Green Peak Realty vs Smt. Karabi Mitra
Party Details
- Green Peak Realty
- Smt. kalpana kar
- Smt. Sesha Kar
- Smt. Karabi Mitra
Case Summary
Green Peak Realty filed Case No. A/833/2015 in the Consumer Court on 29 Jul 2015 against Smt. kalpana kar and Smt. Sesha Kar. The case has undergone 8 hearings over 2 years and 1 month. The case is currently pending. 8 orders have been issued in this matter.
Hearing History (8)
- 22SEP 2017Hearing
Judge: N/A
Stage: DISPOSED OFF
- 23AUG 2017Hearing
Judge: N/A
Stage: JUDGEMENT RESERVED
- 4JUL 2017Hearing
Judge: N/A
Stage: FINAL HEARING
Orders (8)
- 22SEP 2017judgement
Order No: N/A
- 23AUG 2017order
Order No: N/A
- 4JUL 2017order
Order No: N/A
Judgement Details
Cause Title/Judgement-Entry STATE CONSUMER DISPUTES REDRESSAL COMMISSION WEST BENGAL 11A, Mirza Ghalib Street, Kolkata - 700087 First Appeal No.
A/833/2015 (Arisen out of Order Dated 17/11/2014 in Case No.
CC/529/2013 of District North 24 Parganas) 1.
Green Peak Realty A Proprietorship Firm , 3/16, New Town Avenue, B Zone, Durgapur, Pin - 713 205, rep. by, its Proprietor, Mr.
Sumant Kerketta, S/o, Sri Suren Kerketta, May Fair Tarun Apartment, 4th Floor, 9/5, Feeder Road, P.S - Titagarh, P.O - Barrackpore, Kolkata - 700 123, Dist - North 24 Pgs. ...........Appellant(s) Versus 1.
Smt.
Karabi Mitra W/o, Sri Goutam Mitra, Snehalata Apartment, Flat No. - 103, Ist Floor, 3, Siddheswari Tala Road, Monirampur, Majumdermath, P.O & P.S - Barrackpore, Kolkata - 700 120, Dist - North 24 Pgs.
2.
Smt. kalpana kar W/o, Sri Pradip Kar, Flat No. - 102, Ist Floor, Snehalata Apartment, 3, Siddheswari Tala Road, Monirampur, Majumdarmath, P.O & P.S - Barrackpore, Kolkata - 700 120, Dist - North 24 Pgs.
3.
Sesha Kar W/o, Lt.
Taradas Kar, Flat No. - 202, II Floor, Snehalata Apartment, 3, Siddheswari Tala Road, Monirampur, Majumdarmath, P.O & P.S - Barrackpore, Kolkata - 700 120. ...........Respondent(s) BEFORE: HON'BLE MR.
JUSTICE ISHAN CHANDRA DAS PRESIDENT HON'BLE MR.
TARAPADA GANGOPADHYAY MEMBER For the Appellant: Abu Sayem Mr.
Dibyendu Sengupta , Advocate For the Respondent: Mr.
Sankar Kumar Chanda, Advocate Mr.
Biswajit Chattopadhyay, Advocate Dated : 22 Sep 2017 Final Order / Judgement HON’BLE JUSTICE ISHAN CHANDRA DAS, PRESIDENT This appeal has been preferred against the judgment and order dated 17-11-2014 passed by Ld.
DCDRF, 24-Paganas,(North) in CC/529/2013 where Ld.
Forum concerned while disposing of the complaint case allowed the same on contest with cost of Rs.
5,000/- (Rupees five thousand) to be paid by the OP no. the OP no.
3 to the complainant within one month from the date of the order, directed the Opposite Parties to execute the deed of conveyance in respect of the disputed flat within a month, to handover possession of the flat with completion certificate, directed the OP no.
3 to pay Rs.
10,000/- (Rupees ten thousand) towards compensation and in default to pay punitive damages @ Rs.
100/- per day till realization etc.
Being aggrieved by and dissatisfied with the said judgment and order dated 17-11-2014, the present appeal has been preferred by the OP no.
3 of the complaint case i.e.
Green Peak Realty.
Briefly stated, the case of the complainant, was that she entered into an agreement to purchase a flat measuring 725 sq. ft. including super built up area with the appellant/OP no.
3 (hereinafter referred to as OP no.
3 for convenience) who, on the basis of a general power of attorney, being executed by the OPs no.
1 and 2 in favour of the said OP no.
3 became the developer cum promoter of the plot.
The consideration of the flat was Rs.
9,42,500/- (Rupees nine lakh forty two thousand five hundred) but the actual area of the flat was 614.4 sq. ft. and hence the actual amount of consideration would be Rs.
7,98,720/- (Rupees seven lakh ninety eight thousand seven hundred twenty).
The complainant paid a sum of Rs.
3,50,000/- (Rupees three lakh fifty thousand) as advance, on proper receipt, out of Rs.
Rs.
9,42,000/- (Rupees nine lakh forty two thousand) as total consideration.
Thereafter the complainant paid certain amounts through cheques and the amount of Rs.
7,50,000/- (Rupees seven lakh fifty thousand) was already paid to the OPs out of actual consideration of Rs.
On receipt of major part of consideration the OP no.
3, handed over possession of the flat without the document for possession but in unfinished condition.
The OP no.
3 being the developer of the plot violated the sanctioned master plan of the entire building.
