Meta Pixel
CNR: --
PENDING

Himachal Pradesh State Electricity Board Limited vs Neri Hydro Projects Pvt. Ltd.(R-1)

Case NumberAPL
Date of Filing22 Dec 2022
Case TypeAPL
Last Hearing3 May 2024
State--
City--
Year of Filing--

Party Details

Petitioner
  • Himachal Pradesh State Electricity Board Limited
Respondent
  • Neri Hydro Projects Pvt. Ltd.(R-1)
  • Himachal Pradesh Electricity Regulatory Commission (R-5)

Case Summary

Himachal Pradesh State Electricity Board Limited filed Case No. APL in the APTEL on 22 Dec 2022 against Neri Hydro Projects Pvt. Ltd.(R-1) and Himachal Pradesh Electricity Regulatory Commission (R-5). The case has undergone 10 hearings over 1 year and 2 months. The case is currently pending. 14 orders have been issued in this matter.

Hearing History (10)

  • 3MAY 2024
    Hearing

    Judge: N/A

  • 26SEP 2023
    Hearing

    Judge: N/A

  • 21AUG 2023
    Hearing

    Judge: N/A

  • 14AUG 2023
    Hearing

    Judge: N/A

  • 12MAY 2023
    Hearing

    Judge: N/A

  • 20APR 2023
    Hearing

    Judge: N/A

  • 3APR 2023
    Hearing

    Judge: N/A

  • 13MAR 2023
    Hearing

    Judge: N/A

  • 6FEB 2023
    Hearing

    Judge: N/A

  • Hearing

    Judge: N/A

Orders (14)