GUVNL vs Shree Narmada Khand Udyog Sahakari Mandli Limited
- GUVNL
- Shree Narmada Khand Udyog Sahakari Mandli Limited
The case GUVNL vs Shree Narmada Khand Udyog Sahakari Mandli Limited.
The case is filed in the Gujarat Electricity Regulatory Commission (Case No. 2262/2023).
The current case status is pending, last heard on 22 Dec 2023. Next hearing is scheduled for 17 Mar 2026.
Judge: N/A
In the matter of Petition for approval of Power Purchase Agreement executed between Shree Narmada Khand Udyog Sahakari Mandli Limited and GUVNL for Procurement of 15 MW Power during crushing season and 0 MW power during non-crushing season from their 30 MW Bagasse based co-generation project under Order No. 03 of 2022 dated 27.06.2022 issued by the Commission for “Determination of Tariff for Procurement of Power by the Distribution Licensees and Others from Biomass based Power Projects and Bagasse based Co-generation Projects”, for Control Period from FY 2020-21 to FY 2022-23 in the State of Gujarat.
Judge: N/A
In the matter of filing petition for approval of Power Purchase Agreement executed between Shree Narmada Khand Udyog Sahakari Mandli Limited and GUVNL for Procurement of 15 MW Power during crushing season and 0 MW power during non-crushing season from their 30 MW Bagasse based co-generation project under Order No. 03 of 2022 dated 27.06.2022 issued by the Commission for “Determination of Tariff for Procurement of Power by the Distribution Licensees and Others from Biomass based Power Projects and Bagasse based Co-generation Projects”, for Control Period from FY 2020-21 to FY 2022-23 in the State of Gujarat.