The OP who was under contractual obligation was lacking in connection with supply of completion certificate due to the fact that the developer did not construct boundary wall, boundary gate, unfinished staircase, unfinished electric wiring, water connection from Municipal supply, common parking space etc.
It is the case of the complainant that out of total consideration of Rs.
9,42,500/- (Rupees nine lakh forty two thousand five hundred) she already paid Rs.
7,50,000/- (Rupees seven lakh fifty thousand) against 614.04 sq. ft. super built up area and Rs.
48,720/- (Rupees forty eight thousand seven hundred twenty) was due, to be paid to the OPs.
The complainant requested the OPs to execute and register the deed of conveyance in her favour on acceptance of the said amount (Rs.
48,720/-) but the OPs did not respond, for which the complainant had to take recourse of the local municipal authority but no result yielded, save and except usual undertaking by the OP to execute and register such deed.
A legal notice through authorized Advocate was sent to the opposite parties for which a fresh legal notice dated 14-05-2013 was served by Advocate Rabindranath Bhattacharya, requesting the OPs to obey the terms of the said deed of “Agreement for sale” dated 07-02-2011, to be accompanied by completion certificate, letter of possession etc. within the stipulated period which were not handed over for which the complainant prayed for compensation for monitory loss, mental agony etc.
The complainant also stated that as per proper calculation of the value to the tune of Rs.
110.6 X 1300 sq. ft. = Rs.
1,43,780/- (Rupees one lakh forty three thousand seven hundred eighty) should be deducted from the total consideration, payable to the OPs and on the strength of the averments as contained in the petition of complaint certain reliefs have been prayed for.
The OPs no. he OPs no.
1 and 2 filed a joint written version where as the OP no.
3/appellant filed a separate written version and all of them contended that the complaint case was not maintainable against them.
Denying the cause of action, as averred in the body of the petition of complaint, the OPs, contesting the complaint case, categorically averred that the complaint case filed was a speculative one.
Disputing the area of the flat, as averred in the petition of complainant, an order of dismissal of the instant complaint case was prayed for.
Upon rival pleadings of the parties and on consideration of materials on record, Ld.
Trial Forum allowed the complaint case on merit and passed the order impugned, as referred to in the earlier part of the judgment.
Now the point for consideration is whether Ld.
Trial Forum was justified in passing the order impugned.
Here the agreement between the parties with regard to purchase of a flat, referred to in the schedule of the petition of complaint of CC/529/2013 as per agreement dated 07-02-2011 is not disputed.
The consideration of such flat measuring 725 sq. ft. on the 1st floor of the building at a consideration of Rs.
9,42,500/- (Rupees nine lakh forty two thousand five hundred) are admitted by the parties out of which the complainant already paid a sum of Rs.
7,50,000/- (Rupees seven lakh fifty thusand) to the OP no.
3 on proper receipts.
The complainant alleged that the actual super built up area of the said flat was 614.4 sq. ft. whereas the OP no.
3/appellant stated that the same as 615 sq. ft. instead of 725 sq. ft. as specified in the agreement for sale.
The developer i.e. the appellant herein admitted that a total consideration of Rs.
1,43,000/- (Rupees one lakh forty three thousand would be refundable due to shortage of the area of 110 sq. ft., more or less.
It was argued before us that a sum of Rs.
1,06,429/- (Rupees one lakh six thousand four hundred twenty nine) was to be payable by the complainant to the OP no. the OP no.
3 for extra works done by the OP/appellant, including installation of main electric line, transformer and polls etc. and the balance amount is to be recoverable to the complainant.
It is already noted that the complainant would be entitled to Rs.
1,43,000/- (Rupees one lakh forty three thousand) due to shortage of accommodation in the flat measuring about 110 sq. ft. and the appellant was entitled to recover a sum of Rs.
1,06,429/- (Rupees one lakh six thousand four hundred twenty nine) for the extra works done by him for the respondent no.
1.
In the judgment impugned Ld.
Trial Forum failed to calculate the balance amount to be recoverable from the appellant and disposed of the complaint case when there was a pending transaction between the parties who are before us for dissolution of their pending litigation, one of them should not be blamed alone since there was joint responsibility for the parties to the proceeding to resolve their dispute, as per terms of agreement.
Hence, we dispose of the appeal by affirming the order passed by Ld.
Forum concerned subject to modifications as noted below.
The OPs of CC/529/2013 (i.e. the appellant as well as the respondents 2 and 3) are directed to execute and register the deed of conveyance in respect of the flat in question to the complainant/respondent no.
1 within a period of 90 days from the date of the order, the cost of registration shall be borne by the complainant herself and she will be entitled to Rs.
36,571/- (Rupees thirty six thousand five hundred seventy one) which is lying with the OP no.
3 after deduction as specified earlier.
The complainant/respondent no.
1 would be entitled to said Rs.
36,571/- (Rupees thirty six thousand five hundred seventy one) from the appellant, who is directed to pay the same to the respondent no.
1 within 90 days from the date of the order.
The appellant being the OP no.
3 of the complaint case no. t case no.
CC/529/13 is absolved from his liability to pay other charges like cost of litigation and for mental agony and harassment coupled with punitive damages as directed by Ld.
Trial Forum therein in the peculiar facts of the case.
Parties do bear their respective costs of Appeal. [HON'BLE MR.
JUSTICE ISHAN CHANDRA DAS] PRESIDENT [HON'BLE MR.
TARAPADA GANGOPADHYAY] MEMBER