Meta Pixel
CNR: --
PENDING

SPAZE TOWERS PVT LTD vs ARCHANA KUMARI

Case NumberRERA-GRG-4535-2023
Date of Filing--
Case TypeRERA-GRG
Last Hearing21 Aug 2024
StateHaryana
CityGurgaon
Year of Filing2023

Party Details

Petitioner
  • SPAZE TOWERS PVT LTD
Respondent
  • ARCHANA KUMARI

Case Summary

SPAZE TOWERS PVT LTD filed Case No. RERA-GRG-4535-2023 in the Haryana Real Estate Regulatory Authority (RERA) against ARCHANA KUMARI. The case has undergone 4 hearings over 7 months. The case is currently pending. 6 orders have been issued in this matter.

Hearing History (4)

  • 21AUG 2024
    Hearing

    Judge: ASHOK SANGWAN

    The counsel for the complainant-promoter has filed an application dated 09.08.2024  for withdrawal of complaint as the complainant-promoter being the dominus litis does not wish to continue further. In view of the application dated 09.08.2024, the present complaint stands dismissed as withdrawn. File be consigned to the registry.

    Stage: DISMISSED

  • 10JUL 2024
    Hearing

    Judge: ASHOK SANGWAN

    The present complaint was filed on 25.09.2023 and the reply on behalf of respondent was received on 08.01.2024.   Sr. No. Particulars Details Name of the project “Spaze Tristaar”, Sector 92, Gurugram, Haryana. 2.       Project area 2.718 acres 3.       Nature of the project Commercial 4.       DTCP license no. and validity status 72 of 2013 dated 27.07.2013 valid upto 26.07.2017 5.       Name of licensee Spaze Towers Pvt Ltd 6.       RERA Registered/not registered Registered 247 of 2017 dated 26.09.2017 valid upto 30.06.2020 Application dated 28.12.2020 filed for extension of registration 7.       Allotment Letter 22.08.2014 (Page 34 of complaint) 8.       BBA 25.09.2017 (Page 36 of complaint) Unit no. 0053, Ground Floor (Page 46 of complaint) 10.              Unit Area Super Area- 305 sq. ft. (Page 46 of complaint) Possession clause Clause 11(a) “The Developer based on its present plans and estimates and subject to all just exceptions endeavours to complete construction of the Said Building/Said Unit in terms of the approvals (including the renewal/extended period described therein) and in accordance with the terms of this Agreement unless there shall be delay or failure due to department delay or due to any circumstances beyond the power and control of the Developer or Force Majeure conditions including but not limited to reasons mentioned in clause 11(b) and 11(c) or due to failure of the Allottee(s) to pay in time the Total Consideration or any part thereof and other charges and dues/payments mentioned in this Agreement or any failure on the part of the Allottee(s) to abide by all or any of the terms and conditions of this Agreement. In case there is any delay on the part of the Allottee(s) in making of payments to the Developer then notwithstanding rights available to the Developer elsewhere in this Agreement, the period for implementation of the project shall also be extended by a span of time equivalent to each delay on the part of the Allottee(s) in remitting payment(s) to the Developer.” Due date of possession To be ascertained As per the complainant- 30.12.2020 since the validity of registration certificate was upto 30.06.2020 which was extended upto 30.12.2020 Or 25.09.2020 Calculated to be 3 years from date of BBA in terms of Fortune Infrastructure and Ors. vs. Trevor D'Lima and Ors. (12.03.2018 - SC); MANU/SC/0253/2018 Total sale consideration Rs. 46,95,173/- (SOA at page 98 of complaint) Total amount paid by the complainant Rs. 38,18,909/- (SOA at page 98 of complaint) 15.              Application for grant of occupation certificate 13.10.2020 Occupation certificate 03.05.2021 (Page 112 of complaint) Offer of possession 05.05.2021 (Page 115 of complaint)   The complainant is seeking following relief -: 1. To direct the respondent to pay the outstanding dues of Rs. 11,82,417/-(calculated till 31.08.2023) and direct that the payment of interest shall keep on accruing till the actual payment of the outstanding amount. 2. To direct the respondent to take the possession of the unit and get the conveyance deed registered, after paying the outstanding dues. 3. To direct the allottee to pay maintenance charges from date of offer of possession. The husband representing the respondent-allottee  states that the complainant-promoter arbitrarily amended the layout plan of the project  on 13.11.2018 in contravention of Section 14 of the Act, 2016  and shifted the unit of the allottee from 2nd position from the front to 5th position  and further added more units into the project.  Therefore,  the respondent allottee asked for refund on 04.05.2019 (page 12 of the reply).  No response was received on this communication.  He states that the allottee does not wish to remain in the project and seeks refund of the complete amount with interest at the prescribed rate.   The counsel for the complainant-promoter states that  the respondent allottee had objected to the increase area and electrification charges only. So far as change in the building plan is concerned,  there is no change in the location of the unit of the respondent allottee. So far as compliance of Section 14 of the Act is concerned the counsel for the complainant promoter states that objections were invited from the allottees on 16.11.2018 in compliance with the procedure of DTCP. Arguments heard. Order reserved. Meanwhile both the parties may file written submissions within 15 days with an advance copy to each other. Matter to come up on 21.08.2024 for pronouncement of order.

    Stage: RESERVED

  • 27MAR 2024
    Hearing

    Judge: ASHOK SANGWAN

    The present complaint was filed on 25.09.2023 and the reply on behalf of respondent no. 1 was received on 08.01.2024. The husband of the respondent has raised the following objections:- i)                  Change in location of the unit ii)               Increase in super area without any increase in the carpet area iii)             BBA was signed after taking 60% of the sale consideration The complainant is directed to submit original layout plans of the project as well as revised layout plans of the project within a period of 2 weeks with an advance copy to the respondent and also to clarify as to whether the provisions of section 14 (2) of the Act were followed while revising the layout plans. Matter to come up on 10.07.2024 for further proceedings.

    Stage: PENDING

  • 3JAN 2024
    Hearing

    Judge: SANJEEV KUMAR ARORA

    The present complaint was filed on 25.09.2023 and registered as complaint No. 4535/2023. As per the registry, complainant has sent copy of complaint along with annexures through speed post as well as through email and proof regarding having the delivery of the complaint along with annexures made to the respondent has been submitted by the complainant as available in the file.  The registry of the authority sent a notice with a copy of the complaint along with annexures through speed post as per record available in the file.  Registry has also sent the notice along with a copy of the complaint through email at following email address:  [email protected] and the same is shown to has been delivered on the above email address as per the report available in the file.  It is proper service of the notice. However, no reply has been received on behalf of the respondent to date. None present on behalf of the respondent-allottee.     One last opportunity to file the reply is being given to the respondent otherwise defence of the respondent-allottee shall be struck off.  The respondent is directed to file a reply within two weeks in the registry with an advance copy to the complainants.     Matter to come up on 27.3.2024 for further  proceedings

    Stage: FIRST HEARING

Orders (6)