said Policy and Agreement to Sell and payments made as per Payment Plan. It is further agreed by the Allottee that the Developer shall not be liable for delay in completion of construction, in case of force majeure condition and/or the delay is caused due to non-completion of construction of said Complex/building/unit. In the event if a number Allottee(s) are not paying due installments on time or a number of Allottee(s) has withdrawn their application after allotment of unit or a number of units has been cancelled due to nonpayment of due installments or otherwise… [Page 31 of complaint] 13. Possession clause 1(IV) of the Affordable Housing Policy, 2013 All such projects shall be required to be necessarily completed within 4 years from the approval of building plans or grant of environmental clearance, whichever is later. This date shall be referred to as the “date of commencement of project” for the purpose of this policy. The licenses shall not be renewed beyond the said 4 years period from the date of commencement of project. 14. Due date of possession 30.05.2022 (calculated from the date of environment clearance dated 30.11.2017 being later + 6 months as per HARERA notification no. 9/3-2020 dated 26.05.2020 for the projects having completion date on or after 25.03.2020) 15. Total consideration  Rs.26,29,500/- [As per clause 4.1 of the BBA at page 24 of complaint] 16. Amount paid by the complainant Rs.27,60,325/- [As alleged by the complainant at page 15 of complaint]    17. Occupation certificate Not obtained 18. Offer of possession Not offered   The due date for handing over of possession was 30.05.2022 including 6 months  grace period on account of Covid – 19 pandemic.  However,  OC for the project has not been received till date. Therefore,   the complainant is seeking delayed possession charges with direction to hand over possession after obtaining OC.  The counsel for the respondent states that the project was delayed due to force majeure causes including Covid – 19 pandemic and orders of various authorities. Further,  the licence of the respondent has been suspended w.e.f  25.03.2023.  Therefore,  the period beyond 25.03.2023 may be considered as a zero period.  Further four years period for completion of project may be counted from date of consent to establish which was granted only on 18.02.2018.  The counsel for the complainant  is seeking relief  in terms of detailed order already passed by the Authority in CR No.7964/2022  and 14 others. Arguments heard. Both the parties may file brief written submissions within 15 days with an advance copy to each other. Order reserved. Matter to come up on 19.11.2024 for pronouncement of order.

    Stage: RESERVED

  • 28MAY 2024
    Hearing

    Judge: ARUN KUMAR VIJAY KUMAR GOYAL SANJEEV KUMAR ARORA

    The present complaint was filed on 20.01.2023 and the reply on behalf of the respondent was received on 06.02.2024. The proxy counsel for the respondent requests for an adjournment due to non availability of the main arguing counsel. Request is allowed. The counsel for the complainant requests for directions to not create any third party rights in respect of the unit as more than 80%  of the total consideration amount as per BBA has been paid. In view of the same,  creation of any third party rights till further order is hereby restrained. Matter to come up on 17.09.2024 for further proceedings.

    Stage: PENDING

  • 20FEB 2024
    Hearing

    Judge: HARISH GUPTA

    As per the previous order dated 06.02.2024, the respondent was directed to pay the previous cost of Rs. 5000/- failing which reply filed by the respondent shall not be read over and in that eventuality defence of respondent shall be struck off. Cost of Rs. 5000/- not paid by the respondent. Perusal of the case file duly reveals that after filing complaint on 24.01.2023 initial notice was issued to the respondent by the registry and on 25.10.2023 Power of Attorney on behalf of respondent was filed in the registry and since then case was fixed for filing reply subject to cost of Rs. 5000/- (till 06.02.2024). On 06.02.2024 respondent was allowed to file reply in the registry on the undertaking (in this case and other 8 connected cases) given by the learned counsel for respondent to pay cost on next date of hearing i.e. on 20.02.2024. Despite the undertaking given on 06.02.2024, respondent not paid previous cost of Rs. 5000/- to the reasons best known to the respondent. As the respondent is not adhering to the undertaking and order dated 06.02.2024 so reply filed by the respondent is not to be read over and accordingly the defence of respondent is hereby struck off. Now the matter is listed before the authority on 28.05.2024 for final arguments.

    Stage: PENDING

  • 6FEB 2024
    Hearing

    Judge: HARISH GUPTA

    Despite the stipulated period given in the order dated 21.11.2023 respondent neither filed reply nor paid cost. Learned counsel for respondent requesting for allowing her to file reply on behalf of respondent in the registry today itself and to grant further opportunity for payment of cost. At this stage, learned counsel for respondent also filed undertaking for payment of cost (in this case and other 8 connected cases). Heard. In the interest of justice, complainant is allowed to file reply in the registry today and accordingly reply filed in the registry which is taken on record. Copy of reply also supplied to the learned counsel for the complainant. Now the case is adjourned for 20.02.2024 for payment of previous cost of Rs. 5000/- by the respondent failing which reply filed by the respondent shall not be read over and in that eventuality defence of respondent shall be struck off.

    Stage: PENDING

  • 21NOV 2023
    Hearing

    Judge: VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA

    The counsel for the respondent has put in appearance and handed over a copy of reply to the counsel for the complainant during proceedings and  requests for filing the same in the registry of the Authority within 2 days.  The respondent is directed to file reply in the registry of the Authority within two days alongwith costs of Rs. 5000/- to be paid to the complainant failing which the defence of the respondent may be struck off. Matter to come up on 06.02.2024 for further proceedings.

    Stage: PENDING

  • 25OCT 2023
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The counsel on behalf on the respondent/builder has filed an application along with power of attorney on 04.09.2023 that he should  be allowed to submit reply in all such complaints in which order of publication have been issued by the authority on 26.07.2023, 28.07.2023 and 11.08.2023 which are fixed for hearing on 25.10.2023, 20.10.2023 and 10.11.2023. The said request was approved by the Authority.   After due consideration of  the request of the counsel for the respondent and power of attorney filed by him, the matter is being referred to full bench  to be heard on  21.11.2023  as there are lot of litigations involved in this project and  a full bench view is required. It is also directed that Director/authorized representative of the respondent company should also appear alongwith the counsel on the next date of hearing. In case the counsel for the respondent does not file the reply before the next date of hearing, defence of the respondent shall be struck off and matter shall be proceeded on merits and documents already held on record. Matter to come up on 21.11.2023  at 3-00 PM before full bench for further proceedings.

    Stage: PENDING

  • 26JUL 2023
    Hearing

    Judge: ASHOK SANGWAN

    Case has been called out, but no one has appeared on behalf of the respondent.  Written reply not filed by the respondent.  Hence a public notice for respondent be issued in the newspaper by the registry of the Authority at the cost of the complainant.  The registry is directed to publish public notice in the newspaper for appearance of the respondent and for filing of reply.  The publication expenses shall be borne by the complainant.  Matter to come up on 25.10.2023 for further proceedings.

    Stage: FIRST HEARING

Orders (14)